Judgment of the Court (Fifth Chamber)5 April 2017note(Reference for a preliminary ruling — Public procurement — Directive 2004/17/EC — Contract not reaching the threshold laid down by that directive — Articles 49 and 56 TFEU — Limit on reliance on subcontracting — Submission of a common tender — Professional capacities of the tenderers — Changes to the tender specifications)In Case C‑298/15,REQUEST for a preliminary ruling under Article 267 TFEU from the Lietuvos Aukščiausiasis Teismas (Supreme Court, Lithuania), made by decision of 12 June 2015, received at the Court on 18 June 2015, in the proceedings‘Borta’ UABvKlaipėdos valstybinio jūrų uosto direkcija VĮ,THE COURT (Fifth Chamber),composed of J.L. da Cruz Vilaça, President of the Chamber, A. Tizzano (Rapporteur), Vice-President de la Cour, A. Borg Barthet, E. Levits and F. Biltgen, Judges,Advocate General: E. Sharpston,Registrar: M. Aleksejev, Administrator,having regard to the written procedure and further to the hearing on 1 June 2016, after considering the observations submitted on behalf of:— ‘Borta’ UAB, by V. Kilišauskaitė, advokatė,— Klaipėdos valstybinio jūrų uosto direkcija VĮ, by N. Šilaika, advokatas, and by A. Vaitkus, A. Kamarauskas, I. Vaičiulis and L. Rudys,— the Lithuanian Government, by D. Kriaučiūnas and by A. Svinkūnaitė and R. Butvydytė, acting as Agents,— the European Commission, by J. Jokubauskaitė and A. Tokár, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 1 December 2016,gives the following
Judgment
Legal context
EU law
Lithuanian law
Lithuanian Law on public procurement
The tender specifications at issue in the main proceedings
The dispute in the main proceedings and the questions referred for a preliminary ruling
Consideration of the questions referred
Preliminary observations
Question 1(a)
The second question
Question 1(b)
Costs
Operative part