34Nevertheless, where the procurement documents require tenderers to indicate, in their tenders, the share of the contract they may intend to subcontract and the proposed subcontractors, in accordance with the first paragraph of Article 25 of Directive 2004/18, the contracting authority is entitled to prohibit use of subcontractors whose capacities could not be verified at the level of examination of tenders and selection of the contractor, for the performance of essential parts of the contract (see, to that effect, judgment of 18 March 2004 in Siemens and ARGE Telekom, C‑314/01, EU:C:2004:159, paragraph 45).