23Thus, the Court has held that the subject matter of each contract and the criteria governing its award must be clearly defined from the beginning of the award procedure (judgment of 10 May 2012 in Commission v Netherlands, C‑368/10, EU:C:2012:284, paragraph 56) and that a contracting authority cannot apply, by way of award criteria, sub-criteria which it has not previously brought to the tenderers’ attention (judgment of 21 July 2011 in Evropaïki Dynamiki v EMSA, C‑252/10 P, not published, EU:C:2011:512, paragraph 31). Similarly, the contracting authority must interpret the award criteria in the same way throughout the procedure (judgment of 18 October 2001 in SIAC Construction, C‑19/00, EU:C:2001:553, paragraph 43 and the case-law cited).