83In order to answer that question, it must be recalled, as a preliminary point, that, according to settled case-law, the applicable directive is, as a rule, the one in force when the contracting authority chooses the type of procedure to be followed and decides definitively whether it is necessary for a prior call for competition to be issued for the award of a public contract. Conversely, a directive is not applicable if the period prescribed for its transposition expired after that point in time (judgment in Impresa Pizzarotti , C‑213/13, EU;C:2014:2067, paragraph 31 and the case-law cited).