Judgment of the Court (Third Chamber)26 January 2023note(Reference for a preliminary ruling — Article 267 TFEU — Definition of court or tribunal of a Member State — Criteria — Independence and compulsory nature of the jurisdiction of the national body concerned — Stability of the members of that body — Directive 2014/24/EU — Public procurement procedures — Article 58 — Selection criteria — Possibility of including, amongst those criteria, obligations under special laws applicable to the activities connected with the contract in question and not set out as a criterion for selection in the procurement documents — Article 63(1) — Tenderer relying on the capacities of another entity in order to meet the requirements of the contracting authority — Not possible to require recourse to subcontracting)In Case C‑403/21,REQUEST for a preliminary ruling under Article 267 TFEU from the Consiliul Naţional de Soluţionare a Contestaţiilor (National Council for the Resolution of Disputes, Romania), made by decision of 22 June 2021, received at the Court on 29 June 2021, in the proceedingsSC NV Construct SRLvJudețul Timișintervening party:SC Proiect – Construct Regiunea Transilvania SRL,THE COURT (Third Chamber),composed of K. Jürimäe, President of the Chamber, M. Safjan, N. Piçarra, N. Jääskinen and M. Gavalec (Rapporteur), Judges,Advocate General: M. Campos Sánchez-Bordona,Registrar: A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:– the Czech Government, by M. Smolek and J. Vláčil, acting as Agents,– the European Commission, by P. Ondrůšek, E.A. Stamate and G. Wils, acting as Agents,having decided, after hearing the Advocate General, to proceed to judgment without an Opinion,gives the following
Judgment
Legal context
European Union law
Directive 89/665/EEC
Directive 2014/24
Romanian law
Law No 101/2016
The Rules of Procedure of the Consiliul Naţional de Soluţionare a Contestaţiilor (National Council for the Resolution of Disputes, Romania)
The Administrative code
The Law on public procurement
The dispute in the main proceedings and the questions referred for a preliminary ruling
Admissibility of the request for a preliminary ruling
Consideration of the questions referred
The first question
The second question
The third question, point (a)
The third question, point (b)
Costs
Operative part