89In that regard, it must be noted that compliance with the conditions for the performance of a contract is not to be assessed when a contract is awarded. It follows that, if the requirement at issue in the main proceedings were classified as a performance condition and if the successful tenderer did not satisfy it when the public contract was awarded to it, the non-compliance with that condition would have no effect on the question whether the award of the contract to the Consortium was compatible with the provisions of Directive 2014/24.