Contents
Judgment of the Court (Fourth Chamber)3 October 2019note(Reference for a preliminary ruling — Public Procurement — Public procurement procedure — Directive 2014/24/EU — Article 57(4) — Optional grounds for exclusion — Exclusion of an economic operator from participating in a public procurement procedure — Early termination of a prior contract on account of partial subcontracting — Concept of significant or persistent deficiencies — Scope)In Case C‑267/18,REQUEST for a preliminary ruling under Article 267 TFEU from the Curtea de Apel Bucureşti (Court of Appeal, Bucharest, Romania), made by decision of 2 April 2018, received at the Court on 17 April 2018, in the proceedingsDelta Antrepriză de Construcţii şi Montaj 93 SAvCompania Naţională de Administrare a Infrastructurii Rutiere SA,THE COURT (Fourth Chamber),composed of M. Vilaras, President of the Chamber, K. Jürimäe, D. Šváby (Rapporteur), S. Rodin and N. Piçarra, Judges,Advocate General: M. Campos Sánchez-Bordona,Registrar: R. Şereş, administrator,having regard to the written procedure and further to the hearing on 27 February 2019,after considering the observations submitted on behalf of:– Delta Antrepriză de Construcţii şi Montaj 93 SA, by I.G. Iacob, R.E. Cîrlig, I. Cojocaru, A.M. Abrudan and I. Macovei, avocaţi,– the Romanian Government, by C.-R. Canţăr and by R.I. Haţieganu and L. Liţu, acting as Agents,– the Austrian Government, by M. Fruhmann, acting as Agent,– the European Commission, by A. Biolan, P. Ondrůšek and L. Haasbeek, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 8 May 2019,gives the following
Judgment
Legal context
EU law
Directive 2014/24
Implementing Regulation (EU) 2016/7
Romanian law
The dispute in the main proceedings and the question referred for a preliminary ruling
Consideration of the question referred
Costs
Operative part
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.