Judgment of the Court (First Chamber)9 September 2020note(Reference for a preliminary ruling — Directive 92/43/EEC — Conservation of natural habitats and of wild fauna and flora — Article 6(3) — Scope — Concepts of project and agreement — Appropriate assessment of the implications of a plan or project for a protected site — Decision extending the duration of a development consent for the construction of a liquefied natural gas regasification terminal — Original decision based on national legislation which did not properly transposed Directive 92/43)In Case C‑254/19,REQUEST for a preliminary ruling under Article 267 TFEU from the High Court (Ireland) made by decision of 13 March 2019, received at the Court on 26 March 2019, in the proceedingsFriends of the Irish Environment LtdvAn Bord Pleanála,intervening party:Shannon Lng Ltd,THE COURT (First Chamber),composed of J.-C. Bonichot (Rapporteur), President of the Chamber, M. Safjan, L. Bay Larsen, C. Toader and N. Jääskinen, Judges,Advocate General: J. Kokott,Registrar: A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:– Friends of the Irish Environment Ltd, by F. Logue, Solicitor, J. Kenny, Barrister-at-Law, and J. Devlin, Senior Counsel,– An Bord Pleanála, by B. Magee, Solicitor, F. Valentine, Barrister-at-Law, and N. Butler, Senior Counsel,– the European Commission, by C. Hermes and M. Noll-Ehlers, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 30 April 2020,gives the following
Judgment
Legal context
European Union law
The Habitats Directive
The EIA Directive
Irish law
The dispute in the main proceedings and the questions referred for a preliminary ruling
Consideration of the questions referred
First and second questions referred
The third question
The fourth question
The fifth question
The sixth question
Costs
Operative part