Judgment of the General Court (Eighth Chamber, Extended Composition)2 February 2022note(Competition — Abuse of a dominant position — Gas markets of Central and Eastern Europe — Decision to make binding the individual commitments proposed by an undertaking — Article 9 of Regulation (EC) No 1/2003 — Whether the commitments are adequate in the light of the competition concerns initially identified in the statement of objections — Commission decision not to require commitments in relation to some of the initial concerns — Principle of sound administration — Transparency — Obligation to state reasons — Energy-policy objectives of the European Union — Principle of energy solidarity — Misuse of powers)In Case T‑616/18,Polskie Górnictwo Naftowe i Gazownictwo S.A., established in Warsaw (Poland), represented by K. Karasiewicz, radca prawny, T. Kaźmierczak, K. Kicun and P. Moskwa, lawyers,supported byRepublic of Lithuania, represented by K. Dieninis and R. Dzikovič, acting as Agents,byRepublic of Poland, represented by B. Majczyna and M. Nowacki, acting as Agents,and byOvergas Inc., established in Sofia (Bulgaria), represented by S. Gröss and S. Cappellari, lawyers,vEuropean Commission, represented by G. Meessen and J. Szczodrowski, acting as Agents,supported byGazprom PJSC, established in Moscow (Russia),andGazprom export LLC, established in St. Petersburg (Russia),represented by J. Karenfort, J. Hainz, B. Evtimov, N. Tuominen, J. Heithecker, lawyers, and D. O’Keeffe, Solicitor,THE GENERAL COURT (Eighth Chamber, Extended Composition),composed of M. van der Woude, President, J. Svenningsen (Rapporteur), R. Barents, C. Mac Eochaidh and T. Pynnä, Judges,Registrar: R. Ūkelytė, Administrator,Having regard to the written part of the procedure and further to the hearing on 18 and 19 May 2021,gives the following
Judgment
I.Background to the dispute and developments following the bringing of the action
A.The administrative procedure which gave rise to the contested decision
B.The contested decision
1.The preliminary assessment of the practices in question
2.The content of the final commitments
3.The assessment and implementation of the final commitments
C.The complaint
II.Procedure and forms of order sought by the parties
III.Law
A.The requests for measures of organisation of procedure
B.The first plea in law, alleging infringement of Article 9 of Regulation No 1/2003, read together with Article 102 TFEU, and breach of the principle of proportionality, in that the Commission committed a manifest error of assessment in considering that the Yamal objections had proved to be unfounded and in accepting commitments which did not in any way address those objections
1.The first part of the first plea, concerning the Commission’s errors as regards the abandonment of the Yamal objections and the absence of a commitment addressing those objections
(a)The complaint that the Commission was under an obligation to justify the absence of a commitment to address the Yamal objections
(b)The complaints challenging the validity of the two grounds set out in recital 138 of the contested decision
2.The second part of the first plea, concerning breach of the principles of sound administration, transparency and sincere cooperation
(a)Breach of the principles of sound administration and transparency
(b)Breach of the principle of sincere cooperation
C.The second plea in law, alleging infringement of Article 9 of Regulation No 1/2003, read together with Article 102 TFEU, and a breach of the principle of proportionality, in that the Commission accepted the final commitments even though they did not adequately address the objections concerning pricing practices
1.The first part of the second plea, concerning an error in the subject matter of the commitments relating to pricing practices in that they do not address the essence of the objections concerning those practices
2.The second part of the second plea, concerning the ineffectiveness of the new price review process
(a)The ineffectiveness of the commitments in view of Gazprom’s obstructive practices (first complaint)
(b)The failure of the commitments to address the competition concerns in good time (second complaint)
(c)The failure to take into account the costs of arbitration proceedings (third complaint)
(d)The inappropriateness of the limitation of the duration of the contracts (fourth complaint)
3.The third part of the second plea, concerning errors in the formulation of the pricing guidelines
(a)The absence of a hierarchy between the criteria used in the pricing guidelines and the vague nature of those guidelines (first complaint)
(b)The inappropriateness of the criterion relating to the price level at gas hubs (second complaint)
(c)The inappropriateness of average import prices in Germany, France and Italy (third complaint)
(d)The characteristics of the gas supplied under a given contract (fourth complaint)
(e)The elements not referred to in the pricing guidelines (fifth complaint)
4.The fourth part of the second plea, concerning errors of law and manifest errors of assessment as to the relationship between EU law and arbitration
(a)The application of substantive EU law in arbitration (first complaint)
(b)The possibility for the Commission to intervene as amicus curiae (second complaint)
D.The third plea in law, alleging infringement of Article 9 of Regulation No 1/2003, read together with Article 102 TFEU, and a breach of the principle of proportionality, in that the Commission accepted the final commitments even though they did not adequately address the objections concerning territorial restrictions
1.The first part of the third plea, concerning the inadequacy of the commitments relating to territorial restrictions taken as a whole
2.The second part of the third plea, concerning the inadequacy of the commitments relating to delivery points
(a)The insufficiency of the relevant delivery points (first complaint)
(b)The inadequacy of the service fees (second complaint)
(c)The inappropriate limitation on the duration of contracts (third complaint)
(d)The inappropriate requirement as to the minimum volume of gas (fourth complaint)
(e)Insufficient consideration of market conditions in Bulgaria (fifth complaint)
(f)Failure to take into account the likely and foreseeable development of Gazprom’s transit policy (sixth complaint)
3.The third part of the third plea, concerning the inadequacy of the commitments relating to the Bulgarian gas system
E.The fourth plea in law, alleging infringement of Article 194(1) TFEU, read together with Article 7 TFEU, in that the contested decision is contrary to the energy-policy objectives of the European Union in view of the negative impact of that decision on the European gas supply market
F.The fifth plea in law, alleging infringement of Article 18(1) TFEU and a breach of the principle of equal treatment, in that the Commission discriminated between Gazprom’s customers operating in the Western European Member States and those operating in the CEE countries concerned
G.The sixth plea in law, alleging misuse of powers and infringement of essential procedural requirements, in that, by the contested decision, the Commission disregarded the objective of Article 9 of Regulation No 1/2003 and the limits of its powers in the management of the administrative procedure
1.The facts characterising the conduct of the procedure in Case AT.39816
2.The irregularities committed in relation to the handling of the Yamal objections
3.Infringement of various procedural rights, or of essential procedural requirements, in the handling of the complaint
(a)The allegation that a separate procedure was improperly opened for the examination of the complaint (first infringement)
(b)Infringement of Article 5(1) and Article 6(1) of Regulation No 773/2004 (second and third infringements)
(c)Infringement of other procedural rights attached to the status of complainant (fourth infringement)
4.The existence of a misuse of powers
Costs
Operative part