Judgment of the Court (Seventh Chamber)27 June 2024note(Reference for a preliminary ruling — Environment — Directive 2009/28/EC — Article 1 — Article 3(3)(a) — Principles of legal certainty and the protection of legitimate expectations — Charter of Fundamental Rights of the European Union — Article 16 — Promotion of the use of energy from renewable sources — Alteration of the applicable support scheme — Grant of the aid concerned subject to the conclusion of contracts)In Case C‑148/23,REQUEST for a preliminary ruling under Article 267 TFEU from the Consiglio di Stato (Council of State, Italy), made by decision of 27 February 2023, received at the Court on 10 March 2023, in the proceedingsGestore dei Servizi Energetici SpA – GSEvErg Eolica Ginestra Srl,Erg Eolica Campania SpA,Erg Eolica Fossa del Lupo Srl,Erg Eolica Amaroni Srl,Erg Eolica Adriatica Srl,Erg Eolica San Vincenzo Srl,Erg Eolica San Circeo Srl,Erg Eolica Faeto Srl,Green Vicari Srl,Erg Wind Energy Srl,Erg Wind Sicilia 3 Srl,Erg Wind Sicilia 6 Srl,Erg Wind 4 Srl,Erg Wind 6 Srl,Erg Wind Sicilia 5 Srl,Erg Wind 2000 Srl,Erg Wind Sicilia 2 Srl,Erg Wind Sardegna Srl,Erg Wind Sicilia 4 Srl,Enel Hydro Appennino Centrale Srl, formerly Erg Hydro Srl,Erg Power Generation SpA,Ministero dello Sviluppo economico,THE COURT (Seventh Chamber),composed of F. Biltgen, President of the Chamber, A. Prechal (Rapporteur), President of the Second Chamber, acting as Judge of the Seventh Chamber, and M.L. Arastey Sahún, Judge,Advocate General: A. Rantos,Registrar: A. Juhász-Tóth, Administrator,having regard to the written procedure and further to the hearing on 7 February 2024,after considering the observations submitted on behalf of:– Gestore dei Servizi Energetici SpA – GSE, by F. Degni, P.R. Molea and A. Pugliese, avvocati,– Erg Eolica Ginestra Srl, Erg Eolica Campania SpA, Erg Eolica Fossa del Lupo Srl, Erg Eolica Amaroni Srl, Erg Eolica Adriatica Srl, Erg Eolica San Vincenzo Srl, Erg Eolica San Circeo Srl, Erg Eolica Faeto Srl, Green Vicari Srl, Erg Wind Energy Srl, Erg Wind Sicilia 3 Srl, Erg Wind Sicilia 6 Srl, Erg Wind 4 Srl, Erg Wind 6 Srl, Erg Wind Sicilia 5 Srl, Erg Wind 2000 Srl, Erg Wind Sicilia 2 Srl, Erg Wind Sardegna Srl, Erg Wind Sicilia 4 Srl, Enel Hydro Appennino Centrale Srl, formerly Erg Hydro Srl, and Erg Power Generation SpA, by E. Bruti Liberati, A. Canuti and P. Tanferna, avvocati,– the Italian Government, by G. Palmieri, acting as Agent, and by L.G.V. Delbono, S. Fiorentino and P. Garofoli, avvocati dello Stato,– the European Commission, by B. De Meester and G. Gattinara, acting as Agents,having decided, after hearing the Advocate General, to proceed to judgment without an Opinion,gives the following
Judgment
Legal context
European Union law
Italian law
Legislative Decree No 79/1999
Legislative Decree No 28/2011
Decree of 6 July 2012
The standard agreements
The dispute in the main proceedings and the question referred for a preliminary ruling
Admissibility of the request for a preliminary ruling
Consideration of the question referred
Costs
Operative part
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.