Contents
Judgment of the Court (Fourth Chamber)1 August 2022note(Reference for a preliminary ruling — Public procurement — Concession contracts — Formation of a semi-public company — Award to that company of the management of an integrated school service — Appointment of the private partner under a tender procedure — Directive 2014/23/EU — Article 38 — Directive 2014/24/EU — Article 58 — Applicability — In-house criteria — Requirement for minimum participation of the private partner in the capital of the semi-public company — Indirect participation of the contracting authority in the capital of the private partner — Selection criteria)In Case C‑332/20,REQUEST for a preliminary ruling under Article 267 TFEU from the Consiglio di Stato (Council of State, Italy), made by decision of 13 February 2020, received at the Court on 22 July 2020, in the proceedingsRoma Multiservizi SpA,Rekeep SpAvRoma Capitale,Autorità Garante della Concorrenza e del Mercato,intervener:Consorzio Nazionale Servizi Soc. coop. (CNS),THE COURT (Fourth Chamber),composed of C. Lycourgos (Rapporteur), President of the Chamber, S. Rodin, J.‑C. Bonichot, L. S. Rossi and O. Spineanu‑Matei, Judges,Advocate General: M. Szpunar,Registrar: A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:– Roma Multiservizi SpA, by F. Baglivo, T. Frosini, P. Leozappa, D. Lipani and F. Sbrana, avvocati,– Rekeep SpA, by A. Lirosi, M. Martinelli, G. Vercillo and A. Zoppini, avvocati,– Roma Capitale, by L. D’Ottavi, avvocato,– Consorzio Nazionale Servizi Soc. coop. (CNS), by F. Cintioli, G. Notarnicola and A. Police, avvocati,– the European Commission, by G. Gattinara, P. Ondrůšek and K. Talabér-Ritz, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 24 February 2022,gives the following
Judgment
Legal context
European Union law
Directive 2014/23
Directive 2014/24
Directive 2014/25
Italian law
The dispute in the main proceedings and the questions referred for a preliminary ruling
Consideration of the questions referred
Admissibility of the questions referred
Substance
The legal regime applicable to the contract at issue in the main proceedings
Directive 2014/24
Directive 2014/23
Costs
Operative part