Judgment of the Court (Fourth Chamber)17 June 2021note(Reference for a preliminary ruling — Public procurement — Framework agreement — Directive 2014/24/EU — Article 5(5) — Article 18(1) — Articles 33 and 49 — Points 7, 8 and 10 of Part C of Annex V — Implementing Regulation (EU) 2015/1986 — Annex II, fields II.1.5 and II.2.6 — Procurement procedures — Obligation to state, in the contract notice or the tender specifications, first, the estimated quantity or the estimated value and, second, the maximum quantity or the maximum value of the supplies under a framework agreement — Principles of transparency and equal treatment — Directive 89/665/EEC — Article 2d(1) — Procedures for review of the award of public contracts — Ineffectiveness of the contract — Exception)In Case C‑23/20,REQUEST for a preliminary ruling under Article 267 TFEU from the Klagenævnet for Udbud (Public Procurement Complaints Board, Denmark), made by decision of 16 January 2020, received at the Court on 17 January 2020, in the proceedingsSimonsen & Weel A/SvRegion Nordjylland og Region Syddanmark,intervener:Nutricia A/S,THE COURT (Fourth Chamber),composed of M. Vilaras, President of the Chamber, N. Piçarra, D. Šváby (Rapporteur), S. Rodin and K. Jürimäe, Judges,Advocate General: M. Campos Sánchez-Bordona,Registrar: A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:– Simonsen & Weel A/S, by S. Troels Poulsen, advokat,– the Region Nordjylland og Region Syddanmark, by T. Braad and H. Padkjær Sørensen, advokater,– the Danish Government, by J. Nymann-Lindegren, M. Jespersen and M. Wolff, acting as Agents,– the Belgian Government, by L. Van den Broeck and J.‑C. Halleux, acting as Agents,– the German Government, by J. Möller, R. Kanitz and S. Eisenberg, acting as Agents,– the Estonian Government, by N. Grünberg, acting as Agent,– the French Government, by C. Mosser and E. de Moustier, acting as Agents,– the Austrian Government, by A. Posch and J. Schmoll, acting as Agents,– the European Commission, by P. Ondrůšek, H. Støvlbæk and L. Haasbeek, acting as Agents,having decided, after hearing the Advocate General, to proceed to judgment without an Opinion,gives the following
Judgment
Legal context
European Union law
Directive 2014/24
Implementing Regulation (EU) 2015/1986
Directive 89/665/EEC
Directive 92/13
Danish law
Law on public procurement
Law on the Public Procurement Complaints Board
The dispute in the main proceedings and the questions referred for a preliminary ruling
Consideration of the questions referred
Part (a) of the first question and part (a) of the second question
Part (b) of the first question and part (b) of the second question
The third question
Costs
Operative part