42In view of the foregoing, the answer to the question referred must therefore be that Article 57(4)(c) and (g) of Directive 2014/24 must be interpreted as precluding a national provision under which the lodging of a legal challenge to a decision adopted by a contracting authority to terminate a public contract early on account of major deficiencies in the performance thereof prevents the contracting authority which issues a further call for tenders from conducting an assessment, at the stage of selecting tenderers, of the reliability of the operator concerned by that early termination.