Judgment of the Court (Fifth Chamber)7 November 2019note(Reference for a preliminary ruling — Polluter pays principle — Directive 2000/60/EC — Article 9(1) — Recovery of the costs of water services — Common rules for the internal market in electricity — Directive 2009/72/EC — Article 3(1) — Principle of non-discrimination — Article 107(1) TFEU — State aid — Tax on the use of inland waters for the production of electricity — Tax imposed only on hydroelectricity producers operating on inter-communities river basins)In Joined Cases C‑105/18 to C‑113/18,REQUESTS for a preliminary ruling under Article 267 TFEU from the Tribunal Supremo (Supreme Court, Spain), made by decisions of 27 June 2017 (C‑105/18, C‑106/18, C‑108/18, C‑110/18 and C‑111/18), of 18 July 2017 (C‑107/18 and C‑113/18), of 4 July 2018 (C‑109/18) and of 11 July 2017 (C‑112/18), received at the Court on 13 February 2018, in the proceedingsAsociación Española de la Industria Eléctrica (UNESA) (C‑105/18),Energía de Galicia (Engasa) SA (C‑106/18),Duerocanto SL (C‑107/18),Corporación Acciona Hidráulica (Acciona) SLU (C‑108/18),Associació de Productors i Usuaris d’Energia Elèctrica (C‑109/18),José Manuel Burgos Pérez,María del Amor Guinea Bueno (C‑110/18),Endesa Generación SA (C‑111/18),Asociación de Empresas de Energías Renovables (APPA) (C‑112/18),Parc del Segre SA,Electra Irache SL,Genhidro Generación Hidroeléctrica SL,Hicenor SL,Hidroeléctrica Carrascosa SL,Hidroeléctrica del Carrión SL,Hidroeléctrica del Pisuerga SL,Hidroeléctrica Santa Marta SL,Hyanor SL,Promotora del Rec dels Quatre Pobles SA (C‑113/18),vAdministración General del Estado,interveners:Iberdrola Generación SAU,Hidroeléctrica del Cantábrico SA,THE COURT (Fifth Chamber),composed of E. Regan, President of the Chamber, I. Jarukaitis, E. Juhász, M. Ilešič and C. Lycourgos (Rapporteur), Judges,Advocate General: G. Hogan,Registrar: L. Carrasco Marco, administrator,having regard to the written procedure and further to the hearing on 28 February 2019,after considering the observations submitted on behalf of:– Asociación Española de la Industria Eléctrica (UNESA), by J.C. García Muñoz, abogado, and M.C. Villaescusa Sanz, procuradora,– Energía de Galicia SA (Engasa), by F. Plasencia Sánchez and B. Ruiz Herrero, abogados, and P. Ortiz-Cañavate Levenfeld, procuradora,– Corporación Acciona Hidráulica (Acciona) SLU, by F. Plasencia Sánchez and A. Lázaro Gogorza, procuradora,– Associació de Productors i Usuaris d’Energia Elèctrica, by J.C. Hernanz Junquero, abogado, and D. Martín Cantón, procuradora,– Endesa Generación SA, by J.L. Buendía Sierra, F.J. López Villalta y Peinado, E. Gardeta González, J.M. Cobos Gómez and A. Lamadrid de Pablo, abogados,– Parc del Segre SA and Others, by P.M. Holtrop, abogado, and F.S. Juanas Blanco, procurador,– Iberdrola Generación SAU, by J. Ruiz Calzado and J. Domínguez Pérez, abogados, and J.L. Martín Jaureguibeitia, procurador,– the Spanish Government, by A. Rubio González and V. Ester Casas, acting as Agents,– the German Government, initally by T. Henze and J. Möller, and subsequently by J. Möller, acting as Agents,– the European Commission, by O. Beynet, P. Němečková, G. Luengo and E. Manhaeve, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 8 May 2019,gives the following
Judgment
Legal context
EU law
Directive 2000/60
Directive 2009/72
Spanish law
The Energy Tax Law
Royal Decree No 198/2015
The disputes in the main proceedings and the questions referred for a preliminary ruling
Consideration of the questions referred
The first question
The second question
The third question in Joined Cases C‑105/18 to C‑108/18 and C‑110/18 to C‑113/18 and in Case C‑109/18
Costs
Operative part