Judgment of the General Court (Third Chamber, Extended Composition)27 January 2021note(Environment — Directive 2010/75/EU — Industrial emissions — Implementing Decision (EU) 2017/1442 — Large combustion plants — Best available techniques (BAT) conclusions — Article 16(4) and (5) TEU — Article 3(2) and (3) of Protocol (No 36) on transitional provisions — Application of the law ratione temporis — Comitology)In Case T‑699/17,Republic of Poland, represented by B. Majczyna and D. Krawczyk, acting as Agents,Republic of Bulgaria, represented by E. Petranova and T. Mitova, acting as Agents,and byHungary, represented by M. Fehér, acting as Agent,vEuropean Commission, represented by Ł. Habiak, K. Herrmann and R. Tricot, acting as Agents,Kingdom of Belgium, represented by M. Jacobs, acting as Agent,byFrench Republic, represented by J. Traband and A.-L. Desjonquères, acting as Agents,and byKingdom of Sweden, represented by C. Meyer-Seitz, H. Shev, L. Zettergren and A. Alriksson, acting as Agents,THE GENERAL COURT (Third Chamber, Extended Composition),composed of A.M. Collins, President, V. Kreuschitz (Rapporteur), Z. Csehi, G. De Baere and G. Steinfatt, Judges,Registrar: R. Ūkelytė, Administrator,having regard to the written part of the procedure and further to the hearing on 17 September 2020,gives the following
Judgment
Legal framework
The procedure for adopting best available techniques (BAT) conclusions
The applicable provisions concerning the qualified majority
Background to the dispute
Procedure and forms of order sought
Law
The first plea in law, alleging infringement of the provisions of Article 16(4) and (5) TEU in conjunction with those of Article 3(2) and (3) of Protocol No 36
The effects ratione temporis of the annulment of the contested decision
Costs
Operative part