54However, it is possible that such an objective may justify certain limits on the use of subcontracting (see, to that effect, judgments of 18 March 2004, Siemens and ARGE Telekom, C‑314/01, EU:C:2004:159, paragraph 45, and of 14 July 2016, Wrocław - Miasto na prawach powiatu, C‑406/14, EU:C:2016:562, paragraph 34), it must be held that a provision of a national law, such as Article 24(5) of the Law on public procurement, goes beyond what is necessary in order to achieve that objective, in that it prohibits in a general manner reliance on subcontractors for works treated as ‘main’ works by the contracting entity.