49According to paragraph 46 of the judgment of the Court of 6 November 2014 in Cartiera dell’Adda (C‑42/13, EU:C:2014:2345), the contracting authority may not accept any rectification of omissions which, as expressly provided for in the contract documentation, must result in the exclusion of the bid. The Court stated, in paragraph 48 of that judgment, that the obligation concerned was clearly laid down in the contract documentation, on pain of exclusion.