46Furthermore, in such circumstances, Article 51 of Directive 2004/18, which provides that the contracting authority may invite operators to supplement or clarify the certificates and documents submitted pursuant to Articles 45 to 50 of the directive, cannot be interpreted as permitting that authority to accept any rectification of omissions which, as expressly provided for in the contract documentation, must result in the exclusion of the bid.