Judgment of the General Court (Fifth Chamber)29 June 2012note(Competition — Agreements, decisions and concerted practices — German and French markets for natural gas — Decision finding an infringement of Article 81 EC — Market sharing — Duration of the infringement — Fines)In Case T-360/09,E.ON Ruhrgas AG, established in Essen (Germany),E.ON AG, established in Düsseldorf (Germany),represented by G. Wiedemann and T. Klose, lawyers,vEuropean Commission, represented by V. Di Bucci, A. Bouquet and R. Sauer, acting as Agents, assisted by M. Buntscheck, lawyer,THE GENERAL COURT (Fifth Chamber),composed of S. Papasavvas (Rapporteur), President, V. Vadapalas and K. O’Higgins, Judges,Registrar: T. Weiler, Administrator,having regard to the written procedure and further to the hearing on 23 September 2011,gives the following
Judgment
Legal context
1. European Union law
2. National laws
German law
French law
Background to the dispute
1. The undertakings in question
2. The MEGAL agreement
3. Administrative procedure
The contested decision
Procedure and forms of order sought
Law
1.The head of claim seeking the annulment of the contested decision
The first plea, alleging infringement of Article 81(1) EC
–The first part
–The second part
–The third part
–The fourth part
–The fifth part
–The sixth part
The second plea, alleging an error of law in the assessment of the duration of the infringement
–The cessation of the infringement in question
–The conduct of the undertakings in question after the liberalisation of the markets for gas
The third plea, alleging infringement of the principle of equal treatment
The fourth plea, alleging that the alleged infringements stemming from the 1975 agreements are time-barred
The fifth plea, alleging that the second applicant is not liable for the actions of the first applicant
2.The heads of claim seeking a reduction in the amount of the fine
Costs
Operative part