191Results, data, analyses and schematics#
(1)An operator must ensure that a copy of the final results, data, analyses and schematics obtained from any well operation, including those obtained as a result of the following activities, is submitted to the Board:
(a)the testing, sampling and pressure measurements that are conducted as part of the field data acquisition program referred to in section 13 and the well data acquisition program referred to in section 18, as well as any evaluation, testing and sampling of formations that is conducted under section 62; and
(b)any verification conducted under paragraph 71(2)(a) and any segregation test conducted under paragraph 71(2)(b).
(2)Unless otherwise agreed to in writing by the Board, the operator must ensure that the copy is submitted within 60 days after the day on which the activity that gave rise to the results, data, analyses or schematics is concluded.