Contents
The National Energy Board, pursuant to section 134 of the National Energy Board Act, makes the annexed Administrative Monetary Penalties Regulations (National Energy Board).Calgary, May 17, 2013His Excellency the Governor General in Council, on the recommendation of the Minister of Natural Resources, pursuant to section 134 of the National Energy Board Act, approves the annexed Administrative Monetary Penalties Regulations (National Energy Board), made by the National Energy Board on May 17, 2013.notenote
Interpretation
1Definition of Act#
Designated Provisions
2Provisions of the Act or regulations#
Classification
3Provisions#
Penalties
4Penalty#
Service of Documents
5Manner of service#
Coming into Force
*6S.C. 2012, c. 19#
Schedule 1 · Violations (Subsections 2(1) and (4) and subsection 3(1))
| Column 1 | Column 2 | Column 3Item | Provision | Short-form Description | Classification1 | 103(4) | Failure to provide assistance | Type B2 | 179(1) | Construction, operation or abandonment of a pipeline by a person other than a company | Type B3 | 180(1) | Operation of a pipeline without a certificate and leave to open | Type B4 | 181(1) | Failure to obtain required leave | Type B5 | 198(a) | Begin construction of a pipeline without a certificate | Type B6 | 198(c) | Begin construction of a pipeline without an approved plan, profile and book of reference | Type B7 | 211(1) | Failure to submit for approval a plan, profile and book of reference | Type B8 | 213(1) | Opening a pipeline or a section of a pipeline for transmission without leave | Type B9 | 217(1) | Construction of a pipeline without a certificate or order | Type B10 | 218 | Construction or operation of a pipeline without a certificate or order | Type B11 | 241(1) | Abandonment of a pipeline without leave | Type B12 | 247 | Construction or operation of an international power line without a permit or certificate | Type B13 | 265(a) | Begin construction of an international or interprovincial power line without approval of a plan, profile and book of reference | Type B14 | 267 | Construction or operation of an interprovincial or international power line without a permit or certificate | Type B15 | 273(1) | Construction of a facility, or engaging in an activity that causes a ground disturbance, without authorization | Type B16 | 273(2) | Operation of a vehicle or mobile equipment across an international or interprovincial power line in contravention of subsection 273(2) of the Act | Type B17 | 277(1) | Abandonment of a designated international power line or interprovincial power line without leave | Type B18 | 314 | Failure to do as little damage as possible in exercising the powers granted and to compensate all persons interested for damage sustained | Type B19 | 335(1) | Unauthorized construction of a facility or engaging in an unauthorized activity that causes a ground disturbance | Type B20 | 335(2) | Operation of a vehicle or mobile equipment across a pipeline in contravention of subsection 335(2) of the Act | Type B21 | 338(1) | Working or prospecting for mines or minerals without authorization | Type BItem | Column 1 | Column 2 | Column 3Provision | Short-form Description | Classification1 | 4 | Failure to ensure that a pipeline is designed, constructed, operated or abandoned as prescribed | Type B2 | 5.1(1) | Failure to submit prescribed documents for approval | Type B3 | [Repealed, SOR/2022-199, s. 9]4 | 6.1 | Failure to establish, implement and maintain a management system as prescribed | Type B5 | 6.2(1) | Failure to appoint an accountable officer and to ensure that the management system is established, implemented and maintained as prescribed | Type B6 | 6.2(2) | Failure to notify the Regulator as prescribed | Type A7 | 6.2(3) | Failure to ensure that the accountable officer has authority as prescribed | Type B8 | 6.3(1) | Failure to establish policies and goals as prescribed | Type B9 | 6.3(2) | Failure to base the management system on established policies and goals as prescribed | Type B10 | 6.3(3) | Failure of the accountable officer to prepare and communicate a policy statement as prescribed | Type B11 | 6.4 | Failure to have an organizational structure as prescribed | Type B12 | 6.5 | Failure to establish, develop, implement, maintain and document processes as prescribed | Type B13 | 6.6 | Failure to complete an annual report and submit a statement as prescribed | Type B14 | 9 | Failure to develop detailed designs of a pipeline and to submit them to the Regulator when required | Type B15 | 10(1) | Failure to develop a documented risk assessment as prescribed | Type B16 | 10(2) | Failure to submit a documented risk assessment to the Regulator when required to do so | Type A17 | 11 | Failure to design and equip a station as prescribed | Type B18 | 12 | Failure to equip a compressor station or pump station with an alternate source of power as prescribed | Type B19 | 13 | Failure to locate, service or design a storage facility as prescribed | Type B20 | 14 | Failure to develop prescribed specifications, and to submit them to the Regulator when required | Type B21 | 15 | Failure to develop a quality assurance program as prescribed | Type B22 | 16 | Failure to develop a joining program as prescribed, and to submit it to the Regulator when required | Type B23 | 17 | Failure to examine each joint as prescribed | Type B24 | 18 | Failure to contract for services as prescribed | Type B25 | 19(a) | Failure to ensure that the construction activities do not create a hazard to the public or the environment | Type B26 | 19(b) | Failure to inform persons of safety practices and procedures as prescribed | Type B27 | 20(1) | Failure to develop a construction safety manual and to submit it to the Regulator | Type B28 | 20(1.1) | Failure to set out responsibilities as prescribed | Type B29 | 20(2) | Failure to keep a copy of the construction safety manual or relevant parts of it as prescribed | Type B30 | 21 | Failure to restore the right-of-way and temporary work areas of a pipeline as prescribed | Type B31 | 22 | Failure to ensure that there is no undue interference with the use of a utility or private road during the construction of a pipeline | Type B32 | 23 | Failure to develop a pressure testing program as prescribed, and to submit it to the Regulator when required | Type B33 | 24 | Conducting a pressure test without required permits | Type B34 | 25 | Failure to perform pressure testing as prescribed | Type B35 | 26 | Failure to minimize the number of welds that are not pressure-tested as prescribed | Type B36 | 27 | Failure to develop, regularly review and update as required operation and maintenance manuals as prescribed and to submit them to the Regulator when required | Type B37 | 28 | Failure to inform persons of practices and procedures and to make available to them the relevant portion of operation and maintenance manuals as prescribed | Type B38 | 29 | Failure to contract for services as prescribed | Type B39 | 30(a) | Failure to take reasonable steps to ensure that maintenance activities do not create a hazard to the public or the environment | Type B40 | 30(b) | Failure to take reasonable steps to inform persons of safety and environmental protection practices and procedures as prescribed | Type B41 | 31(1) | Failure to develop a maintenance safety manual and to submit it to the Regulator when required | Type B42 | 31(1.1) | Failure to set out responsibilities as prescribed | Type B43 | 31(2) | Failure to keep a copy of the maintenance safety manual or the relevant parts of it as prescribed | Type B44 | 32(1) | Failure to develop, implement and maintain an emergency management program as prescribed | Type B45 | 32(1.1) | Failure to develop, regularly review and update an emergency procedures manual | Type B46 | 32(2) | Failure to submit to the Regulator the emergency procedures manual and any updates | Type A47 | 33 | Failure to establish and maintain liaison as prescribed, and failure to consult as prescribed | Type B48 | 34 | Failure to inform persons who may be associated with an emergency response activity as prescribed | Type B49 | 35 | Failure to develop a continuing education program as prescribed | Type B50 | 36(a) | Failure to maintain communication facilities as prescribed | Type B51 | 36(b) | Failure to periodically test instruments and equipment as prescribed | Type B52 | 36(c) | Failure to continually record as prescribed | Type B53 | 36(d) | Failure to clearly mark valves as prescribed | Type B54 | 36(e) | Failure to clearly mark valves as prescribed | Type B55 | 36(f) | Failure to post signage as prescribed | Type B56 | 37 | Failure to develop and implement a pipeline control system as prescribed | Type B57 | 38(1) | Performing welding on a liquid-filled pipeline other than as prescribed | Type B58 | 38(2) | Failure to treat weld as a temporary installation and replace that installation with a permanent one as soon as is practicable | Type B59 | 38(3) | Failure to submit specifications, procedures and results for approval as prescribed | Type B60 | 39 | Failure to develop a surveillance and monitoring program as prescribed | Type B61 | 40 | Failure to develop, implement and maintain an integrity management program as prescribed | Type B62 | 41(1) | Failure to document the particulars of a defect on a pipeline as prescribed | Type B63 | 41(2) | Failure to submit the documentation in 41(1) when required | Type A64 | 42 | Failure to submit a proposed plan as prescribed | Type B65 | 43 | Failure to submit an application for a change or increase as prescribed | Type B66 | 44 | Failure to submit an application for proposed deactivation as prescribed | Type B67 | 45 | Failure to submit an application for reactivation as prescribed | Type B68 | 45.1 | Failure to submit an application for decommissioning as prescribed | Type B69 | 46 | Failure to develop and implement a training program as prescribed | Type B70 | 47 | Failure to develop, implement and maintain a safety management program as prescribed | Type B71 | 47.1 | Failure to develop, implement and maintain a security management program as prescribed | Type B71.1 | 47.2 | Failure to develop, implement and maintain a damage prevention program as prescribed | Type B72 | 48 | Failure to develop, implement and maintain an environmental protection program as prescribed | Type B73 | 51(a) | Failure to notify as prescribed | Type A74 | 51(b) | Failure to submit to the Regulator on request a crossing report as prescribed | Type A75 | 52(1) | Failure to notify and submit a report to the Regulator as prescribed | Type A76 | 53(1) | Failure to conduct inspections and audits as prescribed | Type B77 | 53(2) | Failure to document the audit as prescribed | Type B78 | 54(1) | Failure to inspect the construction of a pipeline as prescribed | Type B79 | 54(2) | Performance of an inspection by a person who does not have sufficient expertise, knowledge and training to competently carry out the inspection | Type B80 | 55 | Failure to conduct and document audits as prescribed | Type B81 | 56 | Failure to retain records as prescribed | Type AItem | Column 1 | Column 2 | Column 3Provision | Short-form Description | Classification1 | 4(1) | Failure to ensure that the company’s processing plant is designed, constructed, operated or abandoned as prescribed | Type B2 | 5 | Failure to ensure that the company’s processing plant is designed, constructed, operated or abandoned as prescribed | Type B3 | 9 | Failure to develop and submit to the Regulator the prescribed program | Type B4 | 10 | Failure to develop, implement and maintain quality control and quality assurance programs as prescribed | Type B5 | 11 | Failure to conduct a risk analysis as prescribed | Type B6 | 12 | Failure to ensure that employees have required knowledge and training | Type B7 | 13 | Failure to develop and implement a safety program as prescribed | Type B8 | 14 | Failure to develop and implement an environmental protection program as prescribed | Type B9 | 15 | Failure to contract for services as prescribed | Type B10 | 16 | Failure to develop, implement and maintain detailed designs of its processing plant | Type B11 | 17 | Failure to ensure that a processing plant is equipped with an emergency power source | Type B12 | 18 | Failure to ensure that each tank, bullet, sphere or other container is designed, constructed and maintained as prescribed | Type B13 | 19 | Failure to ensure that process equipment and flammable vapour sources are separated as prescribed | Type B14 | 20 | Failure to ensure that process vessels and equipment are vented as prescribed | Type B15 | 21 | Failure to equip all flare headers as prescribed | Type B16 | 22 | Failure to ensure reliable fire suppression systems as prescribed | Type B17 | 23 | Failure to equip a processing plant with systems as prescribed | Type B18 | 24 | Failure to equip a processing plant with alarm devices as prescribed | Type B19 | 25 | Failure to ensure that all pressure-relief piping and systems are designed and constructed as prescribed | Type B20 | 26(a) | Failure to ensure construction does not create a detriment or hazard as prescribed | Type B21 | 26(b) | Failure to inform persons at the construction site as prescribed | Type B22 | 26(c) | Failure to inform persons on the work site as prescribed | Type B23 | 27(1) | Failure to develop, implement and submit a construction safety manual | Type B24 | 27(2) | Failure to keep a copy of the construction safety manual at the processing plant as prescribed | Type B25 | 28(1) | Failure to ensure direct supervision of pressure tests as prescribed | Type B26 | 28(2) | Failure to ensure the independence of the test supervisor as prescribed | Type B27 | 28(3) | Failure to date and sign records | Type B28 | 29 | Failure of the company to develop and implement a non-destructive weld examination program as prescribed | Type B29 | 30(1)(a) | Failure to develop, implement, regularly review and update operations manuals as prescribed | Type B30 | 30(1)(b) | Failure to keep a copy of the operations manuals as prescribed | Type B31 | 30(2) | Failure to ensure that the operations manuals contain the prescribed procedures | Type B32 | 31(2) | Failure to develop and implement a safe-work permit system as prescribed | Type B33 | 32 | Failure to ensure that a processing plant is staffed as prescribed | Type B34 | 33(a) | Failure to ensure maintenance activities do not create a detriment or hazard as prescribed | Type B35 | 33(b) | Failure to inform persons at a maintenance site as prescribed | Type B36 | 34 | Operation of equipment with a hazard-detection alarm or shutdown device bypassed or rendered inoperable | Type B37 | 35(a) | Failure to develop, implement, regularly review and update an emergency procedures manual | Type B38 | 35(b) | Failure to submit the emergency procedures manual as prescribed | Type A39 | 35(c) | Failure to submit updates as prescribed | Type A40 | 36 | Failure to establish and maintain liaison as prescribed and failure to consult as prescribed | Type B41 | 37 | Failure to inform persons who may be associated with an emergency response activity as prescribed | Type B42 | 38 | Failure to develop and implement a continuing educational program as prescribed | Type B43 | 39(a) | Failure to maintain communication facilities as prescribed | Type B44 | 39(b) | Failure to retain incident data as prescribed | Type B45 | 39(c) | Failure to clearly mark valves as prescribed | Type B46 | 39(d) | Failure to post signage as prescribed | Type B47 | 39(e) | Failure to post signage as prescribed | Type B48 | 40(a) | Failure to test hazard-detection devices as prescribed | Type B49 | 40(b) | Failure to document and maintain prescribed records | Type B50 | 41 | Failure to develop and implement a processing plant integrity program as prescribed | Type B51 | 42 | Failure to notify of plant deactivation as prescribed | Type A52 | 43.1 | Failure to submit an application for decommissioning as prescribed | Type B53 | 44 | Failure to develop and implement a training program as prescribed | Type B54 | 45 | Failure to ensure visitors are made familiar with the safety program as prescribed | Type B55 | 46 | Failure to provide immediate notice of any incident and to submit prescribed reports | Type B56 | 47(a) | Failure to notify of any hazard as prescribed | Type A57 | 47(b) | Failure to provide a report as prescribed | Type B58 | 48 | Failure to report burning as prescribed | Type A59 | 49(1.1) | Failure to notify as prescribed | Type A60 | 50 | Failure to prepare and keep current a report as prescribed | Type B61 | 51 | Failure to regularly conduct balance analysis as prescribed | Type B62 | 52(1) | Failure to conduct audits and inspections as prescribed | Type B63 | 52(2) | Failure to document an audit as prescribed | Type B64 | 53 | Failure to inspect as prescribed | Type B65 | 54 | Failure to annually audit the competency of all employees as prescribed | Type B66 | 55 | Failure to develop, implement and maintain a record retention and handling program | Type AItem | Column 1 | Column 2 | Column 3Provision | Short-form Description | Classification1 | 3 | Failure to make a locate request as prescribed | Type B2 | 4 | Failure to inform all persons as prescribed | Type A3 | 7(3) | Failure to comply with any of the prescribed measures when undertaking the construction of a facility | Type B4 | 8 | Failure to meet any of the obligations that relate to a facility | Type B5 | 9(2) | Failure to comply with any of the prescribed measures with respect to the construction of an overhead line | Type B6 | 10(3) | Failure to comply with any of the prescribed measures with respect to an activity that causes a ground disturbance within the prescribed area | Type BItem | Column 1 | Column 2 | Column 3Provision | Short-form Description | Classification1 | 2 | Failure to be a member of a one-call centre when one exists within the geographical area where the pipeline company operates its pipeline | Type B2 | 3(1) | Failure to inform the person that made a request within 10 working days after receiving a request | Type A3 | 4 | Failure to provide information and all reasonable assistance as prescribed | Type B4 | 5 | Failure to send comments to the Regulator as prescribed | Type A5 | 6(1)(a) | Failure to inform, in writing, as prescribed | Type B6 | 6(1)(b) | Failure to mark location of a pipe as prescribed | Type B7 | 6(1)(c) | Failure to provide information as prescribed | Type B8 | 7 | Failure to identify and notify of locations as prescribed | Type B9 | 8(a) | Failure to carry out inspections that are necessary as prescribed | Type B10 | 8(b) | Failure to inspect all exposed pipe prior to backfilling as prescribed | Type B11 | 9(1) | Failure to notify the facility’s owner in writing of any deterioration as prescribed | Type B12 | 9(2) | Failure to notify the Regulator in writing as prescribed | Type A13 | 10(2) | Failure to notify the Regulator in writing of a suspension of consent | Type A14 | 11 | Failure to report to the Regulator as prescribed | Type A15 | 12 | Failure to keep records as prescribed | Type A16 | 13 | Failure to make records and all other materials available to officers of the Regulator and other authorized persons and give them assistance as necessary to inspect the records as prescribed | Type B17 | 14 | Failure to provide a list as prescribed | Type A18 | 15 | Failure to develop and maintain guidelines as prescribed and to make them public | Type B | Column 1 | Column 2 | Column 3Item | Provision | Short-form Description | Classification1 | 7 | Failure to construct a facility as prescribed or failure to obtain authorization | Type B2 | 8 | Failure to conduct a ground disturbance activity as prescribed or failure to obtain authorization | Type B3 | 10 | Failure to construct a power line as prescribed | Type B
Schedule 2 · (Subsection 4(1))
Item | Column 1 | Column 2 | Column 3Gravity Level | Type A Violation | Type B ViolationIndividual | Any Other Person | Individual | Any Other Person1 | –3 or less | $250 | $1,000 | $1,000 | $4,0002 | –2 | $595 | $2,375 | $4,000 | $16,0003 | –1 | $990 | $3,750 | $7,000 | $28,0004 | 0 | $1,365 | $5,025 | $10,000 | $40,0005 | 1 | $1,740 | $6,300 | $13,000 | $52,0006 | 2 | $2,115 | $7,575 | $16,000 | $64,0007 | 3 | $2,490 | $8,850 | $19,000 | $76,0008 | 4 | $2,865 | $10,125 | $22,000 | $88,0009 | 5 or more | $3,000 | $12,000 | $25,000 | $100,000