(b)Any documents required to be submitted under subsection (a) shall include detailed and summarized information with respect to each weapon system covered and shall specifically include each of the following:
(1)The development schedule, including estimated annual costs until development is completed.
(2)The planned procurement schedule, including the best estimate of the Secretary of Defense of the annual costs and units to be procured until procurement is completed.
(3)To the extent required by the second sentence of subsection (a), the result of all operational testing and evaluation up to the time of the submission of the documents, or, if operational testing and evaluation has not been conducted, a statement of the reasons therefor and the results of such other testing and evaluation as has been conducted.
(4)
(A)The most efficient production rate, the most efficient acquisition rate, and the minimum sustaining rate, consistent with the program priority established for such weapon system by the Secretary concerned.
(B)In this paragraph:
(i)The term “most efficient production rate” means the maximum rate for each budget year at which the weapon system can be produced with existing or planned plant capacity and tooling, with one shift a day running for eight hours a day and five days a week.
(ii)The term “minimum sustaining rate” means the production rate for each budget year that is necessary to keep production lines open while maintaining a base of responsive vendors and suppliers.