Contents
- 1 Citation, commencement and extent
- 2 Amendments
- 3 The renewables obligation
- 4 Calculation B
- 5 Omission of Calculation C
- 6 Determining the total number of renewables obligation certificates to be produced in an obligation period
- 7 Determining the number of renewables obligation certificates to be produced by a designated electricity supplier in order to discharge its renewables obligation
- 8 Cases and circumstances when a ROC must not be issued
- 9 Banding
- 10 Refusing to issue and revoking ROCs
- 11 Refusing to issue and revoking ROCs: supplemental
- 12 Late payments to discharge the renewables obligation
- 13 Information to be provided to the Authority where electricity is generated from biomass
- 14 Preliminary accreditation and accreditation of generating stations
- 15 The 2009 Order: Schedule 1
- 16 The 2009 Order: Schedule 2
- 17 The 2009 Order: Schedule 3
- 18 The 2009 Order: Schedule 4
- 19 Transitionals
Article 1Citation, commencement and extent#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 3The renewables obligation#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 5Omission of Calculation C#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 6Determining the total number of renewables obligation certificates to be produced in an obligation period#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 7Determining the number of renewables obligation certificates to be produced by a designated electricity supplier in order to discharge its renewables obligation#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 8Cases and circumstances when a ROC must not be issued#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 10Refusing to issue and revoking ROCs#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 11Refusing to issue and revoking ROCs: supplemental#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 12Late payments to discharge the renewables obligation#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 13Information to be provided to the Authority where electricity is generated from biomass#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 14Preliminary accreditation and accreditation of generating stations#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 15The 2009 Order: Schedule 1#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 16The 2009 Order: Schedule 2#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 17The 2009 Order: Schedule 3#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 18The 2009 Order: Schedule 4#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)
Article 19Transitionals#
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (repealed)