a licensee of the Coal Authoritymeans any person who is for the time being authorised by a licence under Part II of the Coal Industry Act 1994 to carry on coal-mining operations to which section 25 of that Act applies;
approved restoration schememeans a restoration scheme which is approved when an application made under paragraph A.1(a)(i) is finally determined, as approved (with or without conditions), or as subsequently varied with the written approval of the mineral planning authority (with or without conditions);
coalmeans coal other than that— a won or worked during the course of operations which are carried on exclusively for the purpose of exploring for coal, or b which it is necessary to dig or carry away in the course of activities carried on for purposes which do not include the getting of coal or any product of coal.”
coal-related mineralsmeans minerals other than coal which are, or may be, won and worked by coal-mining operations;
designated seam areameans land identified, in accordance with paragraph (a) of the definition of “seam plan”, in a seam plan which was deposited with the mineral planning authority before 30th September 1993;
licensees of the British Coal Corporationmeans persons who are for the time being authorised by virtue of section 25(3) of the Coal Industry Act 1994 to carry on coal-mining operations to which section 25 of that Act applies.
previous coal-mining operationshas the same meaning as in section 54(3) of the Coal Industry Act 1994 and references in this Class to the use of anything in connection with any such operations shall include references to its use for or in connection with activities carried on in association with, or for purposes connected with, the carrying on of those operations;
restoration schememeans a scheme which makes provision for the reinstatement, restoration or aftercare (or a combination of these) of any land which is an authorised site and has been used at any time for or in connection with any previous coal-mining operations at that mine;
seam planmeans a plan or plans on a scale of not less than 1 to 25,000 showing— (a) land comprising the maximum extent of the coal seam or seams that can be worked from shafts or drifts existing at a mine at 13th November 1992, without further development on an authorised site other than development permitted by Class B;
the 1988 Ordermeans the Town and Country Planning General Development Order 1988.