Contents
Part 1 · Sustainable management of natural resources
General
24Power to amend periods for the preparation and publication of documents#
(1)The Welsh Ministers may by regulations make provision changing the time by which the following documents must be prepared or published—
(a)a state of natural resources report or a draft of such a report;
(za)an evaluation report prepared under section 6A;
(2)Regulations under subsection (1) may make provision by way of amendment of this Part.
(3)Before making regulations under subsection (1) in relation to the documents mentioned in subsection (1)(a) or (b), the Welsh Ministers must consult NRW.
25Regulations under this Part#
(1)A power to make regulations under this Part is to be exercised by statutory instrument.
(2)A power to make regulations under this Part includes power—
(a)to make different provision for different purposes or cases;
(b)to make transitional or saving provision.
(3)A statutory instrument containing regulations under this Part may not be made unless a draft of the instrument has been laid before, and approved by a resolution of, the National Assembly for Wales.
(4)A statutory instrument containing regulations whose only substantive effect is to revoke regulations made under section 22(1) , or to revoke a target that has been set in regulations under section 6B and that has been met, is not subject to the requirement in subsection (3), but must be laid before the National Assembly for Wales after being made.
26General interpretation of this Part#
In this Part—• “biodiversity” (“bioamrywiaeth”) means the diversity of living organisms, whether at the genetic, species or ecosystem level;• “land” (“tir”) includes land covered by water;• “land management agreement” (“cytundeb rheoli tir”) means an agreement under section 16;• “national natural resources policy” (“polisi adnoddau naturiol cenedlaethol”) has the meaning given by section 9;• “natural resources” (“adnoddau naturiol”) is to be interpreted in accordance with section 2;• “NRW” (“CNC”) means the Natural Resources Body for Wales;• “principles of sustainable management of natural resources” (“egwyddorion rheoli cynaliadwy ar adnoddau naturiol”) has the meaning given by section 4;• “sustainable management of natural resources” (“rheoli cynaliadwy ar adnoddau naturiol”) has the meaning given by section 3.
27Minor and consequential provision#
(1)The amendments made by this Part to the Natural Resources Body for Wales (Establishment) Order 2012 (S.I. 2012/1903) do not affect the power of the Welsh Ministers to make further orders under sections 13 and 15 of the Public Bodies Act 2011 (c. 24) amending or revoking the provision made by those amendments.
(2)Part 1 of Schedule 2 provides for minor and consequential amendments and repeals relating to this Part.
Introduction
1Purpose of this Part#
The purpose of this Part is to promote sustainable management of natural resources.
2Natural resources#
In this Part, “natural resources” includes (but is not limited to)—
(a)animals, plants and other organisms;
(b)air, water and soil;
(c)minerals;
(d)geological features and processes;
(e)physiographical features;
(f)climatic features and processes.
3Sustainable management of natural resources#
(1)In this Part, “sustainable management of natural resources” means—
(a)using natural resources in a way and at a rate that promotes achievement of the objective in subsection (2),
(b)taking other action that promotes achievement of that objective, and
(c)not taking action that hinders achievement of that objective.
(2)The objective is to maintain and enhance the resilience of ecosystems and the benefits they provide and, in so doing—
(a)meet the needs of present generations of people without compromising the ability of future generations to meet their needs, and
(b)contribute to the achievement of the well-being goals in section 4 of the Well-being of Future Generations (Wales) Act 2015 (anaw 2).
4Principles of sustainable management of natural resources#
In this Part, the “principles of sustainable management of natural resources” are—
(a)manage adaptively, by planning, monitoring, reviewing and, where appropriate, changing action;
(b)consider the appropriate spatial scale for action;
(c)promote and engage in collaboration and co-operation;
(d)make appropriate arrangements for public participation in decision-making;
(e)take account of all relevant evidence and gather evidence in respect of uncertainties;
(f)take account of the benefits and intrinsic value of natural resources and ecosystems;
(g)take account of the short, medium and long term consequences of actions;
(h)take action to prevent significant damage to ecosystems;
(i)take account of the resilience of ecosystems, in particular the following aspects—
(i)diversity between and within ecosystems;
(ii)the connections between and within ecosystems;
(iii)the scale of ecosystems;
(iv)the condition of ecosystems (including their structure and functioning);
(v)the adaptability of ecosystems.
Area-based implementation of the national policy
10Meaning of public body in sections 11 to 15#
(1)In sections 11 to 15, “public body” means any one of the following—
(a)a council of a county or county borough in Wales;
(b)a Local Health Board;
(d)a National Park authority for a National Park in Wales;
(e)a Welsh fire and rescue authority;
(f)the Commission for Tertiary Education and Research;
(g)the Arts Council of Wales;
(h)the Sports Council for Wales;
(i)the National Library of Wales;
(j)the National Museum of Wales.
(2)The Welsh Ministers may by regulations amend subsection (1) by—
(a)adding a person,
(b)removing a person, or
(c)amending a description of a person.
(3)But the regulations—
(a)may amend subsection (1) by adding a person only if that person exercises functions of a public nature;
(b)may amend that subsection by adding a Minister of the Crown only if the Secretary of State consents.
(4)If the regulations amend subsection (1) so as to add a person who has functions of a public nature and other functions, sections 11 to 15 apply to that person only in relation to those of the person's functions that are of a public nature.
(5)Before making regulations under subsection (2), the Welsh Ministers must consult—
(a)NRW,
(b)each person the Welsh Ministers propose to add or remove by the regulations, and
(c)such other persons as the Welsh Ministers consider appropriate.
11Area statements#
(1)NRW must prepare and publish statements (“area statements”) for the areas of Wales that it considers appropriate for the purpose of facilitating the implementation of the national natural resources policy.
(2)NRW may use the area statements for any other purpose in the exercise of its functions.
(3)Each area statement must—
(a)explain why a statement has been prepared for the area, by reference to—
(i)the natural resources in the area,
(ii)the benefits which the natural resources provide, and
(iii)the priorities, risks and opportunities for the sustainable management of natural resources which need to be addressed;
(b)explain how the principles of sustainable management of natural resources have been applied in preparing the statement;
(c)state how NRW proposes to address the priorities, risks and opportunities, and how it proposes to apply the principles of sustainable management of natural resources in doing so;
(d)specify the public bodies which NRW considers may assist in addressing the priorities, risks and opportunities.
(5)NRW must—
(a)take all reasonable steps to implement an area statement, and
(b)encourage others to take such steps.
(6)NRW must keep area statements under review and it may revise them at any time.
(7)Before publishing an area statement, NRW must consider whether—
(a)another plan, strategy or similar document should be incorporated into the area statement, or
(b)the area statement should be incorporated into another plan, strategy or similar document.
12Welsh Ministers' directions to implement area statements#
(1)The Welsh Ministers may direct a public body to take such steps as appear to them to be reasonably practicable to address the matters specified in an area statement under section 11(3).
(2)Before giving a direction the Welsh Ministers must consult the public body they intend to direct.
(3)Where a direction is given to a public body under this section, the body must comply with it.
(4)A direction under this section may not require a public body to do something it may not otherwise do in the exercise of its functions.
(5)A direction under this section—
(a)must be published;
(b)may be varied or revoked by a later direction;
(c)is enforceable by mandatory order on an application by, or on behalf of, the Welsh Ministers.
13Guidance about implementing area statements#
(1)In exercising its functions, a public body must have regard to any guidance given to it by the Welsh Ministers about steps that should be taken to address the matters specified in an area statement under section 11(3).
(2)The Welsh Ministers must publish any guidance they give for the purposes of this section.
14Duty of public bodies to provide information or other assistance to NRW#
(1)If NRW asks a public body to provide NRW with information which it requires for the purpose of exercising functions under section 8 or 11, the public body must provide the information unless the public body is prohibited from providing it by virtue of an enactment or any other rule of law.
(2)If NRW asks a public body to exercise its functions to provide NRW with other assistance which NRW requires for the purpose of exercising functions under section 8 or 11, the public body must provide the assistance unless the public body considers that doing so would—
(a)be incompatible with the public body's own duties, or
(b)otherwise have an adverse effect on the exercise of the public body's functions.
(3)The duties of a public body in subsections (1) and (2) are also duties of the Future Generations Commissioner for Wales, but they only apply to the Commissioner if the information or other assistance is required for the production of a report under section 8 on the state of natural resources.
15Duty of NRW to provide information or other assistance to public bodies#
(1)If a public body asks NRW to provide the public body with information which it requires for the purpose of implementing an area statement, NRW must provide the information unless NRW is prohibited from providing it by virtue of an enactment or any other rule of law.
(2)If a public body asks NRW to exercise its functions to provide the public body with other assistance which the public body requires for the purpose of implementing an area statement, NRW must provide the assistance unless NRW considers that doing so would—
(a)be incompatible with NRW's own duties, or
(b)otherwise have an adverse effect on the exercise of NRW's functions.
Biodiversity lists
7Biodiversity lists and duty to take steps to maintain and enhance biodiversity#
(1)The Welsh Ministers must prepare and publish a list of the living organisms and types of habitat which in their opinion are of principal importance for the purpose of maintaining and enhancing biodiversity in relation to Wales.
(2)Before publishing a list under this section the Welsh Ministers must consult the Natural Resources Body for Wales (“NRW”) as to the living organisms or types of habitat to be included in the list.
(3)Without prejudice to section 6, the Welsh Ministers must—
(a)take all reasonable steps to maintain and enhance the living organisms and types of habitat included in any list published under this section, and
(b)encourage others to take such steps.
(4)The Welsh Ministers must, in consultation with NRW—
(a)keep under review any list published by them under this section,
(b)make such revisions of any such list as appear to them appropriate, and
(c)publish any list so revised as soon as is reasonably practicable after revising it.
(5)In exercising their functions under this section, the Welsh Ministers must apply the principles of sustainable management of natural resources.
Biodiversity targets
6BBiodiversity targets: general#
(1)The Welsh Ministers may by regulations set targets in respect of any matter relating to biodiversity in Wales.
(2)The Welsh Ministers may set a target in the regulations only if they are satisfied that meeting it would contribute to halting and reversing the decline in biodiversity or to restoring biodiversity to resilient levels, in particular through one or more of the following—
(a)increasing the abundance of native species;
(b)enhancing the resilience of ecosystems (in particular the aspects specified in section 6(2)(a) to (e));
(c)increasing genetic diversity.
(3)In considering whether a target would contribute to the matters specified in subsection (2)(a), (b) or (c), the Welsh Ministers must have regard to the list published under section 7.
(4)The regulations must, in relation to each target—
(a)specify a standard to be achieved, which must be capable of being objectively measured, and
(b)specify a date by which the standard is to be achieved.
(5)The regulations must—
(a)include provision about how to measure—
(i)progress towards achieving each standard specified under subsection (4), and
(ii)whether the standard has been achieved, and
(b)specify indicators as a means of measuring those things.
(6)A target under this section is set when the regulations setting it come into force.
(7)In this section—(a) “native species” means species that naturally occur or have in the past naturally occurred in Wales, including—(a) regularly occurring migratory species (both breeding and non-breeding) and natural colonists, and(b) species that have been reintroduced in Wales following past extinction;(b) “natural colonists” means species that arrived in Wales of their own accord and have become established, including those that become migratory species.
(8)In sections 6C, 6D, 6G, 6H and 6I, “specified standard” and “specified date”, in relation to a target set under this section, mean the standard and date specified under subsection (4).
6CDuty to make regulations setting targets: priority areas#
(1)The Welsh Ministers must exercise the power in section 6B to —
(a)set a long-term target in respect of at least one matter within each of the priority areas in subsection (2)(a) and (b),
(b)set a short-term target in respect of at least one matter within each of the priority areas in subsection (2)(a) and (b), and
(c)set a target in respect of at least one matter within each of the priority areas in subsection (2)(c) and (d).
(2)The priority areas are—
(a)reducing the risk of the extinction of native species;
(b)the effective management of ecosystems;
(c)reducing pollution;
(d)the quality of evidence to inform decisions relating to biodiversity, access to that evidence and its use and application.
(3)A target is a “long-term target” if the specified date is at least 15 years after the date on which the target is set.
(4)A target is a “short-term target” if the specified date is less than 15 years after the date on which the target is set.
(5)Targets may not be set in respect of a matter within the priority area in subsection (2)(c) if a target may be set in respect of that matter under the Environment (Air Quality and Soundscapes) (Wales) Act 2024 (asc 2).
(6)In subsection (2)(a), ”native species” has the meaning given by section 6B(7).
(7)The Welsh Ministers must lay a draft of a Welsh statutory instrument containing the regulations required by this section before Senedd Cymru before the end of the period of 2 years beginning with the date on which the Environment (Principles, Governance and Biodiversity Targets) (Wales) Act 2026 (asc xx) receives Royal Assent.
6DTarget-setting process#
(1)Before making regulations under section 6B, the Welsh Ministers must seek advice from persons they consider to be independent and to have relevant expertise.
(2)The Welsh Ministers must publish a summary of any such advice they receive.
(3)When making regulations under section 6B, the Welsh Ministers must apply the principles of sustainable management of natural resources.
(4)Before making regulations under section 6B, the Welsh Ministers must publish a report summarising—
(a)the consultation that was carried out in connection with the regulations, and
(b)any representations that were received as a result of the consultation.
(5)Before making regulations under section 6B that set or amend a target, the Welsh Ministers must be satisfied that the target or amended target can be met.
(6)For the purposes of this Part, a target is met if the specified standard is achieved by the specified date.
(7)Subsections (1) to (4) do not apply to provisions in regulations under section 6B that revoke a target that has been met.
6EDuty to meet targets#
The Welsh Ministers must ensure that targets set in regulations made under section 6B are met.
6FDesignation of public authorities for the purpose of section 6(2A)#
(1)The Welsh Ministers may by regulations designate a public authority within section 6(11) in relation to a target set in regulations made under section 6B.
(2)Before making regulations under this section, the Welsh Ministers must consult—
(a)the public authority they propose to designate, and
(b)such other persons as they consider appropriate.
6GReview of targets#
(1)The Welsh Ministers may, from time to time, review a target set in regulations under section 6B.
(2)The Welsh Ministers must review a target set in regulations under section 6B if it appears to them—
(a)that the target may not be met, or
(b)that the target may no longer be appropriate.
(3)The Welsh Ministers may, from time to time, review the effectiveness of all current targets for the purpose of determining whether setting further targets in regulations under section 6B would be more effective in contributing to halting and reversing the decline in biodiversity or to restoring biodiversity to resilient levels.
(4)The Welsh Ministers must review the effectiveness of all current targets for the purpose mentioned in subsection (3)—
(a)if a target set in regulations under section 6B has not been met by the specified date in relation to that target;
(b)if 10 years have passed since the most recently completed review under any of subsection (3), this subsection or subsection (5).
(5)If no review under subsection (3) or (4) has been completed before the end of 2041, the Welsh Ministers must review the effectiveness of all current targets for the purpose mentioned in subsection (3).
(6)A target is current for the purpose of subsections (3) to (5) if—
(a)it has been set in regulations under section 6B that are in force at the time of the review, and
(b)it has not been met at that time.
(7)In carrying out a review under this section, the Welsh Ministers must seek advice from persons they consider to be independent and to have relevant expertise.
(8)The Welsh Ministers must publish a summary of any such advice they receive.
(9)After carrying out a review under this section, the Welsh Ministers must lay before Senedd Cymru, and publish, a statement noting its conclusions.
(10)If a review under subsection (1) or (2) concludes that a target will not be met or is no longer appropriate, the statement must note the reasons for that conclusion and the steps, if any, the Welsh Ministers intend to take in relation to the target in consequence of the review.
(11)If a review under subsection (3), (4) or (5) concludes that further targets should be set in regulations under section 6B, the Welsh Ministers must lay a draft of a Welsh statutory instrument containing such regulations before Senedd Cymru before the end of the period of 2 years beginning with the day on which the review was completed.
(12)A review is completed for the purpose of subsections (4)(b), (5) and (11) when the statement required by subsection (9) is published.
6HRevoking or lowering targets#
(1)The Welsh Ministers may not make regulations under section 6B that revoke or lower a target (the “existing target”) unless they are satisfied that—
(a)because of changes to the evidence to which they had regard when setting the existing target, meeting it would not contribute to halting and reversing the decline in biodiversity or to restoring biodiversity to resilient levels,
(b)meeting the existing target would have no significant benefit compared with not meeting it or with meeting a lower target,
(c)because of changes in circumstances since the existing target was set, the environmental, social, economic or other costs of meeting it would be disproportionate to the benefits, or
(d)meeting the existing target is no longer achievable—
(i)because of changes in circumstances since the existing target was set, or
(ii)because of changes to the evidence to which the Welsh Ministers had regard when setting the existing target.
(2)If the Welsh Ministers are satisfied that—
(a)the costs of meeting the existing target would be disproportionate to the benefits as mentioned in subsection (1)(c), or
(b)meeting the existing target is no longer achievable as mentioned in subsection (1)(d),
they must, before making regulations under section 6B that revoke the target, consider whether to make regulations that lower the target.
(3)Before making regulations under section 6B that revoke or lower a target, the Welsh Ministers must lay before Senedd Cymru, and publish, a statement explaining why the Welsh Ministers are satisfied as mentioned in subsection (1).
(4)Regulations lower a target if, to any extent, they—
(a)replace the specified standard with a lower standard, or
(b)replace the specified date with a later date.
(5)This section does not apply to provisions in regulations under section 6B that revoke a target that has been met.
6IStatement about targets#
(1)On or before the specified date in relation to each target set under regulations under section 6B, the Welsh Ministers must lay before Senedd Cymru, and publish, a statement containing the required information.
(2)The required information is (as appropriate)—
(a)that the target has been met,
(b)that the target has not been met, or
(c)that the Welsh Ministers are not yet able to determine whether the target has been met, the reasons for that and the steps the Welsh Ministers intend to take in order to determine whether the target has been met.
(3)Where the Welsh Ministers make a statement that a target has not been met, the Welsh Ministers must, before the end of 6 months beginning with the date on which the statement is laid, lay before Senedd Cymru, and publish, a report.
(4)The report must—
(a)explain why the target has not been met, and
(b)set out the steps the Welsh Ministers have taken, or intend to take, to ensure the target is met as soon as reasonably practicable.
(5)Before deciding on the steps referred to in subsection (4)(b), the Welsh Ministers must seek advice from persons they consider to be independent and to have relevant expertise.
(6)The Welsh Ministers must publish a summary of any such advice they receive.
(7)Where the Welsh Ministers make a statement that they are not yet able to determine whether a target has been met, the Welsh Ministers must, before the end of 6 months beginning with the date on which the statement is laid, lay before Senedd Cymru, and publish, a further statement containing the required information.
(8)Subsections (2) to (7) apply to further statements under subsection (7) as they apply to a statement under subsection (1).
Experimental schemes
22Power to suspend statutory requirements for experimental schemes#
(1)On the application of NRW, the Welsh Ministers may by regulations make provision in relation to Wales—
(a)conferring on any person exemption from a statutory requirement for which NRW is responsible;
(b)relaxing any such requirement r in its application to a person;
(c)requiring a person to whom an exemption or relaxation applies to comply with conditions specified in the regulations;
(d)modifying an enactment in a way the Welsh Ministers consider necessary for the enforcement of, or in consequence of, any provision made by virtue of paragraphs (a) to (c)?.
(2)Regulations under subsection (1) may not make provision removing or modifying a function of a Minister of the Crown that was exercisable by a Minister of the Crown before 5 May 2011 unless the Secretary of State consents to the provision.
(3)Before making provision under subsection (1), the Welsh Ministers—
(a)must be satisfied that the provision is necessary to enable an experimental scheme that is likely to contribute to the sustainable management of natural resources to be carried out,
(b)must be satisfied that the regulations will not have the overall effect of increasing the regulatory burden on any person, and
(c)must consult—
(i)persons they think are likely to be affected by provision in the regulations, and
(ii)persons they think are likely to be otherwise affected by the experimental scheme.
(4)Regulations under subsection (1) have effect during a period specified in the regulations which must not exceed three years.
(5)But regulations under subsection (1) may, on one occasion only, extend the period for which previous regulations under that subsection have effect by a period of not more than three years from the end of the period specified in the previous regulations.
(6)Where the only substantive effect of regulations under subsection (1) is to revoke previous regulations under that subsection, the regulations may be made without an application from NRW.
(7)And subsection (3) does not apply to provisions in regulations under subsection (1) which revoke previous regulations under that subsection (whether or not NRW applies for the revocation).
(8)Where provision has been made under subsection (1) to enable an experimental scheme to be carried out, NRW must—
(a)evaluate the scheme at such time as it considers appropriate, and
(b)publish a report setting out the evaluation and describing any action that NRW considers should be taken in light of it.
(9)For the purposes of this section—
(a)a statutory requirement is a requirement imposed by an enactment;
(b)NRW is responsible for a statutory requirement if—
(i)it is a requirement to comply with a standard set or requirement imposed by NRW,
(ii)it is a requirement to obtain a licence or other authorisation from NRW before doing something,
(iii)it is a requirement that may be enforced by NRW, or
(iv)it is a requirement that applies to NRW and is concerned with the way in which, or the purposes for which, natural resources are managed or used.
(10)In this section, “experimental scheme” means a scheme carried out under arrangements made by NRW under article 10C of the Natural Resources Body for Wales (Establishment) Order 2012 (S.I. 2012/1903).
23Power of NRW to conduct experimental schemes etc.#
In the Natural Resources Body for Wales (Establishment) Order 2012 (S.I. 2012/1903), for article 10C substitute—“10C 1 The Body may make arrangements for the carrying out (whether by the Body or by other persons) of research and experimental schemes that are relevant to the exercise of its functions.2 The Body may provide support (by financial means or otherwise) for research and experimental schemes that are relevant to the exercise of its functions; and paragraphs (2) and (3) of article 10B apply to the giving of financial assistance under this paragraph.3 In carrying out activities under this article relating to nature conservation, the Body must have regard to any common standards established under section 34(2)(c) of the Natural Environment and Rural Communities Act 2006 in so far as they are applicable to the activities.4 In this article—• “experimental scheme” (“cynllun arbrofol”) means a scheme designed—(a) to develop or apply new or modified methods, concepts or techniques, or(b) to develop or test proposals for regulatory change;• “research” (“ymchwil”) includes inquiries and investigations.”
Land management agreements
16Power to enter into land management agreements#
(1)NRW may make an agreement with a person who has an interest in land in Wales about the management or use of the land (a “land management agreement”), if doing so appears to it to promote the achievement of any objective it has in the exercise of its functions.
(2)A land management agreement may, among other things—
(c)provide for the carrying out of such work as may be expedient for the purposes of the agreement by any person or persons;
(d)provide for any matter for which a management scheme relating to a site of special scientific interest provides (or could provide);
(e)provide for the making of payments by either party to the other party or to any other person;
(f)contain incidental and consequential provision.
(3)In this section—• “interest in land” (“buddiant mewn tir”) includes any estate in land and any right over land, whether the right is exercisable by virtue of ownership of an interest in land or by virtue of a licence or agreement, and in particular includes sporting rights;• “management scheme” (“cynllun rheoli”) has the meaning given by Part 2 of the Wildlife and Countryside Act 1981 (c. 69) (see section 28J);• “site of special scientific interest” (“safle o ddiddordeb gwyddonol arbennig”) has the meaning given by Part 2 of the Wildlife and Countryside Act 1981 (see section 52(1)).
17Effect on successors in title of certain land management agreements#
(1)Where a land management agreement is made with a person with a qualifying interest in land subject to the agreement which is not registered land, and the agreement provides that the provisions of this subsection have effect in relation to the agreement—
(b)the provisions of section 4 of that Act (which relates to the effect of non-registration) apply as if the agreement were such a land charge, and
(c)subject to the provisions of section 4 of that Act, the agreement is binding upon any successor of the person with the qualifying interest to the same extent as it is binding upon that person, despite the fact that it would not have been binding upon that successor apart from the provisions of this subsection.
(2)Where a land management agreement is made with a person with a qualifying interest in land subject to the agreement which is registered land, and the agreement provides that the provisions of this subsection have effect in relation to the agreement—
(a)the agreement may be the subject of a notice in the register of title under the Land Registration Act 2002 (c. 9) as if it were an interest affecting the registered land,
(b)the provisions of sections 28 to 30 of that Act (effect of dispositions of registered land on priority of adverse interests) apply as if the agreement were such an interest, and
(c)subject to the provisions of those sections, the agreement is binding upon any successor of the person with the qualifying interest to the same extent as it is binding upon that person, despite the fact that it would not have been binding upon that successor apart from the provisions of this subsection.
(3)A person has a qualifying interest in land for the purpose of this section if the interest is—
(a)an estate in fee simple absolute in possession;
(b)a term of years absolute granted for a term of more than seven years from the date of the grant and in the case of which some part of the period for which the term of years was granted remains unexpired.
(4)In this section—• “registered land” (“tir cofrestredig”) has the same meaning as in the Land Registration Act 2002;• “successor” (“olynydd”), in relation to an agreement with a person with a qualifying interest in any land, means a person deriving title or otherwise claiming under that person with a qualifying interest, otherwise than in right of an interest or charge to which the interest of the person with the qualifying interest was subject immediately before—(a) the time when the agreement was made, where the land is not registered land, or(b) the time when the notice of the agreement was registered, where the land is registered land.
18Application of Schedule 2 to the Forestry Act 1967 to land management agreements#
Schedule 2 to the Forestry Act 1967 (c. 10) (power for tenant for life and others to enter into forestry dedication covenants) applies to land management agreements as it applies to forestry dedication covenants.
19Effect of agreements on dedication of highway and grant of easement#
For the purposes of any enactment or rule of law as to the circumstances in which the dedication of a highway or the grant of an easement may be presumed, or may be established by prescription, the use by the public or by any person of a way across land by virtue of a land management agreement is to be disregarded.
20Transitional provisions#
(1)An agreement relating to land in Wales entered into by NRW, or any predecessor of that body, under a disapplied enactment is to be treated as a land management agreement.
(2)The disapplied enactments are—
(a)section 16 of the National Parks and Access to the Countryside Act 1949 (c. 97);
(b)section 15 of the Countryside Act 1968 (c. 41);
(c)section 39 of the Wildlife and Countryside Act 1981 (c. 69).
21Crown land#
(1)The appropriate authority may enter into a land management agreement as respects an interest in Crown land held by or on behalf of the Crown.
(2)A land management agreement as respects any other interest in Crown land is of no effect unless approved by the appropriate authority.
(3)“Crown land” means land an interest in which—
(a)belongs to Her Majesty in right of the Crown,
(b)belongs to Her Majesty in right of the Duchy of Lancaster,
(c)belongs to the Duchy of Cornwall, or
(d)belongs to a government department or is held in trust for Her Majesty for the purposes of a government department.
(4)“The appropriate authority”, in relation to any land, means—
(b)if the land belongs to Her Majesty in right of the Duchy of Lancaster, the Chancellor of the Duchy;
(c)if the land belongs to the Duchy of Cornwall, such person as the Duke of Cornwall, or the possessor for the time being of the Duchy of Cornwall, appoints;
(d)if the land belongs to a government department or is held in trust for Her Majesty for the purposes of a government department, that department.
(5)If any question arises under this section as to what authority is the appropriate authority in relation to any land, that question is to be referred to the Treasury, whose decision is final.
Duties of the Welsh Ministers
8ADuty to promote awareness of biodiversity#
The Welsh Ministers must take steps to promote awareness in Wales of the importance of biodiversity and of the threats to biodiversity.
9Duty to prepare, publish and implement national natural resources policy#
(1)The Welsh Ministers must prepare and publish a document setting out their general and specific policies for contributing to achieving sustainable management of natural resources in relation to Wales (the “national natural resources policy”).
(2)The national natural resources policy must set out what the Welsh Ministers consider to be the key priorities, risks and opportunities for sustainable management of natural resources in relation to Wales, including what they consider should be done in relation to climate change and biodiversity.
(3)The Welsh Ministers may include anything in the national natural resources policy which they consider relevant to achieving sustainable management of natural resources in relation to Wales.
(4)The Welsh Ministers must—
(a)take all reasonable steps to implement the national natural resources policy, and
(b)encourage others to take such steps.
(5)The Welsh Ministers must publish the first national natural resources policy before the end of 10 months starting with the day this section comes into force.
(6)The Welsh Ministers—
(a)must review the national natural resources policy after each general election, and
(b)may review the policy at any other time.
(7)The Welsh Ministers may at any time revise the national natural resources policy and must publish the national natural resources policy as revised.
(8)In exercising their functions under this section, the Welsh Ministers must apply the principles of sustainable management of natural resources.
(9)In preparing or revising the national natural resources policy, the Welsh Ministers must have regard to the most recent report under section 8 on the state of natural resources in relation to Wales.
(10)When the Welsh Ministers publish the national natural resources policy (or a revised policy), they must also publish a report summarising—
(a)any consultation that was carried out in preparing the policy, and
(b)any representations that were received as a result of the consultation.
(11)In subsection (6), “general election” means a poll held at an ordinary general election under section 3 of the Government of Wales Act 2006 (c. 32) or an extraordinary general election under section 5 of that Act.
State of natural resources report
8Duty to prepare and publish state of natural resources report#
(1)NRW must prepare and publish reports in accordance with this section containing its assessment of the state of natural resources in relation to Wales.
(2)Each report must, among other things, set out—
(a)NRW's assessment of the extent to which sustainable management of natural resources is being achieved;
(b)NRW's assessment of biodiversity (including the living organisms and types of habitat included in any list published under section 7);
(c)what NRW considers to be the main trends and factors that are affecting, and are likely to affect, the state of natural resources;
(d)any aspects of the state of natural resources about which NRW considers that it does not have sufficient information to make an assessment.
(3)NRW must publish its first report before the end of four months starting with the day this section comes into force.
(4)Subsequently, NRW must publish a report before the end of the calendar year preceding a year in which an ordinary general election is due to be held.
(5)NRW must publish a draft of each report required by subsection (4) before the end of the calendar year preceding the year in which the report must be published.
(6)In this section, “ordinary general election” means the poll held at an ordinary general election under section 3 of the Government of Wales Act 2006 (c. 32).
Part 2 · Climate change
Introduction
Compliance with carbon budgets: reports and statements by the Welsh Ministers
39Proposals and policies for meeting carbon budget#
(1)The Welsh Ministers must prepare and publish a report for each budgetary period setting out their proposals and policies for meeting the carbon budget for that period.
(2)The report must set out proposals and policies covering the areas of responsibility of each of the Welsh Ministers.
(3)The Welsh Ministers must—
(a)publish the report for the first budgetary period as soon as reasonably practicable after setting the carbon budget for that period;
(b)publish the report for the second and later budgetary periods before the end of the first year of the period in question.
40Carrying amounts from one budgetary period to another#
(1)The Welsh Ministers may decide to carry part of the carbon budget for a budgetary period back to the preceding budgetary period.
(2)The carbon budget for the later period is reduced, and that for the earlier period is increased, by the amount carried back.
(3)The amount carried back must not exceed 1% of the carbon budget for the later period.
(4)The Welsh Ministers may decide to carry any unused part of the carbon budget for a budgetary period forward to the next budgetary period.
(5)The carbon budget for the later period is increased, and that for the earlier period is reduced, by the amount carried forward.
(6)The carbon budget for a period is “unused” to the extent that it exceeds the net Welsh emissions account for the period.
(7)Before deciding to carry an amount back or forward under this section, the Welsh Ministers must consult the advisory body.
41Final statement for budgetary period#
(1)The Welsh Ministers must—
(a)prepare a final statement for each budgetary period in accordance with this section, and
(b)lay the statement before the National Assembly for Wales before the end of the second year after the period to which it relates.
(2)A final statement under this section must state, in respect of each greenhouse gas, the total amount of Welsh emissions, Welsh removals and net Welsh emissions for the budgetary period to which the statement relates.
(3)It must—
(a)state the total amount of carbon units that have been credited to or debited from the net Welsh emissions account for the period, and
(b)give details of the number and type of those units.
(4)It must state the final amount of the net Welsh emissions account for the period.
(5)It must state whether the Welsh Ministers have decided to carry an amount back or forward under section 40 so as to increase or reduce the carbon budget for the period, and if so must state the amount carried back or forward.
(6)It must state the final amount of the carbon budget for the period.
(7)Whether the carbon budget for the period has been met is to be determined by reference to the information in the statement.
(8)The statement must explain what the Welsh Ministers consider to be the reasons why the carbon budget for the period has, or has not, been met.
(9)In particular, it must include the Welsh Ministers' assessment of the extent to which their proposals and policies for meeting the carbon budget for the period—
(a)have been carried out, and
(b)have contributed to the carbon budget for the period being met (or not being met).
(10)The assessment must cover the areas of responsibility of each of the Welsh Ministers.
(11)A statement under this section must also include—
(a)an estimate of the total amount of Welsh consumer emissions for the budgetary period to which the statement relates, and
(b)an explanation of how the Welsh Ministers have calculated the estimate.
42Proposals and policies where carbon budget not met#
(1)This section applies if the Welsh Ministers have laid a final statement before the National Assembly for Wales in respect of a budgetary period for which the net Welsh emissions account exceeds the carbon budget.
(2)No later than three months after laying the statement, the Welsh Ministers must lay before the National Assembly for Wales a report setting out proposals and policies to compensate for the excess emissions in later budgetary periods.
Compliance with emissions targets: statements by the Welsh Ministers
43Statements for interim target years and 2050#
(1)The Welsh Ministers must—
(a)prepare a statement for each interim target year and for the year 2050 in accordance with this section, and
(b)lay each statement before the National Assembly for Wales before the end of the second year after the year to which it relates.
(2)A statement under this section must state, in respect of each greenhouse gas, the total amount of Welsh emissions, Welsh removals and net Welsh emissions for the year to which the statement relates.
(3)It must—
(a)state the total amount of carbon units that have been credited to or debited from the net Welsh emissions account for the year, and
(b)give details of the number and type of those units.
(4)It must state the amount of the net Welsh emissions account for the year.
(5)Whether an interim emissions target or the 2050 emissions target has been met is to be determined by reference to the information in the statement for the year to which the target relates.
(6)The statement must explain what the Welsh Ministers consider to be the reasons why the target has, or has not, been met.
(7)A statement A under this section for a year may be combined with the statement under section 41 for the budgetary period that includes that year.
Emissions targets and carbon budgets: main duties of the Welsh Ministers
29The 2050 emissions target#
(1)The Welsh Ministers must ensure that the net Welsh emissions account for the year 2050 is at least 100% lower than the baseline.
(2)For the meaning of the “net Welsh emissions account” see section 33, and for the meaning of the “baseline” see section 38.
(3)The Welsh Ministers may by regulations amend subsection (1) so that it specifies a percentage greater than 80%.
(4)In this Part, the target in subsection (1) is referred to as the “2050 emissions target”.
30Interim emissions targets#
(1)For each interim target year, the Welsh Ministers must by regulations set a maximum amount for the net Welsh emissions account, expressed as a percentage below the baseline (an “interim emissions target”).
(2)The Welsh Ministers must ensure that the net Welsh emissions account for each interim target year does not exceed the interim emissions target for that year.
(3)The interim target years are 2020, 2030 and 2040.
(4)The Welsh Ministers must set the interim emissions targets before the end of 2018.
31Carbon budgets#
(1)For each budgetary period, the Welsh Ministers must by regulations set a maximum total amount for the net Welsh emissions account (a “carbon budget”).
(2)The Welsh Ministers must ensure that the net Welsh emissions account for each budgetary period does not exceed the carbon budget for that period.
(3)The budgetary periods are—
(a)2016 to 2020, and
(b)each succeeding period of five years, ending with 2046 to 2050.
(4)The Welsh Ministers must—
(a)set the carbon budgets for the first two budgetary periods before the end of 2018, and
(b)set the carbon budget for the third and later budgetary periods at least five years before the start of the period in question.
32Emissions targets and carbon budgets: principles#
(1)The Welsh Ministers must—
(a)set each interim emissions target at a level that they are satisfied is consistent with meeting the 2050 emissions target, and
(b)set the carbon budget for each budgetary period at a level that they are satisfied is consistent with meeting—
(i)the 2050 emissions target, and
(ii)the interim emissions target for any interim target year that falls within or after that budgetary period.
(2)The Welsh Ministers may not make regulations changing the 2050 emissions target, an interim emissions target or a carbon budget unless at least one of the following conditions is met—
(a)they are satisfied that it is appropriate to make the change as a result of significant developments in—
(i)scientific knowledge about climate change, or
(ii)EU or international law or policy relating to climate change;
(b)the change has been recommended by the advisory body;
(c)the change is in connection with provision made under section 35(1) or 37(2).
(3)When making regulations changing the 2050 emissions target, or setting or changing an interim emissions target or a carbon budget, the Welsh Ministers must have regard to—
(a)the most recent report under section 8 on the state of natural resources in relation to Wales,
(b)the most recent future trends report under section 11 of the Well-being of Future Generations (Wales) Act 2015 (anaw 2),
(c)the most recent report (if any) under section 23 of that Act (future generations report),
(d)scientific knowledge about climate change,
(e)technology relevant to climate change, and
(f)EU and international law and policy relating to climate change (including international agreements on measures designed to limit increases in global average temperatures).
(4)Sections 49 and 50 make provision about advice that the Welsh Ministers must obtain from the advisory body and take into account before making regulations changing the 2050 emissions target or setting or changing an interim emissions target or a carbon budget.
Functions of advisory body: reports and advice
44Advisory body#
(1)The Welsh Ministers may by regulations—
(a)establish a body corporate to exercise the functions of the advisory body under this Part, or
(b)designate a person to be the advisory body for the purposes of this Part.
(2)The regulations may designate a person only if the person exercises functions of a public nature.
(3)If no regulations under subsection (1) are in force, the advisory body is the Committee on Climate Change established under section 32 of the Climate Change Act 2008 (c. 27).
(4)Regulations under subsection (1)(a) may, in particular, include provision about—
(a)the status and membership of the body established by the regulations;
(b)the employment of staff by the body;
(c)remuneration, allowances and pensions for members and staff;
(d)the organisation and procedure of the body;
(e)reports and accounts (including audit).
(5)Regulations under subsection (1)(a) may enable the Welsh Ministers to give directions to the body in relation to the matters mentioned in subsection (4).
(6)Regulations under subsection (1) may make incidental, supplementary, consequential, transitional or saving provision, which may include provision amending, repealing or revoking an enactment.
45Progress reports#
(1)Before the end of the first budgetary period, the advisory body must send a report to the Welsh Ministers setting out the body's views on—
(a)the progress that has been made towards meeting—
(i)the carbon budgets that have been set under this Part,
(ii)the interim emissions targets , and
(iii)the 2050 emissions target,
(b)whether those budgets and targets are likely to be met, and
(c)any further measures that are needed to meet those budgets and targets.
(2)No later than six months after the Welsh Ministers lay the final statement for a budgetary period before the National Assembly for Wales under section 41, the advisory body must send a report to the Welsh Ministers setting out the body's views on—
(a)the way in which the carbon budget for the period was or was not met,
(b)the action taken by the Welsh Ministers to reduce net Welsh emissions of greenhouse gases during the period, and
(c)the matters set out in subsection (1).
(3)No later than six months after the Welsh Ministers lay the statement under section 43 relating to 2030 before the National Assembly for Wales, the advisory body must send a report to the Welsh Ministers setting out the body's views on—
(a)whether the interim emissions target for 2040 and the 2050 emissions target are the highest achievable targets, and
(b)if either of them is not the highest achievable target, what is the highest achievable target.
(4)No later than six months after the Welsh Ministers lay the statement under section 43 relating to 2040 before the National Assembly for Wales, the advisory body must send a report to the Welsh Ministers setting out the body's views on—
(a)whether the 2050 emissions target is the highest achievable target, and
(b)if not, what is the highest achievable target.
(5)A report under subsection (3) or (4) may be combined with a report under subsection (2).
(6)The Welsh Ministers must lay a copy of each report they receive under this section before the National Assembly for Wales.
(7)The Welsh Ministers must lay a response to the points raised by the report before the National Assembly for Wales no later than six months after receiving the report.
46Duty of advisory body to provide advice and assistance#
If requested to do so by the Welsh Ministers, the advisory body must provide the Welsh Ministers with advice, analysis, information or other assistance that is relevant to—
(a)the exercise of the Welsh Ministers' functions under this Part, or
(b)any other matters relating to climate change.
Measurement and interpretation
51Measurement of emissions#
(1)For the purposes of this Part, each of the following must be measured or calculated in tonnes of carbon dioxide equivalent—
(a)emissions of greenhouse gases;
(b)reductions in greenhouse gas emissions;
(c)removals of greenhouse gases from the atmosphere.
(2)A “tonne of carbon dioxide equivalent” means one metric tonne of carbon dioxide or an amount of any other greenhouse gas with an equivalent global warming potential (calculated consistently with international carbon reporting practice).
52International carbon reporting practice#
In this Part, “international carbon reporting practice” means accepted practice in relation to reporting for the purposes of—
(a)the protocols to the United Nations Framework Convention on Climate Change, or
(b)such other international agreements or arrangements, or obligations under EU law, as the Welsh Ministers may specify by regulations.
53General interpretation of this Part#
In this Part—• “2050 emissions target” (“targed allyriadau 2050”) has the meaning given by section 29;• “advisory body” (“corff cynghori”) is to be interpreted in accordance with section 44;• “baseline” (“gwaelodlin”) has the meaning given by section 38;• “budgetary period” (“cyfnod cyllidebol”) has the meaning given by section 31(3);• “carbon budget” (“cyllideb garbon“) has the meaning given by section 31(1);• “carbon unit” (“uned garbon”) has the meaning given by section 36(1);• “emissions” (“allyriadau”), in relation to a greenhouse gas, means emissions of that gas into the atmosphere that are attributable to human activity;• “EU law” (“cyfreithiau'r UE”) means—(a) all the rights, powers, liabilities, obligations and restrictions from time to time created or arising by or under the EU Treaties, and(b) all the remedies and procedures from time to time provided for by or under the EU Treaties;• “greenhouse gas” (“nwy tŷ gwydr”) has the meaning given by section 37;• “interim emissions target” (“targed allyriadau interim”) has the meaning given by section 30(1);• “interim target year” (“blwyddyn darged interim”) has the meaning given by section 30(3);• “international carbon reporting practice” (“arferion rhyngwladol adrodd ar garbon”) has the meaning given by section 52;• “net Welsh emissions” (“allyriadau net Cymru”) has the meaning given by section 34(1);• “net Welsh emissions account” (“cyfrif allyriadau net Cymru”) has the meaning given by section 33;• “Welsh emissions” (“allyriadau Cymru”) has the meaning given by section 34(2);• “Welsh removals” (“echdyniadau Cymru”) has the meaning given by section 34(3).
Regulations: procedure and advice
48Regulations: procedure#
(1)A power to make regulations under this Part is to be exercised by statutory instrument.
(2)A statutory instrument is subject to annulment in pursuance of a resolution of the National Assembly for Wales if it contains only—
(b)regulations under section 52.
(3)Any other statutory instrument containing regulations under this Part may not be made unless a draft of the instrument has been laid before, and approved by resolution of, the National Assembly for Wales.
49Requirement to obtain advice about proposals to make regulations#
(1)Before laying draft regulations before the National Assembly for Wales in accordance with section 48, the Welsh Ministers must—
(a)request advice from the advisory body about the proposal to make the regulations, and
(b)take the advisory body's advice into account.
(2)When the Welsh Ministers request advice from the advisory body under this section, they must specify a reasonable period within which the advice must be provided.
(3)The advisory body must provide the advice within that period.
(4)The advisory body's advice must set out the reasons for the advice.
(5)The Welsh Ministers must publish the advisory body's advice as soon as reasonably practicable after receiving it.
(6)If the draft regulations laid before the National Assembly for Wales make different provision from that recommended by the advisory body, the Welsh Ministers must also lay before the National Assembly a statement setting out the reasons why.
(7)This section does not apply to regulations under section 44.
50Advice about proposed regulations relating to targets and budgets#
(1)When the advisory body provides the Welsh Ministers with advice about a proposal to make regulations under section 29 changing the 2050 emissions target or regulations under section 30 setting or changing an interim emissions target, the advice must include the advisory body's opinion as to—
(a)whether the target proposed by the Welsh Ministers is the highest achievable target, and
(b)if not, what is the highest achievable target.
(2)When the advisory body provides the Welsh Ministers with advice about a proposal to make regulations under section 31 setting or changing a carbon budget for a budgetary period, the advice must include the advisory body's opinion as to—
(a)the appropriate level of the carbon budget for the period;
(b)the extent to which the carbon budget for the period should be met—
(i)by reducing the amount of net Welsh emissions of greenhouse gases, or
(ii)by the use of carbon units that in accordance with regulations under sections 33 and 36 may be credited to the net Welsh emissions account for the period;
(c)the respective contributions towards meeting the carbon budget for the period that should be made—
(i)by the sectors of the Welsh economy covered by trading schemes (taken as a whole);
(ii)by the sectors of the Welsh economy not so covered (taken as a whole);
(d)the sectors of the Welsh economy in which there are particular opportunities for contributions to be made towards meeting the carbon budget for the period through reductions in emissions of greenhouse gases.
(3)When advising the Welsh Ministers about a proposal to make regulations changing the 2050 emissions target, or setting or changing an interim emissions target or a carbon budget, the advisory body must have regard to the matters mentioned in section 32(3).
(4)In subsection (2), “trading scheme” has the meaning given by section 44 of the Climate Change Act 2008 (c. 27).
Targets and budgets: scope and main concepts
33The net Welsh emissions account#
(1)The “net Welsh emissions account” for a period is the amount calculated as follows—
(a)determine the amount of net Welsh emissions of greenhouse gases for the period in accordance with section 34;
(b)subtract the amount of carbon units credited to the net Welsh emissions account for the period;
(c)add the amount of carbon units debited from the net Welsh emissions account for the period.
(2)The Welsh Ministers may by regulations make provision about—
(a)the circumstances in which carbon units may be credited to the net Welsh emissions account for a period;
(b)the circumstances in which carbon units must be debited from the net Welsh emissions account for a period;
(c)how this is to be done.
(3)The regulations must contain provision for ensuring that carbon units that are credited to the net Welsh emissions account for a period cease to be available to offset other greenhouse gas emissions.
(4)The Welsh Ministers must by regulations set a limit on the net amount of carbon units by which the net Welsh emissions account for a period may be reduced as a result of applying subsection (1)(b) and (c).
(5)The regulations may provide that carbon units of a description specified in the regulations do not count towards the limit.
34Net Welsh emissions#
(1)In this Part, the “net Welsh emissions” of a greenhouse gas for a period means the amount of Welsh emissions of that gas for the period, reduced by the amount of Welsh removals of that gas for the period.
(2)“Welsh emissions” of a greenhouse gas are—
(a)emissions of that gas from sources in Wales, and
(b)emissions of that gas from international aviation or international shipping that count as Welsh emissions by virtue of regulations under section 35.
(3)“Welsh removals” of a greenhouse gas are removals of that gas from the atmosphere due to land use in Wales, land-use change in Wales or forestry activities in Wales.
(4)The amounts of Welsh emissions and Welsh removals of a greenhouse gas for a period must, so far as reasonably practicable, be determined consistently with international carbon reporting practice.
35Welsh emissions from international aviation and shipping#
(1)The Welsh Ministers may by regulations make provision for emissions of a greenhouse gas from international aviation and international shipping to count as Welsh emissions of the gas.
(2)The regulations may—
(a)specify activities which are to be regarded as international aviation or international shipping;
(b)specify the circumstances in which, and the extent to which, emissions of a greenhouse gas from international aviation or international shipping are to count as Welsh emissions of that gas;
(c)specify the period (whether past or future) from which emissions of a greenhouse gas from international aviation or international shipping are to count as Welsh emissions of that gas;
(d)make provision about how emissions of a greenhouse gas from international aviation or international shipping are to be taken into account in determining Welsh emissions of that gas for the baseline year for that gas;
(e)make different provision for different greenhouse gases and different periods.
36Carbon units#
(1)In this Part, a “carbon unit” means a unit of a kind specified in regulations made by the Welsh Ministers and representing—
(a)a reduction in an amount of greenhouse gas emissions,
(b)the removal of an amount of greenhouse gas from the atmosphere, or
(c)an amount of greenhouse gas emissions allowed under a scheme or arrangement imposing a limit on such emissions.
(2)The Welsh Ministers may by regulations make provision for a scheme—
(a)for registering or otherwise keeping track of carbon units, or
(b)for establishing and maintaining accounts in which carbon units may be held, and between which they may be transferred, by the Welsh Ministers.
(3)The regulations may, in particular, provide for an existing scheme to be adapted for these purposes (including by amending any enactment relating to the existing scheme).
(4)The regulations may make provision—
(a)appointing a person (an “administrator”) to administer the scheme;
(b)conferring or imposing functions on the administrator for that purpose (including by amending any enactment relating to the administrator);
(c)conferring power on the Welsh Ministers to give guidance or directions to the administrator;
(d)conferring power on the Welsh Ministers to delegate the performance of any of the functions conferred or imposed on the Welsh Ministers by the regulations;
(e)requiring the payment by persons using the scheme of charges (of an amount determined by or under the regulations) towards the cost of operating it.
37Greenhouse gases#
(1)For the purposes of this Part, each of the following is a “greenhouse gas”—
(a)carbon dioxide;
(b)methane;
(c)nitrous oxide;
(d)hydrofluorocarbons;
(e)perfluorocarbons;
(f)sulphur hexafluoride;
(g)nitrogen trifluoride.
(2)The Welsh Ministers may by regulations amend subsection (1) to add a gas or modify a description of a gas.
38The baseline#
(1)In this Part, the “baseline” means the aggregate amount of net Welsh emissions of greenhouse gases for the baseline years.
(2)The baseline year for each greenhouse gas is—
(a)carbon dioxide: 1990;
(b)methane: 1990;
(c)nitrous oxide: 1990;
(d)hydrofluorocarbons: 1995;
(e)perfluorocarbons: 1995;
(f)sulphur hexafluoride: 1995;
(g)nitrogen trifluoride: 1995.
(3)The Welsh Ministers may by regulations amend subsection (2) to—
(a)specify the baseline year for a greenhouse gas added by regulations under section 37(2);
(b)modify the baseline year for a greenhouse gas.
(4)The Welsh Ministers may make provision under subsection (3)(b) only if they are satisfied that it is appropriate to do so as a result of significant developments in EU or international law or policy relating to climate change.
Part 4 · Collection and disposal of waste
Enforcement
68Civil sanctions#
(1)For the purposes of Part 3 of the Regulatory Enforcement and Sanctions Act 2008 (c. 13) (“RESA 2008”), the offences under sections 34D and 45AA of the Environmental Protection Act 1990 (as inserted by sections 65 and 66) are to be treated as having been contained in that Act immediately before the day on which RESA 2008 was passed.
(2)Section 10 of the Waste (Wales) Measure 2010 is amended as follows.
(3)In the title, for “the deposit of waste in a landfill” substitute “ offences created by regulations under sections 9 and 9A ”.
(4)In subsection (1), after “9(1)” insert “ or 9A(1) ”.
(5)In subsection (2), for “Regulations under section 9(1) may” substitute “ The power may be exercised to ”.
(6)For subsection (3) substitute—“3 But sections 39(4) and 42(6) of RESA 2008 do not apply to the provision that may be made by regulations under section 9(1) or 9A(1) by virtue of subsection (2).”
(7)In subsection (4), for “to provision made under or by virtue of regulations under subsection (2) as they apply to provision” substitute “ where regulations under section 9(1) or 9A(1) make provision by virtue of subsection (2) as they apply where provision is ”.
(8)In subsection (6), after “9(1)” insert “ or 9A(1) (as appropriate) ”.
General
69Regulations#
(1)Section 161 of the Environmental Protection Act 1990 (regulations, orders and directions) is amended in accordance with subsections (2) to (4).
(2)In subsection (1), for “National Assembly for Wales” substitute “ the Welsh Ministers ”.
(3)In subsection (2A), for “made solely by the National Assembly for Wales” substitute “ containing regulations made solely by the Welsh Ministers ”.
(4)After subsection (2A) insert—“2AA A statutory instrument containing regulations under section 34D or 45AA(10) may not be made unless a draft of the instrument has been laid before, and approved by a resolution of, the National Assembly for Wales.2AB Any other statutory instrument containing regulations made by the Welsh Ministers under this Act is subject to annulment in pursuance of a resolution of the National Assembly for Wales.”
Disposal of waste
66Prohibition on disposal of food waste to sewer#
(1)In the Environmental Protection Act 1990, after section 34C insert—“34D 1 An occupier of premises in Wales must not—a discharge food waste produced on or brought onto the premises, orb knowingly cause or knowingly permit food waste produced on or brought onto the premises to be discharged,into a public sewer or a sewer or drain communicating with a public sewer.2 Subsection (1) does not apply to an occupier of premises within paragraph (a) or (b) of section 75(5) (domestic property and caravans).3 A person commits an offence if, without reasonable excuse, the person contravenes subsection (1).4 A person who commits an offence under subsection (3) is liable on summary conviction, or on conviction on indictment, to a fine.5 In subsection (1)—• “food waste” means controlled waste that—(a) has at any time been food (which for this purpose does not include drink) intended for human consumption, or(b) is biodegradable waste arising from the processing or preparation of food or drink,but does not include waste that is mixed with water or any other liquid as a result of the water or liquid having been used to clean any place or equipment used in processing or preparing food or drink;• “drain”, “public sewer” and “sewer” have the meanings given in section 219(1) of the Water Industry Act 1991.6 The Welsh Ministers may by regulations—a provide for subsection (1) to apply only in circumstances specified in the regulations;b make provision (which may include provision amending this section) for subsection (1) to apply subject to exceptions in addition to those in subsection (2);c amend the definition of “food waste” in subsection (5).7 Regulations under subsection (6)(a) or (b) may make different provision for different purposes, different cases (including different persons, premises or types of food waste) and different areas.”
(2)In section 118 of the Water Industry Act 1991 (c. 56)—
(a)in subsection (1), after “trade premises” insert “ in England ”;
(b)after subsection (1) insert—“1A Subject to the following provisions of this Chapter and section 34D of the Environmental Protection Act 1990, the occupier of any trade premises in Wales in the area of a sewage undertaker may discharge any trade effluent proceeding from those premises into the undertaker's public sewers if the occupier does so with the undertaker's consent.”
67Power to prohibit or regulate disposal of waste by incineration#
In the Waste (Wales) Measure 2010 (nawm 8), after section 9 insert—“9A 1 The Welsh Ministers may by regulations make provision for and in connection with prohibiting or otherwise regulating the incineration in Wales of specified kinds of waste.2 Regulations under subsection (1) may (among other things)—a amend regulations made under section 2 of the Pollution Prevention and Control Act 1999 which relate to the operation of waste incineration plants or waste co-incineration plants;b provide for offences in relation to failure to comply with provision made under the regulations;c provide for penalties in relation to such offences;d provide for enforcement authorities and the functions of such authorities.3 In this section—• “incineration” (“llosgi”), in relation to waste, means—(a) incineration of the waste in a waste incineration plant or waste co-incineration plant, and(b) any other thermal treatment of the waste prior to its incineration;• “waste incineration plant” (“peiriant llosgi gwastraff”) has the meaning given in Article 3(40) of Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions (integrated pollution prevention and control) (Recast);• “waste co-incineration plant” (“peiriant cydlosgi gwastraff”) has the meaning given in Article 3(41) of that Directive.”
Separate collection etc. of waste
65Requirements relating to separate collection etc. of waste#
In the Environmental Protection Act 1990 (c. 43), after section 45A insert—“45AA 1 Where a waste collection authority in Wales arranges for the collection of controlled waste in its area under section 45, it must arrange for the waste to be collected in accordance with any applicable separation requirements.2 A person acting in the course of a business who—a collects controlled waste from premises in Wales, orb receives, keeps, treats or transports controlled waste in Wales,must do so in accordance with any applicable separation requirements.3 For the purposes of subsection (2), a person is acting in the course of a business if the person is—a carrying on any business or undertaking, whether for profit or not, orb exercising any functions of a public nature.4 An occupier of premises in Wales who presents controlled waste for collection (whether by a waste collection authority or by any other person) must do so in accordance with any applicable separation requirements.5 Subsection (4) does not apply to an occupier of premises within paragraph (a) or (b) of section 75(5) (domestic property and caravans).6 A separation requirement is a requirement to take steps specified in regulations made by the Welsh Ministers for the purpose of ensuring or maintaining the separation of one or more types of waste from other types of waste or from other substances or articles.7 A separation requirement is applicable in the circumstances specified in relation to that requirement in regulations made by the Welsh Ministers.8 A person commits an offence if the person fails without reasonable excuse to comply with subsection (2) or (4).9 A person who commits an offence under subsection (8) is liable on summary conviction, or on conviction on indictment, to a fine.10 The Welsh Ministers may by regulations make provision (which may include provision amending this section)—a for subsection (1) or (2) to apply subject to exceptions;b for subsection (4) to apply subject to exceptions in addition to those in subsection (5).11 Regulations under this section may make different provision for different purposes, different cases (including different persons, premises or types of waste) and different areas.45AB 1 The Welsh Ministers may issue one or more codes of practice for the purpose of giving practical guidance about how to comply with requirements imposed by or under section 45AA.2 The Welsh Ministers may revoke or revise a code of practice issued under this section.3 Before issuing a code of practice (or revised code), the Welsh Ministers must consult such persons as they think appropriate.4 Where the Welsh Ministers issue a code of practice (or revised code) they must—a publish the code, andb lay a copy before the National Assembly for Wales.5 A code of practice issued under this section is admissible in evidence in any proceedings and must be taken into account by a court in determining any question to which it appears to the court to be relevant.”
Part 5 · Fisheries for shellfish
Applications for orders relating to fisheries
71Applications for orders relating to fisheries#
(1)In section 1 of the Sea Fisheries (Shellfish) Act 1967 (c. 83) (power to make orders as to fisheries for shellfish), after subsection (2) insert—“2A In relation to applications to the Welsh Ministers, subsection (2) has effect as if for “prescribed by regulations made by the appropriate Minister” there were substituted “ specified by the Welsh Ministers ”.2B The Welsh Ministers may require a person who applies to them for an order under this section to provide them with such further information as they think necessary to enable them to determine the application.”
(2)The amendment made by subsection (1) does not apply in relation to applications that have been made to the Welsh Ministers before this section comes into force.
Protection of marine environment
72Requirement to include environmental provisions in orders relating to fisheries#
(1)The Sea Fisheries (Shellfish) Act 1967 is amended as follows.
(2)After section 5 insert—“5A 1 An order made by the Welsh Ministers under section 1 of this Act must contain—a such provision (if any) as the Welsh Ministers consider appropriate for the purpose of preventing harm to any European marine site identified in the order, andb such other provision (if any) as they consider appropriate for the purpose of protecting the marine environment.2 For the purposes of this section, “the marine environment” includes—a the natural beauty or amenity of marine or coastal areas (including their geological or physiographical features);b features of archaeological or historic interest in such areas;c flora and fauna which are dependent on, or associated with, a marine or coastal environment.”
(3)In section 3, in subsection (2), for “section 4” substitute “ sections 4 and 5A ”.
73Power to serve notices for protection of European marine sites#
In the Sea Fisheries (Shellfish) Act 1967, after section 5A (as inserted by section 72) insert—“5B 1 If it appears to the Welsh Ministers that harm to a European marine site has occurred, or is likely to occur, as a result of any activity—a carried on in the exercise of a right conferred by an order made by them under section 1 of this Act, orb authorised in pursuance of provision made by or under such an order which confers a right of regulating a fishery,the Welsh Ministers may serve a site protection notice on the grantees of the order.2 A site protection notice is a notice which requires the grantees to take steps specified in the notice for the purpose of preventing harm (or further harm) to the European marine site.3 The provision that may be made by a site protection notice includes provision prohibiting, restricting or interfering with the exercise of any right conferred by the order.4 A site protection notice must—a be in writing,b set out the reasons for giving the notice, andc specify the time by which, or the period for which, the steps specified in the notice must be taken.5 The Welsh Ministers must consult the grantees of the order before serving a site protection notice on them, unless it appears to the Welsh Ministers that there is an urgent need to take steps to prevent harm (or further harm) to the European marine site.6 The Welsh Ministers may vary or cancel a site protection notice by serving notice of the variation or cancellation on the grantees of the order.7 The Welsh Ministers must publish every notice served by them under this section in such manner as they consider appropriate for the purpose of bringing the notice to the attention of persons likely to be affected by it.8 Provision under subsection (4)(c) may specify a time after, or a period which ends after, the expiry of the order; and in such a case, references in sections 5C and 5D of this Act to the grantees of the order are, in relation to any time after its expiry, references to the persons who were the grantees immediately before the order expired.9 Subsections (2) to (7) of section 5 of this Act apply for the purposes of this section as they apply for the purposes of subsection (1) of that section.5C 1 An appeal lies to the First-tier Tribunal against—a a site protection notice;b any provision of a site protection notice;c the variation of a site protection notice;d the refusal of a request for the variation or cancellation of a site protection notice.2 An appeal may be brought—a in the case of an order made under section 1 of this Act which confers a right of several fishery, by the grantees of the order;b in the case of such an order which confers a right of regulating a fishery—i by the grantees of the order, orii by a person authorised to carry on an activity in pursuance of provision made by or under the order who is affected by the site protection notice or variation.3 Where an appeal is brought by a person mentioned in subsection (2)(b)(ii), the grantees of the order are entitled to be parties to the appeal.4 The First-tier Tribunal may suspend a site protection notice, or a variation of such a notice, pending the determination of an appeal.5 On an appeal the Tribunal may confirm, vary or cancel a site protection notice.6 If the Tribunal varies or cancels the notice, it may order the Welsh Ministers to pay compensation to any other party to the appeal for loss or damage suffered by that party as a result of the notice.5D 1 If the grantees of an order made under section 1 of this Act fail to comply with a site protection notice, the Welsh Ministers may themselves do anything that could be done by the grantees for the purpose of complying with the notice.2 If the Welsh Ministers incur expenses in doing anything under subsection (1), they may recover those expenses from the grantees as a debt.”
74Power to vary or revoke orders to protect European marine sites#
(1)The Sea Fisheries (Shellfish) Act 1967 is amended as follows.
(2)After section 5D (as inserted by section 73) insert—“5E 1 This section applies where—a the Welsh Ministers have served a site protection notice on the grantees of an order made under section 1 of this Act,b the notice has not been cancelled under section 5B(6) or 5C(5) of this Act, andc no appeal under section 5C of this Act is pending.2 The Welsh Ministers may vary or revoke the order to reflect the effect of the site protection notice.3 Before making an order by virtue of this section, the Welsh Ministers must consult—a any persons who are entitled to a right of several fishery or a right of regulating a fishery in any part of the area to which the order relates, andb any other persons the Welsh Ministers think are likely to be interested in the order or affected by it.4 For the purposes of subsection (1)(c), an appeal under section 5C is pending if—a an appeal under that section (or a further appeal) has been brought and has not been determined or withdrawn, orb an appeal under that section (or a further appeal) has not been brought but the period for bringing such an appeal is still running.”
(3)In section 1 (power to make orders as to fisheries for shellfish), in subsection (8), after “subsection (10) below” insert “ or by virtue of section 5E of this Act ”.
75Supplementary provision#
In the Sea Fisheries (Shellfish) Act 1967, after section 5E (as inserted by section 74) insert—“5F 1 In sections 5A to 5E of this Act—• “European marine site” has the same meaning as in the Conservation of Habitats and Species Regulations 2010 (S.I. 2010/490) (see regulation 8);• “the grantees”, in relation to a right of several fishery, means the persons for the time being entitled to that right;• “harm”, in relation to a European marine site, means—(a) an adverse effect on the integrity of the site,(b) the deterioration of a relevant natural habitat or of the habitat of a relevant species, or(c) the disturbance of a relevant species, in so far as the disturbance could be significant in relation to the objectives of the Habitats Directive.2 For the purposes of the definition of “harm” in subsection (1)—• a “relevant” natural habitat or species is one for which the site in question has been designated or classified as a European marine site;• “the Habitats Directive” means Council Directive 92/43/EEC on the conservation of natural habitats and of wild fauna and flora.3 Sections 5A to 5E of this Act do not apply in relation to an order made under section 1 of this Act before the coming into force of Part 5 of the Environment (Wales) Act 2016.”
Part 6 · Marine licensing
76Advice and assistance in relation to marine licensing#
In the Marine and Coastal Access Act 2009 (c. 23), after section 67 insert—“67A 1 This section applies where the Welsh Ministers are the appropriate licensing authority.2 The licensing authority may provide advice or other assistance to any person who requests it in connection with—a an application which the person proposes to make to the licensing authority for a marine licence, orb any other matter in respect of which the licensing authority exercises functions under this Part.3 The licensing authority may charge fees in respect of the reasonable costs incurred by it in connection with the provision of advice or other assistance under subsection (2).”
77Fees for monitoring, variation etc. of marine licences#
(1)In the Marine and Coastal Access Act 2009, after section 72 insert—“72A 1 This section applies where the Welsh Ministers are the appropriate licensing authority in relation to a marine licence granted under this Part.2 The licensing authority may require the licensee to pay a fee for—a monitoring an activity authorised by the licence,b assessing and interpreting the results of any monitoring of an activity authorised by the licence, orc dealing with an application by the licensee for a variation, suspension, revocation or transfer of the licence under section 72.3 In subsection (2) “monitoring”, in relation to a licence, means monitoring carried out for the purposes of enabling the licensing authority to determine—a the environmental, economic or social consequences of any activity authorised by the licence, orb whether the licensee is complying with any conditions attached to that licence.4 The fees that may be charged under subsection (2) are to be determined by or in accordance with regulations made by the licensing authority.5 Regulations under subsection (4) may provide for different fees for different cases.6 If the licensing authority carries out any investigation, examination or test which in its opinion is necessary or expedient to enable it to determine an application by a licensee for a variation, suspension, revocation or transfer of a licence under section 72, the authority may require the licensee to pay a fee towards the reasonable expenses of that investigation, examination or test.7 If a licensee fails to comply with a requirement to pay a fee charged under subsection (2)(a) or (b), the licensing authority may by notice vary, suspend or revoke the licence.8 The suspension of a licence under subsection (7) continues in effect until the fee is paid (but this is subject to any provision made under section 108(3)(b) in relation to notices under that subsection).9 If a licensee who has applied for a variation, suspension, revocation or transfer of a licence under section 72 fails to comply with a requirement to pay a fee charged under this section in connection with that application, the licensing authority may—a refuse to proceed with the application, orb refuse to proceed with it until the failure is remedied.”
(2)The amendment made by subsection (1) has effect in relation to marine licences whenever granted.
78Further provision about payment of fees#
In the Marine and Coastal Access Act 2009, after section 107 insert—“107A 1 This section applies where the Welsh Ministers are the appropriate licensing authority.2 Where a person is required to pay a fee to the licensing authority under this Part, the licensing authority may require the person to pay a deposit on account of the fee.3 The amount that a person may be required to pay under subsection (2) is to be determined by or in accordance with regulations made by the licensing authority.4 If a licensee fails to comply with a requirement to pay a deposit charged under subsection (2) on account of a fee charged under section 72A(2)(a) or (b), the licensing authority may by notice vary, suspend or revoke the licence.5 The suspension of a licence under subsection (4) continues in effect until the deposit is paid (but this is subject to any provision made under section 108(3)(b) in relation to notices under that subsection).6 If a person who has applied for a licence under section 67 or for a variation, suspension, revocation or transfer of a licence under section 72 fails to comply with a requirement to pay a deposit charged under subsection (2) in connection with that application, the licensing authority may—a refuse to proceed with the application, orb refuse to proceed with it until the failure is remedied.107B 1 This section applies where the Welsh Ministers are the appropriate licensing authority.2 When making provision under section 67(2) or 72A(4) about fees payable in respect of a type of application to the licensing authority or in respect of an activity of the licensing authority, the licensing authority must decide what provision to make by reference to the expected costs of dealing with that type of application or of carrying out that activity.3 The licensing authority may require a fee charged by it under this Part to be payable in advance of the activity to which the fee relates being carried out.4 The licensing authority may waive or reduce a fee.5 The licensing authority may by regulations make provision about how and when a fee or deposit charged by it under this Part is to be paid.6 A fee or deposit charged under this Part may be recovered by the licensing authority as a civil debt (in addition to any other action that may be taken by the licensing authority).”
79Appeal against variation etc. of marine licence for non-payment of fee or deposit#
In section 108 of the Marine and Coastal Access Act 2009 (appeals against notices), after subsection (2) insert—“2A The Welsh Ministers must by regulations make provision for any person to whom a notice is issued under section 72A(7) or 107A(4) to appeal against that notice.”
80Exceptions from power to delegate licensing authority functions#
In section 98(6) of the Marine and Coastal Access Act 2009 (functions excepted from power to delegate)—
(a)after paragraph (c) insert—“ca section 72A(4) (making regulations regarding fees for monitoring, variation etc of licences for which the Welsh Ministers are the licensing authority);”
(b)after paragraph (h) insert—“ha section 107A(3) (making regulations regarding deposits payable on account of fees where the Welsh Ministers are the licensing authority);hb section 107B(5) (making regulations regarding payment of fees and deposits where the Welsh Ministers are the licensing authority);”
Part 7 · Miscellaneous
Byelaws
86Byelaws made by the Natural Resources Body for Wales#
Part 5 of Schedule 2 contains amendments relating to byelaws made by the Natural Resources Body for Wales.
Flood and Coastal Erosion Committee
81Establishment of Flood and Coastal Erosion Committee#
(1)In the Flood and Water Management Act 2010 (c. 29), before section 27 (and the italic cross-heading before it) insert—“26B 1 There is established a committee to be known as the Flood and Coastal Erosion Committee or Pwyllgor Llifogydd ac Erydu Arfordirol.2 The purpose of the Committee is to advise the Welsh Ministers on matters relating to flood and coastal erosion risk management.3 The Welsh Ministers may by regulations confer or impose additional functions on the Committee for any purpose connected with flood or coastal erosion risk management in Wales.26C 1 The Welsh Ministers may by regulations make provision about the membership of the Flood and Coastal Erosion Committee, including—a the number of members,b conditions of eligibility for appointment, andc the method of selection and appointment of members (including who is to appoint them).2 The Welsh Ministers may by regulations make provision about the proceedings of the Committee, including—a quorum, andb the nature and extent of a majority required for specified purposes.26D 1 The Welsh Ministers may by regulations make provision for the payment to or in respect of persons who chair or have chaired the Flood and Coastal Erosion Committee of—a remuneration;b allowances;c sums by way of or in respect of pension;d compensation for loss of office.2 The Welsh Ministers may by regulations make provision for the payment of allowances to members of the Committee.3 Regulations under this section—a must specify who is to make any payment for which the regulations make provision;b may make provision about the circumstances in which a payment is to be made;c may determine, or provide for the determination of, the amount or maximum amount of a payment.”
(2)The Regional Flood and Coastal Committee established under section 22(1)(c) of the Flood and Water Management Act 2010 is abolished.
(3)Part 4 of Schedule 2 provides for minor and consequential amendments and repeals relating to this section.
Land drainage
82Repeal of requirements to publish in local newspapers etc.#
(1)In the Land Drainage Act 1991 (c. 59), omit—• section 2(2A);• section 3(4A);• section 38(6A);• section 39(5A);• section 48(3A);• section 58(3A);• paragraph 1(1A) of Schedule 5.
(2)In Schedule 9 to the Water Act 2014 (c. 21), omit paragraphs 2(3), 3(3), 4(3), 5(3), 6(3), 7(3) and 8(3).
84Power to make provision for appeals against special levies#
(1)The Local Government Finance Act 1988 (c. 41) is amended as follows.
(2)In section 75 (special levies), after subsection (7) insert—“7A Regulations made by the Welsh Ministers may include provision for appeals to be made to the Welsh Ministers from special levies issued to meet expenses incurred in the exercise of functions relating to land drainage.”
(3)In section 138 (judicial review)—
(a)in subsection (2)(f), after “above” insert “ (subject to subsection (4)) ”;
(b)after subsection (3) insert—“4 Subsection (1) does not affect appeals made by virtue of provision made in regulations under section 75(7A)”
(4)In section 143 (orders and regulations)—
(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b)omit subsection (4A).
(5)In Schedule 7 to the Local Government Act 2003 (c. 26), omit paragraph 24(4).
85Power of entry: compliance with order for cleansing ditches etc.#
(1)In section 29 of the Land Drainage Act 1991 (c. 59) (effect of orders requiring cleansing of ditches etc.), after subsection (1) insert—“1A Where, in the case of an order made under section 28 by the Agricultural Land Tribunal in relation to land in Wales, the Welsh Ministers, at any time after the end of three months or such longer period as may be specified in the order, have reasonable grounds for believing that any work specified in the order has not been carried out—a the Welsh Ministers, orb any person authorised by them, either generally or in a particular case,may, in order to ascertain whether the work has been carried out, enter any land which it is necessary to enter for that purpose.”
(2)The amendment made by subsection (1) has effect in relation to orders whenever made.
Part 8 · General
87Interpretation#
In this Act—• “enactment”(“deddfiad”) means a provision contained in any of the following (whenever enacted or made)—(a) an Act of Parliament;(b) a Measure or an Act of the National Assembly for Wales;(c) subordinate legislation within the meaning of the Interpretation Act 1978 (c. 30) (including subordinate legislation made under an Act of Parliament or a Measure or Act of the National Assembly for Wales);• “Wales” (“Cymru”) has the meaning given by section 158 of the Government of Wales Act 2006 (c. 32).
88Coming into force#
(1)This Part comes into force on the day on which this Act receives Royal Assent.
(2)The following provisions come into force at the end of the period of two months beginning with the day on which this Act receives Royal Assent—
(a)Part 1 (sustainable management of natural resources);
(b)Part 2 (climate change);
(c)Part 5 (fisheries for shellfish);
(d)section 82 (repeal of publication requirements);
(e)section 84 (appeals against special drainage levies);
(f)section 85 (power of entry);
(g)section 86 (byelaws).
(3)The following provisions come into force on a day appointed by the Welsh Ministers in an order made by statutory instrument—
(a)Part 3 (charges for carrier bags);
(b)Part 4 (collection and disposal of waste);
(c)Part 6 (marine licensing);
(d)section 81 (flood and coastal erosion committee);
(e)section 83 (valuation of non-agricultural land).
(4)An order under subsection (3) may—
(a)appoint different days for different purposes;
(b)make such transitional or saving provision in connection with the coming into force of a provision of this Act as the Welsh Ministers consider appropriate.
Schedule 2 · Minor and consequential amendments and repeals
Part 1 · Sustainable management of natural resources
National Parks and Access to the Countryside Act 1949 (c. 97)
(1)
(1)The National Parks and Access to the Countryside Act 1949 is amended as follows.
(2)In section 15A(2)—
(a)in paragraph (a)—
(i)after “Act” insert “ or section 16 of the 2016 Act ”;
(ii)omit the “and” at the end;
(3)In section 16—
(a)in subsection (1)—
(i)for “The Natural Resources Body for Wales” the first time it appears substitute “ A Welsh local authority ”;
(ii)for “Natural Resources Body for Wales” the second time it appears substitute “ Welsh local authority ”;
(b)after subsection (1) insert—“1A The power of a Welsh local authority in subsection (1)—a is also exercisable where it appears to the authority that it is expedient in the interests of the locality that land should be managed as a nature reserve;b is exercisable only in relation to land in the authority's area that is not held by, or managed in accordance with an agreement entered into with, the Natural Resources Body for Wales.”
(c)in subsection (3), in paragraphs (b) and (c), for “the Natural Resources Body for Wales” substitute “ a Welsh local authority ”;
(d)in subsection (4), for “the Natural Resources Body for Wales” substitute “ a Welsh local authority ”;
(e)after subsection (5) insert—“6 In this section a “Welsh local authority” means—a the council of a county or county borough in Wales, andb a National Park authority for a National Park in Wales.”
(4)In section 21(4)—
(a)omit “, the Natural Resources Body for Wales”;
(b)for “references in subsection (1) of sections sixteen and seventeen respectively of this Act to the national interest were references” substitute “ reference in subsection (1) of section 17 of this Act to the national interest were a reference ”.
Countryside Act 1968 (c. 41)
(2)
(1)The Countryside Act 1968 is amended as follows.
(2)Omit section 4.
(3)Omit section 15.
(4)In section 15A(6)(b), for “such agreement as is referred to in section 15(2)” substitute “ an agreement under section 16 of the Environment (Wales) Act 2016 imposing, for the purpose of conserving flora, fauna, or geographical or physiographical features of special interest, restrictions on the exercise of rights over land by persons having an interest in the land ”.
(5)In section 41(2)(b)—
(a)in sub-paragraph (i), for “section 4” substitute “ an experimental scheme under article 10C of the Natural Resources Body for Wales (Establishment) Order 2012 (S.I. 2012/1903), where the scheme is designed to facilitate the enjoyment of the countryside, or to conserve or enhance its natural beauty or amenity ”;
(b)in sub-paragraph (ii), for “section 4(5)(b)” substitute “ section 16 of the Environment (Wales) Act 2016 that is designed to facilitate the enjoyment of the countryside, or to conserve or enhance its natural beauty or amenity ”.
(6)In section 45(1), omit “the NRBW or”.
(7)In section 47(3), omit “section 4(5)(b) or”.
Wildlife and Countryside Act 1981 (c. 69)
(3)
(1)The Wildlife and Countryside Act 1981 is amended as follows.
(2)In section 28E(3)(b) for “, section 15 of the 1968 Act or section 7 of the Natural Environment and Rural Communities Act 2006” substitute “ , section 7 of the Natural Environment and Rural Communities Act 2006 or section 16 of the Environment (Wales) Act 2016 ”.
(3)In section 28J, omit subsection (13).
(5)In section 39(5), omit paragraph (e).
(6)Omit section 40.
(7)In section 41(5)—
(a)in the definition of “management agreement”, in paragraph (b), after “39” insert “ or under section 16 of the Environment (Wales) Act 2016 ”;
(b)in the definition of “the relevant authority”, after “Natural England” insert “ and in relation to Wales it also includes the Natural Resources Body for Wales ”.
(8)In section 50(1)(a), omit “or an agreement under section 16 of the 1949 Act or section 15 of the 1968 Act”.
(9)In section 51(1)—
(a)in paragraph (c), omit “or an agreement under section 16 of the 1949 Act or section 15 of the 1968 Act”;
(b)in paragraph (h), omit “or an agreement under section 16 of the 1949 Act or section 15 of the 1968 Act”.
Road Traffic Regulation Act 1984 (c. 27)
(4)In section 22(1)(a) of the Road Traffic Regulation Act 1984—
(a)in sub-paragraph (iv), for “or the Natural Resources Body for Wales are conducting a scheme under section 4 of the 1968 Act” substitute “ , or in which the Natural Resources Body for Wales is conducting a scheme under article 10C of the Natural Resources Body for Wales (Establishment) Order 2012 (S.I. 2012/1903) that is designed to facilitate the enjoyment of the countryside or to conserve or enhance its natural beauty or amenity ”;
(b)in sub-paragraph (v), omit “or an agreement under section 15 of the 1968 Act”.
Water Industry Act 1991 (c. 56)
(5)In section 156(8) of the Water Industry Act 1991, in the definition of “management agreement”, in paragraph (b), after “1981” insert “ or section 16 of the Environment (Wales) Act 2016 ”.
Environment Act 1995 (c. 25)
(6)
(1)The Environment Act 1995 is amended as follows.
(2)In section 9(5)(b)(ii), omit “, 5E”.
(3)In section 66, after subsection (7) insert—“7A A National Park authority for a park in Wales which is proposing to publish, adopt or review any plan under this section must have regard to—a the state of natural resources report published under section 8 of the Environment (Wales) Act 2016, andb any area statement published under section 11 of that Act for an area that includes all or part of the park.”
Countryside and Rights of Way Act 2000 (c. 37)
(7)In section 90 of the Countryside and Rights of Way Act 2000, after subsection (1) insert—“1A In the case of an area of outstanding natural beauty in Wales, a conservation board or relevant local authority which is proposing to publish, adopt or review any plan under section 89 must have regard to—a the state of natural resources report published under section 8 of the Environment (Wales) Act 2016, andb any area statement published under section 11 of that Act for an area that includes all or part of the area of outstanding natural beauty.”
Planning and Compulsory Purchase Act 2004 (c. 5)
(8)
(1)The Planning and Compulsory Purchase Act 2004 is amended as follows.
(2)In section 60(5), as substituted by section 3 of the 2015 Act, before paragraph (a) insert—“za the national natural resources policy published under section 9 of the Environment (Wales) Act 2016,”
(3)In section 62(5), after paragraph (ba), as inserted by paragraph 25 of Schedule 2 to the 2015 Act, insert—“bb any area statement published under section 11 of the Environment (Wales) Act 2016 for an area that includes all or part of the area of the authority;”
(4)In this paragraph, “the 2015 Act” means the Planning (Wales) Act 2015 (anaw 4).
Natural Environment and Rural Communities Act 2006 (c. 16)
(9)
(1)The Natural Environment and Rural Communities Act 2006 is amended as follows.
(2)In section 40—
(a)before subsection (1) insert—“A1 This section applies where—a Her Majesty's Revenue and Customs are exercising their functions;b any other public authority is exercising its functions in relation to England.”
(b)in subsection (1), for “Every” substitute “ The ”;
(c)in subsection (2) for “, government department or the National Assembly for Wales” substitute “ or government department ”;
(d)in subsection (4)—
(i)omit paragraph (b);
(ii)in paragraph (c), for “, a local planning authority and a strategic planning panel” substitute “ and a local planning authority ”;
(e)in subsection (5), in the definition of “local authority”—
(i)in paragraph (a), for “in relation to England, a county council” substitute “ a county council in England ”;
(ii)omit paragraph (b);
(f)in that subsection, omit the definition of “strategic planning panel”.
(3)Omit section 42.
(4)In Schedule 11, omit the following—
(a)paragraphs 6 to 8;
(b)paragraph 14(4);
(c)paragraphs 41 and 42;
(d)in paragraph 43—
(i)sub-paragraphs (2) and (3);
(ii)in sub-paragraph (4), paragraphs (a), (b) and (c)(i);
(iii)sub-paragraph (5);
(iv)sub-paragraph (7);
(e)paragraph 44;
(f)paragraph 50;
(g)paragraph 55(2);
(h)paragraph 57;
(i)paragraph 59;
(j)paragraph 80;
(k)paragraphs 117 to 121;
(l)paragraph 123;
(m)paragraph 126;
(n)paragraph 141(2)(b).
Well-being of Future Generations (Wales) Act 2015 (anaw 2)
(10)
(1)The Well-being of Future Generations (Wales) Act 2015 is amended as follows.
(2)In section 11(3), for the words after “means” substitute “ the goals set out in “Transforming our world: the 2030 Agenda for Sustainable Development”, adopted by the General Assembly of the United Nations by resolution A/Res/70/1 of 25 September 2015 ”.
(3)In section 38(3), after paragraph (g) insert—“ga each area statement under section 11 of the Environment (Wales) Act 2016 (if any) which relates to any part of the local authority's area;”
Planning (Wales) Act 2015 (anaw 4)
(11)In Schedule 2 to the Planning (Wales) Act 2015, omit paragraph 28.
Part 2 · Charges for carrier bags
Climate Change Act 2008 (c. 27)
Waste (Wales) Measure 2010 (nawm 8)
Part 3 · Collection and disposal of waste
Environmental Protection Act 1990 (c. 43)
(14)
(1)The Environmental Protection Act 1990 is amended as follows.
(2)In the heading of section 45A, for “Arrangements” substitute “ England: arrangements ”.
(3)Omit section 45B.
Household Waste Recycling Act 2003 (c. 29)
(15)In the Household Waste Recycling Act 2003, omit section 2.
Government of Wales Act 2006 (c. 32)
(16)In Schedule 11 to the Government of Wales Act 2006, in paragraph 35(3), in Table 1, omit the entry relating to section 45B(1) of the Environmental Protection Act 1990.
Waste (Wales) Measure 2010 (nawm 8)
(17)
(1)The Waste (Wales) Measure 2010 is amended as follows.
(2)For the italic cross-heading before section 9 substitute— “ Disposal in a landfill or by incineration ”.
(3)In section 11—
(a)in subsection (1), after “9” insert “ or 9A ”;
(b)omit subsection (2).
Part 4 · Flood and coastal erosion committee
Public Bodies (Admission to Meetings) Act 1960 (c. 67)
(18)In the Schedule to the Public Bodies (Admission to Meetings) Act 1960, in paragraph 1, after sub-paragraph (i) insert—“ia the Flood and Coastal Erosion Committee established by section 26B of the Flood and Water Management Act 2010;”
Local Government Act 1974 (c. 7)
(19)In section 25(1)(d) of the Local Government Act 1974, omit “for an area wholly or partly in England”.
Water Resources Act 1991 (c. 57)
(20)
(1)The Water Resources Act 1991 is amended as follows.
(2)In section 118(7)—
(a)before “means” insert—“—a in relation to the Agency,”
(3)In section 134(2), for “appropriate agency” substitute “ Agency ”.
(5)In section 145, in the definition of “flood risk management region”—
(a)before “means” insert—“—a in relation to the Agency,”
(6)In Schedule 26, in paragraph 7, in the definition of “the relevant Minister”, in paragraph (a)(ii), omit “the whole or the greater part of which is”.
Land Drainage Act 1991 (c. 59)
Environment Act 1995 (c. 25)
(22)In section 6 of the Environment Act 1995—
(a)in subsection (5), omit “and the Natural Resources Body for Wales' flood defence functions shall extend to the territorial sea adjacent to Wales”;
(b)after subsection (5) insert—“5A The flood defence functions of the Natural Resources Body for Wales extend to the territorial sea adjacent to Wales.”
Freedom of Information Act 2000 (c. 36)
(23)In Part 6 of Schedule 1 to the Freedom of Information Act 2000, after the entry for the Firearms Consultative Committee insert— “ Flood and Coastal Erosion Committee or Pwyllgor Llifogydd ac Erydu Arfordirol. ”
Public Services Ombudsman (Wales) Act 2005 (c. 10)
Flood and Water Management Act 2010 (c. 29)
(25)
(1)The Flood and Water Management Act 2010 is amended as follows.
(3)In section 17(4), after “section 23(3)” insert “ for the Agency ”.
(4)In the italic cross-heading before section 22, after “Committees” insert “ for regions in England ”.
(5)In section 22—
(a)in subsection (1)—
(i)for “appropriate agency” substitute “ Environment Agency ”;
(ii)omit “and Wales”;
(iii)omit the words from “that is wholly or mainly in England” to the end of the subsection;
(b)in subsection (2)—
(i)for “Minister” substitute “ Secretary of State ”;
(ii)for “appropriate agency” substitute “ Agency ”;
(c)omit subsection (3).
(6)In section 23—
(a)in subsection (1)—
(i)in the opening words, for “appropriate agency” substitute “ Environment Agency ”;
(ii)in paragraph (a), for “appropriate agency” substitute “ Agency ”;
(iii)in paragraph (b), for “appropriate agency's” substitute “Agency's”;
(b)in subsections (2) to (4), for “appropriate agency” substitute “ Agency ”.
(7)In section 24, for “Minister” substitute “ Secretary of State ”.
(8)In section 25—
(a)in subsection (1)—
(i)in the opening words, for “Minister may direct the appropriate agency” substitute “ Secretary of State may direct the Environment Agency ”;
(ii)in paragraph (d), for “Minister” substitute “ Secretary of State ”;
(b)in subsection (2), for “appropriate agency” substitute “ Agency ”;
(c)in subsection (3), for “Minister” substitute “ Secretary of State ”.
(9)Omit sections 26 and 26A.
(10)In section 49(3), omit paragraph (c).
Public Bodies Act 2011 (c. 24)
(26)
(1)The Public Bodies Act 2011 is amended as follows.
(2)In section 13—
(a)in subsection (1)—
(i)at the end of paragraph (b), insert “ or ”;
(ii)omit paragraph (d) and the “or” before it;
(b)omit subsection (4);
(c)omit subsections (8) and (9).
(3)In section 36(1), in the definition of “cross-border operator”—
(a)at the end of paragraph (za), insert “ or ”;
(b)omit paragraph (b) and the “or” before it.
Water Act 2014 (c. 21)
(27)In Schedule 10 to the Water Act 2014, omit paragraph 18.
Part 5 · Byelaws
National Parks and Access to the Countryside Act 1949 (c. 97)
(28)
(1)The National Parks and Access to the Countryside Act 1949 is amended as follows.
(2)In section 106(5), for “Countryside Council for Wales” substitute “ Natural Resources Body for Wales ”.
(3)In section 106A, in the heading and in subsection (1), for “Countryside Council for Wales” substitute “ Natural Resources Body for Wales ”.
Countryside Act 1968 (c. 41)
(29)In section 41(7A) of the Countryside Act 1968, for “Council” substitute “ NRBW ”.
Local Government Byelaws (Wales) Act 2012 (anaw 2)
(30)
(1)The Local Government Byelaws (Wales) Act 2012 is amended as follows.
(2)In section 3(d), for “Countryside Council for Wales” substitute “ Natural Resources Body for Wales ”.
(3)In section 7(8)(b), for “Countryside Council for Wales” substitute “ Natural Resources Body for Wales ”.
(4)In section 8(8), in the opening words—
(a)for “Countryside Council for Wales” substitute “ Natural Resources Body for Wales ”;
(b)for “the Council” substitute “ the Body ”.
(5)In Schedule 2, omit paragraph 11.
Contains public sector information licensed under the Open Government Licence v3.0.