Article 17European standard nominal track gauge for rail#
1.Member States shall ensure that any new railway line of the core network and the extended core network, including connections referred to in Article 14(1), point (d), provides for the European standard nominal track gauge of 1435 mm. That requirement is considered to be met when 1435 mm track gauge trains can circulate on the infrastructure by 31 December 2030 for the core network and by 31 December 2040 for the extended core network. For the purposes of this Article, new railway line means any line for which construction works have not started by 18 July 2024.
2.By way of derogation from paragraph 1 of this Article, the Member States on the territory of which, on 18 July 2024, no new railway line is planned to be connected to the land border of another Member State according to Annex I, shall draw up a plan identifying the new railway line to be built in accordance with the European standard nominal track gauge of 1435 mm. That plan shall take account of the impact on interoperability with the neighbouring Member State or Member States, by taking account of, notably, the possible migration of existing railway lines to the European standard nominal track gauge of 1435 mm in accordance with paragraph 3 of this Article. The plan shall include a socio-economic cost-benefit analysis justifying the decision of the Member State, where relevant, not to build new railway infrastructure to the European standard nominal track gauge of 1435 mm and an assessment of the impact on interoperability. That plan shall be submitted to the Commission by 19 July 2026.
3.Member States with an existing rail network, or a part thereof, with a track gauge different from that of the European standard nominal track gauge of 1435 mm shall carry out an assessment, by 19 July 2026, identifying the existing railway lines located on the European Transport Corridors in view of their possible migration to the European standard nominal track gauge of 1435 mm. The assessment shall be coordinated with the neighbouring Member State or Member States in the case of cross-border sections. The assessment shall include a socio-economic cost-benefit analysis on the viability of the possible migration to the European standard nominal track gauge of 1435 mm and an assessment of the impact on interoperability.Based on the assessment under the first subparagraph, Member States shall draw up a plan for migration to the European standard nominal track gauge of 1435 mm where relevant, at the latest one year following the completion of the assessment, identifying the existing railway lines located on the European Transport Corridors to be migrated to the European standard nominal track gauge of 1435 mm and provide for an indication of the timeline of that migration.First and second subparagraphs shall apply mutatis mutandis to the railway lines for which construction works have started on 18 July 2024.
4.The priorities for infrastructure and investment planning resulting from the plans referred to in paragraphs 2 and 3 of this Article shall be included in the first work plan of the European Coordinator for a European Transport Corridor of which the freight railway lines with a track gauge different from that of the European standard nominal track gauge is part, in accordance with Article 54.
5.At the request of a Member State, in duly justified cases, the Commission shall adopt implementing acts granting a temporary exemption from the requirements referred to in paragraph 1 for new railway lines of the core network and extended core network, or for part thereof, on the ground of negative results of socio-economic cost-benefit analysis. Any request for exemption shall be based on sufficient justification. The requests for exemption shall be coordinated with the neighbouring Member State or Member States in the case of cross-border sections. The neighbouring Member States may provide an opinion to the Member State requesting the exemption. The Member State shall attach the opinions of the neighbouring Member States to its request. A Member State may request the granting of several exemptions in a single request.The Commission shall assess the request in the light of the justification provided as well as in terms of its significant impact on interoperability and continuity of the railway network, where relevant. The Commission shall take duly into account the opinions of the neighbouring Member States concerned.The Commission may ask for additional information from the Member State no later than 30 calendar days following the receipt of request pursuant to the first subparagraph. If the Commission considers that the information provided is insufficient, it may ask the Member State to supplement that additional information within 30 calendar days from the receipt of that additional information.The Commission shall take a decision on the requested exemption no later than six months following the receipt of the request pursuant to the first subparagraph or, in the event that further information has been provided by the Member States concerned pursuant to the third subparagraph, no later than four months following the latest receipt of such information, whichever is later. The decision shall indicate the period for which the exemption is granted.The Commission shall inform other Member States of the exemptions granted pursuant to this Article.
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.