Article 12Evaluation#
1.Aid schemes referred to in Article 1(7) shall be subject to an ex post evaluation if they have a State aid budget or accounted expenditures over EUR 150 million in any given year or EUR 750 million over their total duration, i.e. the combined duration of the aid scheme and any predecessor aid scheme covering a similar objective and geographical area, starting from 1 January 2023. Ex post evaluations shall only be required for aid schemes the total duration of which exceeds 3 years, starting from 1 January 2023.
2.The ex post evaluation requirement may be waived for aid schemes that are an immediate successor of a scheme covering a similar objective and geographical area that has been subject to an evaluation, delivered a final evaluation report in compliance with the evaluation plan approved by the Commission and has not generated any negative findings. Where the final evaluation report of an aid scheme is not in compliance with the approved evaluation plan, that scheme shall be suspended with immediate effect. Any successor of such suspended aid scheme shall not be block exempted.
3.The aim of the evaluation shall be to verify whether the assumptions and conditions underlying the compatibility of the aid scheme have been achieved, in particular the necessity and the effectiveness of the aid measure in the light of its general and specific objectives. It shall also assess the impact of the scheme on competition and trade.
4.For aid schemes subject to the evaluation requirement pursuant to paragraph 1, Member States shall notify to the Commission a draft evaluation plan as follows:
(a)within 20 working days from the aid scheme's entry into force, if the budget of the aid scheme exceeds EUR 150 million in any given year or EUR 750 million over its total duration;
(b)within 30 working days following a significant change that increases the budget of the aid scheme to over EUR 150 million in any given year or EUR 750 million over the total duration of the aid scheme;
(c)within 30 working days following the recording in official accounts of expenditure under the aid scheme in excess of EUR 150 million in any year.
5.The draft evaluation plan shall be in line with the common methodological principles provided by the Commissionnote. Member States shall publish the evaluation plan approved by the Commission.
6.The ex post evaluation shall be carried out by an expert independent from the aid granting authority on the basis of the evaluation plan. Each evaluation shall include at least one interim and one final evaluation report. Member States shall publish both reports.
7.The final evaluation report shall be submitted to the Commission at the latest 9 months before the expiry of the exempted aid scheme. That period may be reduced for aid schemes triggering the evaluation requirement in the last 2 years of implementation of the aid scheme. The precise scope and arrangements for each evaluation shall be set out in the Commission Decision approving the evaluation plan. The notification of any subsequent aid measure with a similar objective shall describe how the results of the evaluation have been taken into account.