This Regulation establishes detailed arrangements with regard to the selection of engines, test procedures and reporting of results relating to monitoring of gaseous pollutant emissions from in-service internal combustion engines installed in non-road mobile machinery using portable emission measurement systems.
1.This Regulation applies to monitoring of the gaseous pollutant emissions from the following categories of in-service engines of emission Stage V installed in non-road mobile machinery regardless of when the EU type-approval for those engines was granted:
(a)NRE and NRG (all sub-categories);
(b)NRS-vi-1b, NRS-vr-1b, NRS-v-2a, NRS-v-2b and NRS-v-3;
(c)IWP and IWA (all sub-categories);
(d)RLL and RLR (all sub-categories);
(e)ATS;
(f)SMB;
(g)NRSh (all sub-categories);
(h)NRS-vi-1a and NRS-vr-1a.
2.This Regulation applies to engine manufacturer.This Regulation does not apply to original equipment manufacturer.
3.This Regulation does not apply where the manufacturer demonstrates to the approval authority that it is not able to obtain access to any engine installed in a non-road mobile machinery for the purposes of in-service monitoring.
Article 3Procedures and requirements for monitoring of emissions of in-service engines#
(ii)the aging procedure used to establish the deterioration factor (DF) for the engine type, or, where applicable the engine family, as required by section 4.3 of Annex III to Commission Delegated Regulation (EU) 2017/654note, including any automated element, shall be designed to allow the manufacturer to appropriately predict the in-use emission deterioration expected over the emission durability period (EDP) of those engines under typical use.
(iii)the Commission shall, every 5 years, in cooperation with manufacturers, conduct a pilot programme involving the most recent engine types in order to ensure that the procedure to determine DFs set out in section 4 of Annex III to
1.Notwithstanding the application of the provisions of this Regulation, as amended by Commission Delegated Regulation (EU) 2018/987note, approval authorities shall, until 31 December 2018, also continue to grant EU type-approvals to engine types or engine families in accordance with this Regulation, in its version applicable on 6 August 2018.
2.Notwithstanding the application of the provisions of this Regulation, as amended by Delegated Regulation (EU) 2018/987, the Member States shall, until 30 June 2019, also permit the placing on the market of engines based on an engine type approved in accordance with this Regulation, in its version applicable on 6 August 2018.
3.EU type-approvals of an engine type or engine family approved in accordance with this Regulation before 28 December 2022 shall not be required to be revised or extended as a result of the testing carried out in accordance with the requirements of the Annex.
For the purposes of this Annex ‘category of non-road mobile machinery’ means a grouping of non-road mobile machinery that fulfil the same generic function(s),
1.2.
The manufacturer shall obtain access to engines installed in non-road mobile machinery in order to conduct in-service monitoring tests.
When conducting the in-service monitoring test the manufacturer shall perform the emissions data sampling, measurement of exhaust parameters and data logging of an in-service engine installed in a non-road mobile machinery operated over its normal operating duty cycles until reaching the minimum test duration as set out in point 2 of Appendix 2.
For the carrying out of in-service testing, all engine types and engine families produced by the manufacturer shall be grouped in accordance with its sub-category as set out in Table 1 and illustrated in Figure 1. One manufacturer may have one ISM Group for each possible type of ISM Group.
1.2.b.The approval authority ensuring the compliance with this Regulation shall be either:
(a)the approval authority that granted the type-approval of the engine type or engine family, in case that the ISM Group contains a single type-approval;
(b)the approval authority that granted the type-approval of several engine types and/or engine families within the same ISM Group;
(c)in the case that the ISM Group contains engine types, and/or engine families, approved by different approval authorities, the approval authority designated by all approval authorities involved.
(a)be installed in one of the most representative categories of non-road mobile machinery for the selected engine type or, where applicable, engine family;
(b)be placed on the Union market;
(c)have a maintenance record to show that the engine has been properly maintained and serviced in accordance with the manufacturer's recommendations;
(d)exhibit no indications of misuse (e.g. overloading or misfuelling), or other factors (such as tampering) that could affect the gaseous pollutant emissions performance;
(e)be in conformity with the EU type-approval documents with regard to the components of the emission control system(s) installed in the engine and in the non-road mobile machinery.
1.3.
Engines subject to in-service monitoring test shall:
1.4.
Engines with an Electronic Control Unit (ECU) and a communication interface intended to provide the necessary data as specified in Appendix 7, but with a missing interface or missing data, or where it is not possible to achieve clear identification and validation of the necessary signals, shall not be eligible for in-service monitoring test, and an alternative engine shall be selected.
The approval authority shall not accept the absence of an ECU or interface, or absent or invalid signals, or lack of conformity of the ECU torque signal, as a reason to reduce the number of engines to be tested under this Regulation.
1.5.
Engines where the collection of ECU data influences the non-road mobile machinery gaseous pollutant emissions or performance shall be considered as non-eligible for in-service monitoring test. Notwithstanding the requirements of article 39 of Regulation (EU) 2016/1628, an alternative engine shall only be selected if the manufacturer can substantially prove to the approval authority the absence of any defeat strategy.
(a)for ISM Group A, one month of the start of production of any engine type or engine family within the ISM Group;
(b)for any other ISM Group, the later date of the following:
(i)26 June 2023;
(ii)1 month after the start of production of any engine type or engine family within the ISM Group.
2.1.
The manufacturer shall submit the initial plan for monitoring each ISM Group to the approval authority within:
(a)the engine families or engine types and category(ies) of non-road mobile machinery included in the plan;
(b)the list of particular engine(s) and non-road mobile machinery selected for in-service monitoring test, if already identified;
(c)the chosen testing scheme.
2.2.
The initial plan shall include the list of engine types and engine families in the ISM Group, together with the criteria used for and the justification of the selection of:
2.3.
Manufacturers shall submit to the approval authority an updated plan for monitoring in-service engines whenever the list of engine families in the ISM Group changes or the list of particular engine(s) and non-road mobile machinery selected is completed or revised. The updated plan shall include a justification of the criteria used for the selection and the reasons for revising the previous list, if applicable. Where the number of engine families in the ISM Group or the annual production volume for the Union market changes, the plan with the number of tests to be executed in accordance with point 2.6, shall also be adjusted accordingly.
2.4.
The approval authority shall approve the initial and subsequently updated plan(s) or request the appropriate amendments within 2 months of their submission, and shall ensure that the final plan includes the widest variety of engine types and categories of non-road mobile machinery.
2.5.
Each initial or subsequently updated monitoring plan shall be approved by the approval authority before the testing of engines and non-road mobile machinery identified therein is started.
The number of engines to be tested refers to the ISM group, and not to the engine sub-categories, engine families or engine types belonging to ISM group.
The manufacturer shall select engines that represent, in a balanced manner, the sub-categories, engine families and engine types belonging to the ISM group. This should not necessarily imply testing engines belonging to each engine sub-category, engine family or engine type.
For ISM groups containing both category IWP and IWA the engine selection shall include, to the extent possible, engines of both categories.
2.6.1.1.1.Testing 9 engines from the ISM group with an accumulated service of less than a % of the EDP, in accordance with Table 2. Test results shall be submitted to the approval authority by 28 December 2024.
2.6.1.1.2.Testing 9 engines from the ISM group with an accumulated service higher than b % of the EDP, in accordance with Table 2. Test reports shall be submitted to the approval authority by 28 December 2026.
The in-service monitoring test shall reflect the engine's performance when installed in a non-road mobile machinery, in actual operation and operated by its usual professional operator.
The non-road mobile machinery's operator performing the in-service monitoring test may be other than the usual professional one if the manufacturer demonstrates to the approval authority that the designated operator has attained enough skills and training to operate the non-road mobile machine.
3.1.2.
The manufacturer shall provide detailed explanations to the approval authority on the usual operator's skills and training, and demonstrate that the selected operator is adequate for the in-service monitoring test.
The test shall be performed during the complete (or partial) non-road mobile machinery's actual operation.
3.2.2.
When the manufacturer demonstrates to the approval authority that it is not possible to comply with point 3.2.1, the test duty cycle shall represent, as far as possible, the non-road mobile machinery's actual operation.
3.2.2.1.
The representative test duty cycle shall be determined by the manufacturer in agreement with the approval authority.
(a)assess the actual operation of the majority of in-service population of the selected category(ies) of non-road mobile machinery;
(b)not include a disproportionate amount of activity at idle speed;
(c)comprise of sufficient load activity to achieve the minimum test duration set out in point 2 of Appendix 2.
3.2.3.
Regardless of whether the test is conducted during the actual operation of the non-road mobile machinery or under a representative test duty cycle, it shall:
3.3.1.Atmospheric pressure shall be equal or greater than 82,5 kPa;
3.3.2.Temperature shall be equal or greater than 266 K (– 7 °C), except for ISM group O which shall be equal or greater than 253K (– 20 °C), and equal or less than the temperature determined by the following equation at the specified atmospheric pressure:T = – 0,4514 * (101,3 – pb) + 311where:
—T is the ambient air temperature, K;
—pb is the atmospheric pressure, kPa.
The test shall be conducted under ambient conditions meeting the following requirements:
The lubricating oil, fuel and reagent (for exhaust after-treatment systems that use a reagent to reduce gaseous pollutant emissions) shall comply with the specifications issued by the manufacturer.
(a)12 months following the completion of the test; or
(b)1 month after the manufacturer submits the respective test report to the approval authority.
3.4.2.
To demonstrate compliance with point 3.4, samples shall be taken and retained until at least, whichever is the shortest period of time form the following:
Operating sequence is the elapsed time of uninterrupted non-road mobile machinery operation and continuous data sampling during an in-service monitoring test.
The in-service monitoring test shall be conducted in one single operating sequence, except under the combined data sampling method set out in point 4.2, where several operating sequences are combined in a single in-service monitoring test.
Continuous data sampling shall be used when one single operating sequence is equal or more than the minimum test duration set out in point 2 of Appendix 2.
4.1.1.
A maximum of 3 minutes of data may be excluded due to one or several episodes of temporary signal loss.
As alternative to point 4.1, the data sampling may be obtained from combining the results of several operating sequences.
4.2.1.
Combined data sampling shall be used only when the test conditions do not enable reaching the minimum test duration set out in point 2 of Appendix 2 with one single operating sequence despite attempting to achieve this, or when the category(ies) of non-road mobile machinery selected for testing is employed in multiple working activities with different relevant duty cycle(s).
(a)the different operating sequences shall be obtained using the same non-road mobile machinery and engine;
(b)the combined data sampling of tests performed at ambient temperature above 273,15 K shall contain a maximum of three operating sequences;
(c)the combined data sampling of tests performed at ambient temperature equal or below 273,15 K shall contain a maximum of six operating sequences;
(d)the maximum period elapsed between the first and last operating sequence shall be 72 hours;
(e)combined data sampling shall not be used if an engine malfunction occurs, as set out in point 8 of Appendix 2;
(f)to be eligible for combined data sampling each operating sequence of an in-service monitoring test shall contain the following minimum amount of work (kWh) or CO2 mass (g/cycle):
(i)for engines in ISM Groups A and C, a minimum of one hot-start NRTC reference work or CO2 reference mass;
(ii)for engines in ISM Group H, a minimum of one LSI-NRTC reference work or CO2 reference mass;
(iii)for engines in all other ISM Groups, a minimum of one steady-state cycle reference work or CO2 reference mass determined using the method set out in Appendix 9;
(iv)For engines where in-service monitoring testing is performed at 0 °C degrees or below, a minimum of three quarters reference work or CO2 reference mass during the first operating sequence and a minimum of half a steady-state cycle reference work or CO2 reference mass for the following operating sequences, determined using the method set out in Appendix 9;
In case of an in-service test of an engine type within an engine family, the reference value shall be that for the parent engine type;
(g)prior to joining the operating sequences, all necessary pre-processing shall be completed individually for each sequence in accordance with the requirements set out in point 6.3;
(h)the operating sequences in the combined data sampling shall be joined in a chronological order including all data not excluded by sub-point (f);
(i)the combined data sampling shall be considered one ISM test;
(j)the determination of working events set out in point 6.4 and calculations set out in point 8 shall be applied to the complete combined data sampling.
4.2.2.
The following additional requirements shall be fulfilled when applying combined data sampling:
Parameter recording shall reach a data completeness of not less than 98 %, meaning that a maximum of 2 % of data with no consecutive period of more than 30 seconds duration may be excluded from each operating sequence due to one or several episodes of unintended temporary signal loss in the original data recording. No signal loss shall be created during pre-processing, combination or post-processing of any operating sequence.
5.1.Engines fitted with an ECU and a communication interface shall provide data stream information to the measurement instruments or data logger of the PEMS in accordance with the requirements set out in Appendix 7.
5.2.Prior to the in-service test, the availability of the measurement data requested by Appendix 7 shall be validated.
5.3.The conformity of the ECU torque signal shall be validated during the in-service monitoring in accordance with the method set out in Appendix 6.
5.4.Where an engine fitted with an ECU and a communication interface does not permit fulfilling the requirements set out in points 5.1., 5.2 and 5.3., point 1.4. shall apply.
In-service monitoring tests shall be conducted using PEMS in accordance with Appendix 1.
6.2.
Manufacturers shall comply with the test procedure set out in Appendix 2 with regard to the in-service monitoring of engines installed on non-road mobile machinery using a PEMS.
6.3.
Manufacturers shall follow the procedures set out in Appendix 3 for the pre-processing of the data resulting of the in-service monitoring of engines installed on non-road mobile machinery using a PEMS.
6.4.
Manufacturers shall follow the procedures set out in Appendix 4 for the determination of working and non-working events for gaseous pollutant emissions calculation following an in-service monitoring test of engines installed on non-road mobile machinery using a PEMS.
6.5.In accordance with point 4.2.2, where combined data sampling is used, the requirements of points 6.1 to 6.3 shall apply individually to each operating sequence prior to combining operating sequences. The determination of working and non-working events set out in point 6.4 and calculations set out in point 8. shall be applied to the complete combined data sampling.
6.6.Figure 3 outlines the complete sequence for conducting in-service monitoring including planning, PEMS preparation and installation, test procedures, data pre-processing, data calculations and validation.
No data shall be modified or removed from the raw test data file(s) used for the completion of point 6. Those raw test data file(s) shall be retained at least for 10 years by the manufacturer and made available upon request to the approval authority and the Commission.
8.1.In the case of engines with an ECU that were produced with a communication interface intended to permit the collection of the engine torque and speed data as specified in Table 1 of Appendix 7, the calculations shall be conducted and results reported for both the work-based method and the CO2 mass-based method. In all other cases, the calculations shall be conducted and results reported for the CO2 mass based method only.
8.2.In all cases, the calculations shall be conducted twice following the pre-processing of data in accordance with point 6.3 of this Annex:
(a)firstly, using only working events determined in accordance with point 6.4 of this Annex and valid windows; and
(b)secondly, using all data not excluded by point 6.3 of this Annex, without applying point 6.4 of this Annex, and without exclusion of invalid windows as set out in points 2.2.2 and 2.3.1 of Appendix 5.
Manufacturers shall follow the procedures set out in Appendix 5 for the gaseous pollutant emissions calculations for the in-service monitoring of engines installed on non-road mobile machinery using a PEMS.
Approval authorities may conduct a confirmatory in-service monitoring test in order to have an independent in-service monitoring measurement.
9.2.
The confirmatory test shall be performed on the engine family/type and category(ies) of non-road mobile machinery specified in point 2; a particular engine fitted in a relevant non-road mobile machinery shall be tested according to the requirements set out in this Regulation.
Manufacturers shall draft a test report of the in-service monitoring of engines installed on non-road mobile machinery using a PEMS for each engine tested. The test report shall show the activities and results of the in-service monitoring and include at least the information required by data entries 1 to 11 of Appendix 8.
Instantaneous measured data and instantaneous calculated data shall not be included in the test report but shall be kept by the manufacturer and made available upon request to the European Commission and the approval authority for the period set out in point 7.
10.2.2.
Instantaneous measured data and instantaneous calculated data shall include at least the information required by data entries I-1 to I-2.20 of Appendix 8.
For the purposes of Article 44(3)(b) of Regulation (EU) 2016/1628, the manufacturer shall provide a separate report containing the information required by the following data entries of Appendix 8: 1.1, 2.2, 2.4, 3.2, 6.3, 6.4.1, 6.10 Section 9 and Section 10.
Information for data entry 6.3 shall be provided at regional level, providing approximate geographic location only.
2.6.1.1.3.When the manufacturer cannot fulfil the requirement under point 2.6.1.1 due to unavailability of engines with the required service accumulation of point 2.6.1.1.2, the approval authority may permit testing of engines under this point with an accumulated service between 2 times a % and b % of the EDP, subject to the manufacturer providing robust evidence that they have selected engines with the highest available service accumulation. As an alternative, the approval authority shall accept a change to the testing scheme based on a 4-year period set out in point 2.6.1.2. In that case, the total number of engines to be tested under point 2.6.1.2 shall be reduced by the number of engines already tested and reported in accordance with point 2.6.1.1.Table 2% of EDP values for ISM group defined in 2.6.1Reference power of selected engine (kW) | a | b56 ≤ P < 130 | 20 | 55130 ≤ P ≤ 560 | 30 | 70
2.6.1.2.1.The test results of the first nine engines shall be submitted not later than 24 months after the first engine was installed in non-road mobile machinery and not later than 30 months after starting the production of an approved engine type or engine family within the ISM group.
2.6.1.2.2.Where the manufacturer demonstrates to the approval authority that no engine has been installed in non-road mobile machinery 30 months after starting the production, the test results shall be submitted after the installation of the first engine, on a date agreed with the approval authority.
2.6.1.2.3.Small-volume manufacturersThe number of engines tested shall be adapted in case of small-volume manufacturers as follows:
(a)manufacturers producing only two engine families within an ISM group shall submit an average of six engine test results per year;
(b)manufacturers producing for the Union market more than 250 engines per year of an ISM group containing only one single engine family shall submit an average of three engine test results per year;
(c)manufacturers producing for the Union market between 125 and 250 engines per year of an ISM group containing only one single engine family shall submit an average of two engine’s test results per year;
(d)manufacturers producing for the Union market fewer than 125 engines per year of an ISM group containing only one single engine family shall submit an average of one engine’s test results per year.
The approval authority shall verify the declared production quantities are not exceeded during the 4-year period that the manufacturer conducts testing. If these quantities are exceeded at any point, the manufacturer shall test an average of nine engines per year for the remaining years of the 4-year period for which results have not been reported.
Every manufacturer shall test an average of nine engines per year from the ISM group during 4 consecutive years.The test reports shall be submitted to the approval authority every year for the tests that have been performed. The schedule for testing and submitting results shall be included in the initial plan, and in any subsequently updated plan, for monitoring in-service engines submitted by the manufacturer and approved by the approval authority.
The manufacturer shall choose, for each group, one of the following testing schemes described in points 2.6.2.1 and in 2.6.2.2 for in-service monitoring.
2.6.2.1.1.Testing x engines from the ISM group with an accumulated service of less than c % of the EDP, in accordance with Table 3. Test results shall be submitted to the approval authority by 28 December 2024.
2.6.2.1.2.Testing x engines from the ISM group with an accumulated service higher than d % of the EDP, in accordance with Table 3. Test results shall be submitted to the approval authority by 28 December 2026.
2.6.2.1.3.When the manufacturer cannot fulfil the requirements set out in points 2.6.2.1.1 and 2.6.2.1.2 due to unavailability of engines with the required service accumulation, the approval authority may permit testing of engines under this point with an accumulated service between 2 times c % and d % of the EDP, subject to the manufacturer providing robust evidence that they have selected engines with the highest available service accumulation. As an alternative, the approval authority shall accept a change to the testing scheme based on a 4-year period set out in point 2.6.2.2. In that case, the total number of engines to be tested under point 2.6.2.2 shall be reduced by the number of engines already tested and reported in accordance with points 2.6.2.1.1 and 2.6.2.1.2.
2.6.2.1.4.When the test report of a Stage IIIB engine family equivalent to category RLL is used to obtain a corresponding Stage V type-approval for that engine family in accordance with Article 7(2) of Implementing Regulation (EU) 2017/656 and the engine manufacturer cannot fulfil the requirements under points 2.6.2.1.1 and 2.6.2.1.2 due to unavailability of Stage V engines with the required service accumulation, the approval authority shall accept the selection of a Stage IIIB engine to comply with the requirements of points 2.6.2.1.1 and 2.6.2.1.2.Table 3% of EDP values for ISM groups defined in 2.6.2.1Reference power of selected engine (kW) | c | dP < 56 | 10 | 4056 ≤ P < 130 | 20 | 55P ≥ 130 | 30 | 70Table 4Number of engines to be tested for ISM groups defined in 2.6.2, 2.6.3.1 and 2.6.4.1N | CA | x1 | - | 12 ≤ N ≤ 4 | - | 2> 4 | ≤ 50 | 25 ≤ N ≤ 6 | > 50 | 3≥ 7 | > 50 | 4Where:NTotal number of EU engine families produced by the manufacturer within the ISM groupCACombined annual production for EU market for the remaining engine families produced by the manufacturer within an ISM group after discarding the four families with the highest annual production for EU market.xNumber of engines to be tested
2.6.2.2.1.The test results of the first x engines shall be submitted before the later date of the following:
(a)28 December 2024;
(b)12 months after the first engine was installed in non-road mobile machinery;
(c)18 months after starting the production of an approved engine type or engine family within the ISM group.
2.6.2.2.2.When the manufacturer demonstrates to the approval authority that no engine has been installed in non-road mobile machinery 18 months after starting the production, the test results shall be submitted after the installation of the first engine, on a date agreed with the approval authority.
2.6.2.2.3.Small-volume manufacturersThe number of engines tested shall be adapted in case that the combined annual production across all engine families in an ISM group does not exceed 50 engines (small volume manufacturers), as follows:
(a)manufacturers producing a total between 25 and 50 engines per year for the Union market across all families in a given ISM group shall submit either:
The manufacturer shall choose, for each group, one of the testing schemes described in point 2.6.2 or the testing scheme based on age of equipment described in section 2.6.3.1 for in-service monitoring.
2.6.3.1.1.Testing x engines from the ISM group with non-road mobile machinery production year not more than 2 years prior to the date of that test, (see Figure 2), in accordance with Table 4. Test results shall be submitted to the approval authority by 28 December 2024.
2.6.3.1.2.Testing x engines from the ISM group with non-road mobile machinery production year not less than 4 years prior to the date of that test, (see Figure 2), in accordance with Table 4. Test results shall be submitted to the approval authority by 28 December 2026.
2.6.3.1.2.1.Robust evidence shall be provided to the approval authority that each engine selected for testing under point 2.6.3.1.2 has been used each year in a manner and to an extent similar to that of the population of corresponding engines placed on the Union market. Suitable evidence may include characteristics demonstrating normal wear, records of use, records of maintenance and records of fuel consumed.
2.6.3.1.3.When the manufacturer cannot fulfil the requirements set out in points 2.6.3.1.1 and 2.6.3.1.2 due to unavailability of engines with the required non-road mobile machinery production year or insufficient evidence of use, the approval authority shall accept a change to the testing scheme based on a 4-year period set out in point 2.6.2.2. In that case, the total number of engines to be tested under point 2.6.2.2 shall be reduced by the number of engines already tested and reported in accordance with points 2.6.3.1.1 and 2.6.3.1.2.
The manufacturer shall choose, for each ISM group, one of the testing schemes described in point 2.6.2. In the case the testing scheme set out in point 2.6.2.1 is chosen, manufacturers shall have the possibility to apply, within the same ISM group, the testing scheme based on the odometer reading described in point 2.6.4.1.
In the case the manufacturer choses the procedure set out in point 2.6.2.1, the required accumulated service shall be the one stated in Table 5 instead of the one stated in Table 3.
2.6.4.1.1.Testing x engines from the ISM group with non-road mobile machinery odometer reading an accumulated service of less than c (km) in accordance with Table 4 and Table 6. Test results shall be submitted to the approval authority by 28 December 2024.
2.6.4.1.2.Testing x engines from the ISM group with non-road mobile machinery odometer reading an accumulated service of more than d (km) in accordance with Table 4 and Table 6. Test results shall be submitted to the approval authority by 28 December 2026.Table 6Accumulated service for ISM groups O and PGroup | Engine swept volume (cm3) | c (km) | d (km)O | Any | 1600 | 4400P | < 100 | 1350 | 5400≥ 100 | 2700 | 10800
(i)one engine test results with an accumulated service between c % and d % of EDP as defined in Table 3 by 28 December 2025, or;
(ii)an average of one engine test results per year over 2 years, starting 12 months after the first engine was installed in non-road mobile machinery,
(b)manufacturers producing a total of fewer than 25 engines per year for the EU market across all families in a given ISM group need not submit any engine test unless the production exceeds 35 engines in a two-year rolling period, in which case the manufacturer shall follow the same scheme as set out in sub-point (a).
The approval authority shall verify that the declared production quantities are not exceeded during the periods set out in the first paragraph, sub-point (a). If those quantities are exceeded at any point, the manufacturer shall change to one of the testing schemes set out in points 2.6.2.1. and 2.6.2.2. In that case, the total number of engines to be tested under those points shall be reduced by the number of engines already tested and reported in accordance with this point.
Testing an average of x engines from the ISM group per year during 4 consecutive years, in accordance with Table 4. Test reports shall be submitted to the approval authority every year for the tests that have been performed. The schedule for testing and submitting results shall be included in the initial plan, and in any subsequently updated plan, for monitoring in-service engines submitted by the manufacturer and approved by the approval authority.