2.The timetable for the actions referred to in Article 2, point (b), shall be the following:
(a)upgrading the existing conventional line Bussoleno-Avigliana section: end of works between 2026-2032.
(b)construction of the new line Avigliana-Orbassano:
(i)environmental assessment and permits obtained between 2024-2025;
(ii)start of works by 2026;
(iii)end of works by 2033.
(c)rearrangement of the Orbassano marshalling yard including South Junction, first phase, Turin side, by 2026.
(d)connectivity within the Turin railway urban node:
i)Porta Susa - Stura section: concluded at 98 % (completion expected by 2025)
(ii)Porta Susa- Porta Nuova section: completion by 2028;
(iii)Turin-Genoa line: by 2027 (first phase):
—completion of the technological adaptation of the systems of the CCS Subsystem of the Trofarello-Alessandria section with the construction of the ACCM-SCCM in sub-phases;
—completion of the ACC of the Villafranca station;
—completion of the new ACC of Asti.