1.The timetable for the actions referred to in Article 2 point (a), shall be the following:
(a)In 2025: start of mechanized excavation of the first French lot of the base tunnel (operational construction site 7) – France.
(b)by the end of 2026/early 2027: start of mechanized excavation of the other lots of the base tunnel (operational construction sites 3-4-5-6) – France and Italy.
(c)by 2028: end of civil works at the entrance section - Saint Martin La Porte (operational construction site 8) – France.
(d)by 2027: contract award proposal of railway and non-railway installations (operational construction site 12) – France and Italy.
(e)by 2028: start of the interconnection tunnel excavation with traditional method in Bussoleno (operational construction site 1) – Italy.
(f)by 2029: start of civil works at Susa international station (operational construction site 2) –Italy.
(g)by 2030: end of civil works of the multimodal exchange hub at Saint-Jean-de-Maurienne international station (operational construction site 9) – France.
(h)by 2031: completion of the base tunnel excavation on the French and Italian sides (operational construction sites 3-4-5-6-7-8) – France and Italy.
(i)by 2031: completion of the Saint-Jean-de Maurienne international station with related ancillary infrastructure; starting of the construction of the Susa international station equipment (operational construction sites 9 and 2) – France and Italy.
(j)By 31 December 2032: completion of the railway infrastructure for mixed traffic, in compliance with the TEN-T parameters set out in Regulation (EU) 2024/1679 – France and Italy.
(k)By 2033: operational installation ERTMS Level 2 – France and Italy.