THE EUROPEAN COMMISSION,Having regard to the Treaty on the Functioning of the European Union,Having regard to Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricitynote, and in particular Article 64 thereof,Having regard to Directive (EU) 2019/944 of the European Parliament and of the Council of 5 June 2019 on common rules for the internal market for electricity and amending Directive 2012/27/EUnote, and in particular Article 66 thereof,Whereas:
HAS ADOPTED THIS DECISION:
Article 1#
A derogation is granted to the Hellenic Republic from the provisions of Articles 6, 7(1), 8(1) and (4), 9, 10 and 11 of Regulation (EU) 2019/943 and from the provisions of Article 40(4) to (7) of Directive (EU) 2019/944, as regards Crete.
Article 2#
The derogation granted under Article 1 shall apply until 31 December 2023 or until the completion of Phase II of the interconnection between Crete and mainland Greece, whichever comes first.
Article 3#
The Hellenic Republic shall inform the European Commission by the end of 2022 of the progress and remaining planning towards the completion and commercial operation of Phase II of the interconnection between Crete and mainland Greece, including regarding the deployment and operation of the adequate metering infrastructure allowing the participation of Crete in the Greek wholesale and balancing market.
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.