(3)As an alternative measure, the project foresees to create an access to a safe area through a vertical emergency exit to the surface after 3,895 km of the entrance of the Miglionico tunnel, with the purpose of evacuating passengers and allowing access for rescue vehicles. The proposed measure corresponds to the requirement set under the Italian Ministerial Decree of 28 October 2005 ‘safety in railway tunnel’note, which provides for the construction of an emergency exit approximately every 4 km for tunnels above 5 km. A specific and detailed risk analysis was carried out by the Italian infrastructure manager in accordance with Commission Implementing Regulation (EU) No 402/2013note, demonstrating that in this case all identified risks are below the level of unacceptability, and therefore concluding that the safety of the tunnel is considered acceptable and that with the mitigating measure in place, the non-application of point 4.2.1.5.2, (b)(1) of the Annex to Regulation (EU) No 1303/2014 would not compromise the safety of the tunnel.