Contents
Article 1#
This Decision establishes the harmonised conditions for the availability and efficient use of radio spectrum for the Railway Mobile Radio (RMR) in the bands 874,4-880,0 MHz, 919,4-925,0 MHz and 1900-1910 MHz.
Article 2#
For the purposes of this Decision, the following definitions shall apply:
(a)‘RMR terminal’ is an item of mobile radio equipment under the control of the RMR network;
(b)‘cab-radio’ means a RMR terminal installed on board the train capable of supporting voice and data applications;
(c)‘equivalent isotropically radiated power (‘e.i.r.p.’)’ means the product of the power supplied to the antenna and the absolute or isotropic gain in a given direction relative to an isotropic antenna.
Article 3#
1.By 1 January 2022, Member States shall designate and make available on a non-exclusive basis the paired frequency bands 874,4-880,0 MHz and 919,4-925,0 MHz for Railway Mobile Radio, in accordance with the technical conditions set out in the Annex.
2.At the latest by 1 January 2025, based on national demand, Member States shall designate and make available on a non-exclusive basis the unpaired frequency band 1900-1910 MHz for Railway Mobile Radio, in accordance with the technical conditions set out in the Annex.
3.Member States shall ensure that networks using the frequency bands referred to in paragraph 1 give appropriate protection to systems in adjacent bands.
4.Member States where no rail services are provided at the date of 1 January 2022 shall only apply paragraph 1 as soon as a rail line is planned to be activated.
Article 4#
Member States shall report to the Commission on the implementation of this Decision by 1 January 2025.Member States shall monitor the use by RMR of the frequency bands subject to this Decision and report their findings, including any impacts on interoperability related to spectrum issues, to the Commission upon request or at their own initiative to allow a timely review of this Decision, where needed.
PART A — TECHNICAL CONDITIONS FOR GSM-R IN 874,4-880,0 MHZ and 919,4-925,0 MHZ BANDS
For GSM-R, the following parameters apply:
GSM-R Downlink centre frequency fDL = 921 MHz + n × 0,2 MHz (1) where
GSM-R Uplink centre frequency fUL = fDL – 45 MHz
GSM-R channel bandwidth is 200 kHz
| GSM-R channel bandwidth | Maximum EIRP |
|---|---|
| 200 kHz | = 70,5 dBm + (fDL – 921) × 40/3 dB |
| fDL is the centre frequency in MHzThere is no EIRP restriction on GSM-R Base Stations transmitting in the 921-925 MHz frequency band. Formula applicable to fDL ≤ 921 MHz. To allow higher EIRP the implementation of a coordination procedure or other mitigation measures must be applied. |
PART B — TECHNICAL CONDITIONS FOR A SINGLE WIDEBAND RAILWAY MOBILE RADIO (RMR) CARRIER IN 874,4-880,0 MHZ and 919,4-925,0 MHZ BANDS
Technical conditions for RMR Base Stations using wideband technologies
—The lower edge of the lowest Resource Block shall be ≥ 919,6 MHzTable 2General in-block requirement – not mandatoryRMR channel bandwidth | Maximum EIRPFor any channel bandwidth | The following value may be used in case an upper bound is desired: = Min {65 dBm/channel, Maximum EIRP specific to the channel bandwidth}Table 3Specific in-block requirements for 5,6 MHz and 5 MHz channels mandatory for uncoordinated deploymentRMR channel bandwidth | Maximum EIRP5,6 MHz | = 62 dBm/5,6 MHz5 MHz | = 64,5 dBm/5 MHz + (fDL – 922,1) × 40/3 dB (Note 1)fDL is the centre frequency in MHz.Table 4Specific in-block requirements for frequency channels of 3 MHz, and smaller than or equal to 200 kHz, which are mandatory for uncoordinated deploymentRMR channel bandwidth | Maximum EIRP3 MHz | = 61 dBm/3 MHz + (fDL – 921,4) × 40/3 dB (Note 1)200 kHz (Note 2) | = 70,5 dBm/200 kHz + (fDL – 921) × 40/3 dB (Note 3)fDL is the centre frequency in MHz.Table 5Out-of-band requirementsMHz from block edge (919.4-925 MHz) | EIRP limit0 ≤ Δf < 0.2 | 32,5 dBm/200 kHz0,2 ≤ Δf < 1 | 14 dBm/800 kHz1 ≤ Δf < 10 | 5 dBm/MHzOn a case-by-case basis, at a national level, higher out-of-band limits may be applied.Table 6Baseline requirementFrequency range | EIRP limit880-915 MHz | -49 dBm/5 MHzThis requirement prevails over out-of-band requirements.
The technical conditions defined in this section are in the form of a block-edge mask (BEM) applicable to wideband RMR Base Stations. The technical conditions defined in this section are valid for a single RMR carrier using wideband technologies. The BEM is developed on the basis that detailed coordination and cooperation agreements would not be required to be in place prior to network deployment. To allow multiple carriers or higher EIRP for RMR Base Stations than stated in the harmonised technical conditions, the implementation of a coordination procedure or other mitigation measures must be applied. Base Stations using active antenna systems are prohibited.
For radio access technologies other than GSM-R, the following parameters apply:
Technical conditions for RMR cab-radio using wideband technologies
For radio access technologies other than GSM-R, the following parameters apply:
Maximum output power: higher than 23 dBm and up to 31 dBm;
ACLR (1): 37 dB minimum;
Uplink power control is mandatory and shall be activated.
Technical conditions for RMR terminals, other than cab-radios, using wideband technologies
For radio access technologies other than GSM-R, the following parameters apply:
Maximum output power: 23 dBm;
ACLR: 30 dB minimum;
Uplink power control is mandatory and shall be activated.
Technical conditions for RMR receivers using wideband technologies
The band can be accessed if techniques to access spectrum and mitigate interference that provide an appropriate level of receiver performance to comply with the essential requirements of Directive 2014/53/EU of the European Parliament and of the Council (3) are used. Where relevant techniques are described in harmonised standards or parts thereof the references of which have been published in the Official Journal of the European Union in accordance with Directive 2014/53/EU, performance at least equivalent to the performance level associated with those techniques shall be ensured.
| Parameter | Value |
|---|---|
| Level of the wanted signal | RefSens + 3 dB |
| Maximum interfering signal in 870-874,4 MHz (Note 1) | -34 dBm |
| The antenna connector of the radio module is the reference point. The reference sensitivity (RefSens) is the minimum mean power received at the antenna connector at which a specified minimum performance shall be met.These requirements cover both blocking and third-order intermodulation. |
| Parameter | Value |
|---|---|
| Level of the wanted signal | RefSens + 3 dB |
| Maximum interfering signal in 880-918,9 MHz (Note 1) | -26 dBm |
| Maximum continuous wave interfering signal in 925,6-927 MHz | -13 dBm |
| Maximum continuous wave interfering signal in 927-960 MHz | -10 dBm |
| Maximum 5 MHz LTE interfering signal (lowest carrier at 927,6 MHz) | -13 dBm |
| The antenna connector of the radio module is the reference point. The reference sensitivity (RefSens) is the minimum mean power received at the antenna connector at which a specified minimum performance shall be met.These requirements cover both blocking and third-order intermodulation. |
Part C — technical conditions for wideband rmr in 1900-1910 mhz (tdd) band
Technical conditions for RMR Base Stations using wideband technologies
The technical conditions defined in this section are in the form of a block-edge mask (BEM) applicable to wideband RMR BS. The BEM is developed on the basis that detailed coordination and cooperation agreements would not be required to be in place prior to network deployment. Base Stations with active antenna systems are prohibited.
The following parameters apply:
| RMR channel bandwidth | Maximum EIRP |
|---|---|
| 10 MHz | = 65 dBm/10 MHz (Note 1) |
| Frequency range | EIRP limit |
|---|---|
| 1920 -1980 MHz | -43 dBm/5 MHz |
Technical conditions for RMR cab-radio using wideband technologies
—25 dBm/MHz maximum in 1920-1925 MHz,
—30 dBm/MHz maximum in 1925-1980 MHz;
The following parameters apply:
Maximum output power: 31 dBm;
ACLR: 37 dB minimum;
Unwanted output power in 1920-1980 MHz:
Uplink power control is mandatory and shall be activated.
Technical conditions for RMR terminals, other than cab-radios, using wideband technologies
The following parameters apply:
Maximum output power: 23 dBm;
ACLR: 30 dB minimum;
Uplink power control is mandatory and shall be activated.
Technical conditions for RMR receivers using wideband technologies
The band can be accessed if techniques to access spectrum and mitigate interference that provide an appropriate level of receiver performance to comply with the essential requirements of Directive 2014/53/EU are used. Where relevant techniques are described in harmonised standards or parts thereof the references of which have been published in the Official Journal of the European Union in accordance with Directive 2014/53/EU, performance at least equivalent to the performance level associated with those techniques shall be ensured.
| Parameter | Value |
|---|---|
| Level of the wanted signal | RefSens + 3 dB |
| Maximum 5 MHz LTE interfering signal in 1805 -1880 MHz | -20 dBm |
| The antenna connector of the Base Station receiver is the reference point. The reference sensitivity (RefSens) is the minimum mean power received at the antenna connector at which a specified minimum performance shall be met.These requirements cover both blocking and third-order intermodulation. |
| Parameter | Value |
|---|---|
| Level of the wanted signal | RefSens + 3 dB |
| Maximum 5 MHz LTE interfering signal in 1805 -1880 MHz | -13 dBm |
| Maximum 5 MHz LTE interfering signal in 1920 -1980 MHz | -39 dBm |
| The antenna connector of the Base Station receiver is the reference point. The reference sensitivity (RefSens) is the minimum mean power received at the antenna connector at which a specified minimum performance shall be met.These requirements cover both blocking and third-order intermodulation. |
(1)GSM-R channel raster of 200 kHz.(2)ACLR: Adjacent Channel Leakage power Ratio.(3)Directive 2014/53/EU of the European Parliament and of the Council of 16 April 2014 on the harmonisation of the laws of the Member States relating to the making available on the market of radio equipment and repealing Directive 1999/5/EC (OJ L 153, 22.5.2014, p. 62).(4)Requirements for RMR terminal receiver other than cab-radio are not covered in this table
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.