Judgment of the General Court (Third Chamber, Extended Composition)8 October 2025note(Energy — Internal market for electricity — Guideline on electricity balancing — Article 1 of Regulation (EU) 2017/2195 — European platform for the imbalance netting process — Non-participation of the Swiss Transmission System Operator — ACER decision amending the Implementation Framework for the Platform — Appeal brought before the ACER Board of Appeal — Specific conditions and arrangements for appeals — Article 28 of Regulation (EU) 2019/942 — Inadmissibility for lack of standing to bring proceedings before the Board of Appeal — Direct and individual concern)In Case T‑556/23,Swissgrid AG, established in Aarau (Switzerland), represented by P. De Baere, P. L’Ecluse, K. T’Syen, V. Lefever and V. Ion, lawyers,vEuropean Union Agency for the Cooperation of Energy Regulators (ACER), represented by P. Martinet and E. Tremmel, acting as Agents, and by B. Creve and T. Kölsch, lawyers,supported byEuropean Commission, represented by O. Beynet, T. Scharf, B. De Meester and C. Hödlmayr, acting as Agents,THE GENERAL COURT (Third Chamber, Extended Composition),composed, at the time of the deliberations, of P. Škvařilová-Pelzl, President, I. Nõmm (Rapporteur), G. Steinfatt, D. Kukovec and R. Meyer, Judges,Registrar: I. Kurme, Administrator,having regard to the written part of the procedure,further to the hearing on 12 March 2025,gives the following
Judgment
Background to the dispute
Forms of order sought
Law
The first plea, alleging an error of law in the interpretation of Regulation 2017/2195
The second plea, alleging an error of assessment in the application of Article 28(1) of Regulation 2019/942 to the circumstances of the present case
Admissibility of the second part, contested by ACER
Examination of the merits of the plea
Costs
Operative part