Contents
Judgment of the General Court (Fifth Chamber)6 November 2024note(State aid — Madeira Free Zone — Aid scheme implemented by Portugal — Decision finding that the scheme does not comply with Decisions C(2007) 3037 final and C(2013) 4043 final, declaring that scheme to be incompatible with the internal market and ordering recovery of aid paid under it — Obligation to state reasons — Concept of existing aid within the meaning of Article 1(b)(ii) of Regulation (EU) 2015/1589 — No derogation from the condition relating to the creation or maintenance of jobs in the Autonomous Region of Madeira — Principle of sound administration — Principle of sincere cooperation — Legitimate expectations — Legal certainty)In Case T‑462/22,Millennium BCP Participações, SGPS, Sociedade Unipessoal, Lda, established in Funchal (Portugal),BCP África, SGPS, Lda, established in Funchal,represented by B. Santiago, L. do Nascimento Ferreira, P. Gouveia e Melo, D. Oda and A. Queiroz Martins, lawyers,vEuropean Commission, represented by I. Barcew and P. Caro de Sousa, acting as Agents,THE GENERAL COURT (Fifth Chamber),composed of J. Svenningsen, President, J. Martín y Pérez de Nanclares (Rapporteur) and M. Stancu, Judges,Registrar: L. Ramette, Administrator,having regard to the written part of the procedure, in particular:– the decision of 17 January 2023 not to stay the proceedings pending the decision of the Court of Justice closing the proceedings in the case which subsequently gave rise to the judgment of 4 July 2024, Portugal v Commission (Madeira Free Zone) (C‑736/22 P, not published, EU:C:2024:579);– the measure of organisation of procedure of 18 July 2023 by which the General Court requested the European Commission to provide the notifications and the correspondence which it exchanged with the Portuguese authorities in the administrative proceedings relating to Cases N 421/2006 and SA.34160 (2011/N);– the replies from the Commission lodged at the Court Registry of the General Court on 28 August 2023 by which it stated that it was unable to communicate the documents by reason of the general presumption of confidentiality which they enjoyed in State aid proceedings;– the order of 26 September 2023 by which the Court requested the production of the documents at issue by way of a measure of inquiry pursuant to Article 91(b) and Article 92(3) of its Rules of Procedure;– the decision of 8 November 2023 by which the Court ruled on the relevance and the absence of confidentiality of the documents produced pursuant to the order of 26 September 2023 given that they were more than five years old and did not contain particularly sensitive data,further to the hearing on 20 February 2024,gives the following
Judgment
Background to the dispute
Forms of order sought
Law
The first plea in law, alleging an infringement of the obligation to state reasons
The second plea in law, alleging an error of law in so far as the Commission included holding companies in the group of beneficiaries covered by the recovery obligation in the event of non-compliance with the condition relating to the creation or maintenance of jobs in the ARM
The subject matter of the second plea in law
Merits of the second plea in law
–The scope of the 2007 decision
–The scope of the 2013 decision
The third plea in law, alleging a breach of the principles of protection of legitimate expectations and legal certainty
The principle of protection of legitimate expectations
The principle of legal certainty
Costs
Operative part
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.