Judgment of the General Court (Third Chamber, Extended Composition)25 September 2024note(Energy — Internal market for electricity — Capacity calculation region — Core region — Adoption by ACER of the methodology for cost sharing of redispatching and countertrading — Determination of the threshold for legitimate loop flows — Article 16(13) of Regulation (EU) 2019/943)In Case T‑485/21,Bundesnetzagentur für Elektrizität, Gas, Telekommunikation, Post und Eisenbahnen (BNetzA), established in Bonn (Germany), represented by U. Karpenstein and K. Reiter, lawyers,supported byFederal Republic of Germany, represented by J. Möller and N. Scheffel, acting as Agents,vEuropean Union Agency for the Cooperation of Energy Regulators (ACER), represented by P. Martinet, Z. Vujasinovic and E. Tremmel, acting as Agents, and by P. Goffinet, L. Bersou and M. Shehu, lawyers,THE GENERAL COURT (Third Chamber, Extended Composition),composed of F. Schalin, President, P. Škvařilová-Pelzl, I. Nõmm, G. Steinfatt and D. Kukovec (Rapporteur), Judges,Registrar: I. Kurme, Administrator,having regard to the written part of the procedure,further to the hearings on 12 and 13 June 2023,gives the following
Judgment
Background to the dispute
Forms of order sought
Law
The first plea, concerning the scope of the contested cost sharing methodology
Preliminary observations
Analysis of scope
–The extent of the scope of the contested cost sharing methodology
–The incentives derived from including internal network elements within the scope of the contested cost sharing methodology
The fourth plea, concerning the prioritisation of loop flows
The third plea, concerning the threshold
Compliance with the requirements of Article 16(13) of Regulation 2019/943
The conditions for recognising implicit competence
Recognition that ACER has implicit competence
Whether the contested decision should be maintained
Costs
Operative part