Judgment of the General Court (Fourth Chamber, Extended Composition)25 October 2023note(Competition — Abuse of a dominant position — Internal market in natural gas — Decision finding an infringement of Article 102 TFEU — Regulated market — Definition of the relevant market — Romanian Transit Pipeline 1 — Holder of an exclusive right to use the Romanian Pipeline 1 — Refusal to grant access — Public supply obligation — State action defence — Transmission system operator — Storage system operator — Anticompetitive strategy — Exclusionary effects — Single and continuous infringement — Rights of the defence)In Case T‑136/19,Bulgarian Energy Holding EAD, established in Sofia (Bulgaria),Bulgartransgaz EAD, established in Sofia,Bulgargaz EAD, established in Sofia,represented by M. Powell, A. Komninos, H. Gafsen and W. De Catelle, lawyers,supported byRepublic of Bulgaria, represented by L. Zaharieva and T. Mitova, acting as Agents,vEuropean Commission, represented by H. van Vliet, G. Meessen, J. Szczodrowski and C. Georgieva, acting as Agents,supported byOvergas Inc., established in Sofia, represented by S. Cappellari and S. Gröss, lawyers,THE GENERAL COURT (Fourth Chamber, Extended Composition),composed, at the time of the deliberations, of S. Gervasoni, President, L. Madise, P. Nihoul, R. Frendo (Rapporteur) and J. Martín y Pérez de Nanclares, Judges,Registrar: I. Kurme, Administrator,having regard to the written part of the procedure,further to the hearing on 29 September 2022,gives the following
JudgmentOnly the paragraphs of the present judgment which the Court considers it appropriate to publish are reproduced here.…
I. Background to the dispute
A. Factual background…
1. Gas supply in Bulgaria
2. Gas supply in Bulgaria
4. The Chiren storage facility
C. Contested decision
II. Forms of order sought
III. Law
A. The second plea in law, alleging a failure to state reasons and errors of law and of fact concerning the definition of the market for capacity services on the Romanian Pipeline 1…
3. The third part, alleging errors of law and errors in the assessment of the facts in the definition of the market for capacity services on the Romanian Pipeline 1
(a)The errors of law and of fact based, respectively, on the argument that the Commission failed to distinguish between the primary and secondary capacity markets on the Romanian Pipeline 1 and did not identify Transgaz as being a supplier of that capacity
(b)The error of fact regarding the identification of Bulgargaz as being a supplier on the Romanian Pipeline 1
B. The third plea in law, alleging an incorrect finding that the applicants held a dominant position on the relevant markets
1. The first part, alleging an incorrect finding that Bulgargaz held a dominant position on the market for capacity services on the Romanian Pipeline 1
(a)The first complaint, alleging that the Commission erred in finding that Bulgargaz controlled third-party access to the Romanian Pipeline 1
(b)The second complaint, alleging that the Commission did not identify Transgaz as being a supplier of capacity services on the Romanian Pipeline 1
C. The fourth plea in law, alleging an incorrect finding of abuse of a dominant position by the applicants
1. Applicable principles and case-law…
(c)The concept of abuse of a dominant position
2. The first ‘sub-plea’, alleging an incorrect finding that access to the Romanian Pipeline 1 was refused…
(b)The second part, alleging an error of law in the application of the essential facilities doctrine in that an abusive refusal to supply was imputed to Bulgargaz, even though the latter was merely a user of the Romanian Pipeline 1
(g)The seventh part, alleging the lack of probative value of the reservation of the entire capacity on the Romanian Pipeline 1
(h)The eighth part, alleging that the discussions relating to the renegotiation of the 2005 Agreement have no probative value
(1)The first complaint, regarding the intergovernmental nature of the renegotiation of the 2005 Agreement
(iii)The central nature of the security of gas supply in Bulgaria and the role of Bulgargaz, as a public supplier, in the renegotiation of the 2005 Agreement
(i)Conclusions on the first ‘sub-plea’
5. Conclusion on the fourth plea
1. The anticompetitive strategy
2.A single and continuous infringement
D. The first plea, alleging substantive procedural defects affecting the exercise of the applicants’ rights of defence and breach of the principle of good administration…
1. The first and second parts, alleging infringement of the obligations to record and place on the file the documents relating to the Commission’s meetings with Overgas, and alleging insufficient access to those documents
2. The existence of procedural defects
(a)The first complaint, alleging a failure properly to record and include in the file the statements made during the meetings with Overgas
(1)The meetings of 2015 and 2016
(2)The meetings of 2010 to 2013
(b)The second complaint, regarding the access to the detailed minutes and to the follow-up observations
(1)The obligation to challenge the redactions in the follow-up observations immediately
(2)The access to the documents made available in the data room and to the excessively redacted versions of the follow-up observations
(c)Conclusion on the procedural defects
3. The effects of the identified errors in terms of the guarantee of the applicants’ rights of defence
(a)The undisclosed elements of the detailed minutes
(b)The undisclosed elements of the follow-up observations
(c)Conclusion on the first and second parts
E. Conclusion on the claim for annulment of the contested decision