Contents
Judgment of the Court (Ninth Chamber)18 November 2020note(Reference for a preliminary ruling — Combating late payments in commercial transactions — Directive 2000/35/EC — Concept of commercial transactions — Concepts of delivery of goods and provision of services — Article 1 and first subparagraph of Article 2(1) — Public works contract)In Case C‑299/19,REQUEST for a preliminary ruling under Article 267 TFEU from the Tribunale ordinario di Torino (District Court, Turin, Italy) made by decision of 9 March 2019, received at the Court on 11 April 2019, in the proceedingsTechbau SpAvAzienda Sanitaria Locale AL,THE COURT (Ninth Chamber),composed of N. Piçarra (Rapporteur), President of the Chamber, S. Rodin and K. Jürimäe, Judges,Advocate General: M. Bobek,Registrar: A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:– Azienda Sanitaria Locale AL, by C. Castellotti, avvocato,– the European Commission, by R. Tricot, G. Gattinara and K. Mifsud-Bonnici, acting as Agents,having decided, after hearing the Advocate General, to proceed to judgment without an Opinion,gives the following
Judgment
Legal context
EU law
Directive 2000/35
Directive 2004/18/EC
Directive 2011/7
Italian law
Legislative Decree No 231
Legislative Decree No 163
Legislative Decree No 192
Law No 161
The facts in the main proceedings and the question referred for a preliminary ruling
Consideration of the question referred
Costs
Operative part
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.