Judgment of the Court (Sixth Chamber)14 May 2020note(Reference for a preliminary ruling — Environment — Scheme for greenhouse gas emission allowance trading in the European Union — Directive 2003/87/EC — Article 10a — Transitional regime for free allocation of allowances — Decision 2011/278/EU — Article 9 — Determination of the historical activity level — Significant change in the capacity of an installation which took place before the baseline period — Determination of the relevant baseline period)In Case C‑189/19,REQUEST for a preliminary ruling under Article 267 TFEU from the Bundesverwaltungsgericht (Federal Administrative Court, Germany), made by decision of 22 November 2018, received at the Court on 26 February 2019, in the proceedingsSpenner GmbH & Co. KGvBundesrepublik Deutschland,THE COURT (Sixth Chamber),composed of M. Safjan, President of the Chamber, J.‑C. Bonichot (Rapporteur), President of the First Chamber, L. Bay Larsen, Judge,Advocate General: H. Saugmandsgaard Øe,Registrar: A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:– Spenner GmbH & Co. KG, by S. Altenschmidt and D. Jacob, Rechtsanwälte,– the German Government, by S. Eisenberg and J. Möller, acting as Agents,– the European Commission, by J.‑F. Brakeland and A.C. Becker, acting as Agents,having decided, after hearing the Advocate General, to proceed to judgment without an Opinion,gives the following
Judgment
Legal context
European Union law
Directive 2003/87
Decision 2011/278
Decision 2013/448/EU
Decision 2017/126
German law
The dispute in the main proceedings and the questions referred for a preliminary ruling
Consideration of the questions referred
The first question
The second question
The third question
The fourth question
Costs
Operative part