29Under those circumstances, the admissibility of the main action cannot, without depriving Directive 89/665 of its effectiveness, be contingent on a prior finding that all of the bids ranked lower than that of the tenderer are invalid. That admissibility cannot, moreover, be made subject to the condition that the tenderer adduces evidence that the contracting authority will have to restart the public procurement procedure. The mere existence of such a possibility must be regarded as being sufficient in that respect.