29It is for the contracting authority to carry out its own evaluation of the economic operator’s conduct covered by the early termination of a prior public contract. In that regard, it must examine, diligently and impartially, on the basis of all the relevant factors, in particular the early termination decision, and in the light of the principle of proportionality, whether that operator is, from its point of view, responsible for significant or persistent deficiencies in the performance of a substantive requirement imposed on it under that contract, those deficiencies being such as to break the relationship of trust with the economic operator in question.