68With regard to the arguments relating to the fact that that agreement involves reciprocal obligations, it is sufficient to note that the grant is not consideration for the realisation of the project forming the subject of the grant agreement. The sums paid by the Commission under that agreement are paid solely in order to allow the beneficiary to meet costs generated by such realisation. As part of those costs were found to be ineligible, as the beneficiary failed to comply with the contractual obligation to substantiate the use of the sums allocated to him, an amount equal to that part of the costs must be recovered by the Commission, and the fact that the beneficiary has in the meantime completed the project that is the subject of the grant agreement does not affect that obligation.