26In that regard, it follows from the Court’s case-law that Directive 2004/17 in fact applies not only to contracts awarded in the sphere of one of the activities expressly listed in Articles 3 to 7 thereof, but also to contracts which, even though they are different in nature and could as such normally fall within the scope of Directive 2004/18/EC of the European Parliament and of the Council of 31 March 2004 on the coordination of procedures for the award of public works contracts, public supply contracts and public service contracts (OJ 2004 L 134, p. 114), are used in the exercise of activities defined in Directive 2004/17. Consequently, where a contract awarded by a contracting entity is connected with an activity which that entity carries out in the sectors listed in Articles 3 to 7 of that directive, that contract is subject to the procedures laid down in that directive (see, to that effect, judgment of 10 April 2008, Ing Aigner, C‑393/06, EU:C:2008:213, paragraphs 56 to 59).