51The Court has thus held, inter alia, that a request for clarification cannot make up for the lack of a document or information whose production was required by the contract documents, the contracting authority being required to comply strictly with the criteria which it has itself laid down (see, to that effect, judgments of 10 October 2013, Manova, C‑336/12, EU:C:2013:647, paragraph 40, and of 11 May 2017, Archus and Gama, C‑131/16, EU:C:2017:358, paragraph 33).