Judgment of the Court (Second Chamber)2 March 2017note*(Reference for a preliminary ruling — Environment — Directive 2009/28/EC — The second subparagraph of Article 2(a) — Energy from renewable sources — Hydropower — Meaning — Energy produced in a small-scale hydropower plant located at the point of discharge of industrial waste water from another plant)In Case C‑4/16,REQUEST for a preliminary ruling under Article 267 TFEU from the Sąd Apelacyjny w Warszawie Wydział Cywilny (Court of Appeal, Warsaw, Civil Division, Poland), made by decision of 1 October 2015, received at the Court on 4 January 2016, in the proceedingsJ. D.vPrezes Urzędu Regulacji Energetyki,THE COURT (Second Chamber),composed of M. Ilešič, President of the Chamber, A. Prechal, A. Rosas, C. Toader and E. Jarašiūnas (Rapporteur), Judges,Advocate General: M. Campos Sánchez-Bordona,Registrar: M. A. Calot Escobar,having regard to the written procedure,after considering the observations submitted on behalf of:— J. D., by T. Gałecki, radca prawny,— the Polish Government, by B. Majczyna, acting as Agent,— the Italian Government, by G. Palmieri, acting as Agent, and by M. P. Garofoli, avvocato dello Stato,— the European Commission, by K. Talabér-Ritz and K. Herrmann, acting as Agents,after hearing the Opinion of the Advocate General at the sitting on 15 November 2016,gives the following
Judgment
Legal context
European Union law
Directive 2009/28
Directive 2003/54
Regulation No 1099/2008
Polish law
The dispute in the main proceedings and the question referred for a preliminary ruling
Consideration of the question referred
Costs
Operative part
Source: EUR-Lex, © European Union, 1998-2026. Reuse authorised under Decision 2011/833/EU.