37According to settled case-law of the Court, in the context of the cooperation between the Court and the national courts provided for by Article 267 TFEU, it is solely for the national court before which the dispute has been brought, and which must assume responsibility for the subsequent judicial decision, to determine, in the light of the particular circumstances of the case, both the need for a preliminary ruling in order to enable it to deliver judgment and the relevance of the questions which it submits to the Court (judgments of 22 December 2008, Les Vergers du Vieux Tauves, C‑48/07, EU:C:2008:758, paragraph 16, and of 21 December 2016, Vervloet and Others, C‑76/15, EU:C:2016:975, paragraph 56 and the case-law cited).