57However, it is apparent from the case-law of the Court that the contracting authority cannot be required to communicate to an unsuccessful tenderer, first, in addition to the reasons for rejecting its tender, a detailed summary of how each detail of its tender was taken into account when the tender was evaluated and, second, in the context of notification of the characteristics and relative advantages of the successful tender, a detailed comparative analysis of the successful tender and of the unsuccessful tender (judgment of 4 October 2012, Evropaïki Dynamiki v Commission, C‑629/11 P, not published, EU:C:2012:617, paragraph 21 and the case-law cited).