30As regards the time from which review procedures must be available, it is appropriate to recall that, as is apparent from its first and second recitals, Directive 89/665 is intended to strengthen the existing mechanisms, both at national and EU levels, to ensure the effective application of the directives relating to public procurement, in particular at a stage when infringements can still be corrected. To that effect, the third subparagraph of Article 1(1) of that directive requires Member States ‘to ensure that … decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible’ (see judgment of 12 December 2002, Universale-Bau and Others, C‑470/99, EU:C:2002:746, paragraph 74).