57Thus, as the Advocate General observed in point 51 of her Opinion, an alternative less restrictive measure which guarantees the achievement of the objective pursued would have been to require the main contractor to indicate in their tender the proportion of the contract that they intend to contract out, the proposed subcontractors and their capacities. It might also be possible for the contracting entity to prohibit tenderers from changing subcontractors if that entity was not able beforehand to verify the identity and capacity of the latter.