40This applies, however, only in case of an explicit reference, which can be controlled by a party applying normal diligence and where it is established that the general conditions containing the jurisdiction clause was actually communicated to the other contracting party (see, to that effect, judgment of 14 December 1976 in Estasis Saloti di Colzani, 24/76, EU:C:1976:177, paragraph 12).